Dashboard for New Service Connections(non AG)

Dashboard for New Service Connections(non AG) pending as on 13-Jul-2025
Application Source New connection(A1) application received Technical Feasibility Done Estimate generated but payment not received Payment received but meter not assigned Total Applications at various stages
Infra not required / Infra Completed Infra required Infra not required / Infra Completed Infra required Infra not required / Infra Completed Infra required
Aaple Sarkar 5 0 0 8 0 0 0 13
MAHAVITARAN 54,937 1,095 2,191 38,467 18,546 24,299 19,003 1,58,538
MAITRI 1,516 42 179 315 746 883 1,307 4,988
Total 56,458 1,137 2,370 38,790 19,292 25,182 20,310 1,63,539