Guidelines and Circulars for Load Shedding

Sr. No. Guidelines and Circulars for Load Shedding Date File
      25 08 hours day time 3-phase power supply to Ag consumers connected on AGLM feeders of substations where solar power projects of capacity 2 to 10 MW are connected and commissioned under Mukhyamantri Sour Krishi Vahini Yojana (MSKVY) in Ch.Sambhajinagar District 29/12/2023
      24 Time Schedule for giving 3-phase power availability to AgLM Scheme feeders for the months of January-2024 to March-2024 29/12/2023
      23 08 hours day time 3-phase power supply to Ag consumers connected on AGLM feeders of substations where solar power projects of capacity 2 to 10 MW are connected and commissioned under “Mukhyamantri Sour Krishi VahiniYojana (MSKVY)” in Dharashiv District 15/12/2023
      22 Time Schedule for giving 3-phase power availability to AgLM Scheme feeders for the months of October-2023 to December-2023 27/09/2023
      21 08 hours day time 3-phase power supply to Ag consumers connected on AGLM feeders of substations where solar power projects of capacity 2 to 10 MW are connected and commissioned under “Mukhyamantri Sour Krishi VahiniYojana (MSKVY)” in Kolhapur District 11/09/2023
      20 Providing 08 hours day time 3-phase power supply to Ag consumers connected on AGLM feeders of substations where solar power projects of capacity 2 to 10 MW are connected and commissioned under “Mukhyamantri Sour Krishi VahiniYojana (MSKVY)” in Satara and Akola Districts 19/07/2023
      19 Time Schedule for giving 3-phase power availability to AgLM Scheme feeders for the months of  July-2023 to Sept-2023 30/06/2023
      18 Providing 08 hours day time 3-phase power supply to Ag consumers connected on AGLM feeders of substations where solar power projects of capacity 2 to 10 MW are connected and commissioned under Mukhyamantri Sour Krishi Vahini Yojana (MSKVY) 31/05/2023
      17 Providing 08 hours’ daytime 3-phase power supply to Ag consumers connected on AGLM feeders of substations where new solar power projects are connected and commissioned under “Mukhyamantri Sour Krishi Vahini Yojana (MSKVY)” 23/03/2023
      16 Providing 08 hours day time 3-phase power supply to Ag consumers connected on AGLM feeders of substations where solar power projects of capacity 2 to 10 MW are connected and commissioned under “Mukhyamantri Sour Krishi Vahini Yojana (MSKVY)” 15/03/2023
      15 Time schedule of 08 hours day time 3-phase power supply to Ag consumers connected on AGLM feeders of substations where solar power projects of capacity 2 to 10 MW are connected and commissioned under “Mukhyamantri Sour Krishi Vahini Yojana (MSKVY)” 30/12/2022
      14 Time schedule of 08 hours day time 3-phase power supply to Ag consumers connected on AGLM feeders of substations where solar power projects of capacity 2 to 10 MW are connected and commissioned under “Mukhyamantri Sour Krishi Vahini Yojana (MSKVY)” 26/07/2022
      13 Circular No. 56: ” Temporary revision in Load Shedding Time Schedule and existing load shedding protocol and detailed guidelines for implementation thereof.” 18/04/2022
      12 Time schedule of 08 hours day time 3- phase power supply to Ag consumers connected on AGLM feeders of substations where solar power projects of capacity 2 to 10 MW are connected and commissioned under “Mukhyamantri Sour Krishi Vahini Yojana (MSKVY)” 08/02/2022
      11 Revised Time Schedule for giving 3 phase availability to Ag Load Management (AGLM) Scheme feeders for the month of November-2021 29/10/2021
      10 Circular No. 55 : Revised Time Schedule for giving 3 phase availability to Ag Load Management (AGLM) Scheme feeders for the month of October-2021 06/10/2021
     09 Time Schedule of 8 hrs day time supply on AG LM feeders under “Mukhyamantri Sour Krishi Vahini Yojana” 13/11/2020
     08 Time schedule of 08 hours day time 3-phase power supply to Ag consumers connected on AGLM feeders of substations where solar power projects of capacity 2 to 10 MW are connected and commissioned under “Mukhyamantri Sour Krishi VahiniYojana (MSKVY)” 02/11/2020
     07 Circular No. 54 : Regarding 3 Phase Availability To AG Load Management (AGLM) Scheme Feeders 29/12/2018
     06 Circular No.53 : Agriculture Load Management (AGLM) 09/10/2018
     05 Circular No. 51 : Revised Load Shedding Time Schedule 04/10/2017
     04 Circular No. 48 : DCL Computation Criteria For Feeders Lying In Naxalite Affected Areas 02/07/2014
     03 Circular No. 47 : Load Shedding Protocol For Single Phasing Scheme Feeders & AG Separated Feeders With SDT 19/06/2014
     02 Circular No. 46 : Load Shedding Protocol 14/01/2013
     01 Guidelines For Feederwise Load Shedding 14/08/2012

Urja