Statistics of LT New Service connections (Non AG) Applications from 01-Jan-2022
Statistics of LT New Service connections (Non AG) Applications Report generated as on 17-Sep-2024 |
||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Financial Year | Region | Zone | Circle | Division | Service | Infra Status | Area | Notified Timeline (Days) | Number Of Applications Received | Number Of Applications Approved | Maximum (Days) | Minimum (Days) | Mean (Days) | Mode (Days) | Median (Days) | Compliance |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1840 | 1840 | 85 | 0 | 6 | 0 | 4 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 16 | 16 | 350 | 6 | 111 | 6 | 74 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1246 | 1246 | 66 | 0 | 5 | 0 | 3 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 292 | 292 | 113 | 0 | 11 | 20 | 11 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1741 | 1741 | 404 | 0 | 38 | 0 | 25 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 6 | 6 | 122 | 13 | 44 | 13 | 34 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 690 | 690 | 421 | 0 | 38 | 0 | 9 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 27 | 27 | 183 | 0 | 78 | 110 | 71 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 667 | 667 | 410 | 0 | 20 | 0 | 9 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 34 | 34 | 314 | 19 | 126 | 140 | 140 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 599 | 599 | 249 | 0 | 27 | 2 | 11 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 5 | 5 | 251 | 1 | 117 | 1 | 119 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1401 | 1401 | 721 | 0 | 48 | 0 | 35 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 5 | 5 | 315 | 38 | 143 | 38 | 76 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 804 | 804 | 247 | 0 | 18 | 0 | 10 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 65 | 65 | 294 | 0 | 175 | 294 | 232 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1388 | 1388 | 874 | 0 | 36 | 0 | 6 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 189 | 189 | 581 | 0 | 121 | 64 | 74 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1272 | 1272 | 445 | 0 | 13 | 0 | 3 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 129 | 129 | 547 | 0 | 25 | 0 | 2 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1194 | 1194 | 513 | 0 | 38 | 0 | 9 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 12 | 12 | 426 | 0 | 139 | 0 | 129 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 730 | 730 | 588 | 0 | 40 | 0 | 11 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 14 | 14 | 545 | 3 | 211 | 545 | 94 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 718 | 718 | 215 | 0 | 55 | 5 | 25 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 816 | 816 | 222 | 0 | 17 | 0 | 6 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 9 | 9 | 204 | 2 | 50 | 2 | 38 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 987 | 987 | 242 | 0 | 57 | 6 | 28 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 6 | 6 | 139 | 33 | 59 | 33 | 46 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 865 | 865 | 209 | 0 | 59 | 0 | 36 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 10 | 10 | 264 | 12 | 92 | 12 | 76 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1703 | 1703 | 457 | 0 | 11 | 0 | 5 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 7 | 7 | 138 | 11 | 40 | 11 | 26 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1161 | 1161 | 529 | 0 | 51 | 11 | 23 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 5 | 5 | 25 | 11 | 22 | 25 | 25 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 902 | 902 | 244 | 0 | 88 | 0 | 93 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 4 | 4 | 83 | 9 | 34 | 9 | 22 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 70 | 70 | 104 | 0 | 42 | 52 | 45 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 1383 | 1383 | 220 | 0 | 16 | 0 | 8 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 478 | 478 | 211 | 0 | 19 | 2 | 13 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 3 | 3 | 55 | 15 | 34 | 15 | 31 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 558 | 558 | 567 | 0 | 26 | 0 | 9 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 643 | 643 | 269 | 0 | 19 | 0 | 3 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 77 | 77 | 812 | 0 | 94 | 16 | 49 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 999 | 999 | 558 | 0 | 36 | 0 | 8 | 100% |
2021-2022 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - II | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 9 | 9 | 806 | 2 | 330 | 2 | 426 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1066 | 1066 | 692 | 0 | 54 | 0 | 45 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 14 | 14 | 389 | 0 | 128 | 0 | 66 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1061 | 1061 | 227 | 0 | 39 | 0 | 28 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 11 | 11 | 91 | 5 | 29 | 16 | 16 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2682 | 2682 | 453 | 0 | 103 | 7 | 91 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 9 | 9 | 740 | 0 | 92 | 0 | 9 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1214 | 1214 | 525 | 0 | 78 | 5 | 93 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 23 | 23 | 524 | 2 | 73 | 2 | 41 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 879 | 879 | 143 | 0 | 57 | 95 | 64 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 526 | 526 | 174 | 7 | 53 | 24 | 24 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 416 | 416 | 184 | 0 | 16 | 3 | 3 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 3 | 3 | 40 | 0 | 22 | 0 | 26 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 362 | 362 | 283 | 0 | 8 | 6 | 5 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 374 | 374 | 188 | 0 | 26 | 31 | 22 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 106 | 106 | 124 | 29 | 77 | 71 | 71 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1899 | 1899 | 286 | 0 | 77 | 119 | 86 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 6 | 6 | 319 | 79 | 145 | 79 | 113 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 2091 | 2091 | 175 | 0 | 62 | 78 | 72 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 2309 | 2309 | 283 | 0 | 38 | 0 | 31 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3810 | 3810 | 183 | 0 | 79 | 101 | 93 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 2 | 2 | 15 | 3 | 9 | 3 | 9 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 4 | 4 | 71 | 14 | 41 | 14 | 39 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 2630 | 2630 | 578 | 0 | 60 | 0 | 65 | 100% |
2021-2022 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 4 | 4 | 80 | 11 | 31 | 11 | 17 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 437 | 437 | 297 | 0 | 69 | 69 | 65 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 46 | 46 | 174 | 0 | 61 | 47 | 64 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 266 | 266 | 167 | 0 | 51 | 110 | 39 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 646 | 646 | 206 | 0 | 27 | 0 | 20 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 11 | 11 | 203 | 6 | 85 | 6 | 49 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 6 | 6 | 185 | 4 | 59 | 4 | 40 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 550 | 550 | 224 | 0 | 27 | 0 | 14 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 11 | 11 | 199 | 16 | 79 | 16 | 64 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 689 | 689 | 435 | 0 | 67 | 17 | 53 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 29 | 29 | 204 | 16 | 100 | 25 | 106 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 616 | 616 | 218 | 0 | 49 | 0 | 46 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 5 | 5 | 62 | 14 | 32 | 14 | 30 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1030 | 1030 | 361 | 0 | 78 | 0 | 84 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 27 | 27 | 428 | 25 | 110 | 50 | 100 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 294 | 294 | 234 | 0 | 67 | 102 | 77 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 1430 | 1430 | 493 | 0 | 69 | 0 | 58 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 13 | 13 | 213 | 23 | 109 | 61 | 62 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 41 | 41 | 616 | 23 | 121 | 112 | 98 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 307 | 307 | 353 | 0 | 68 | 100 | 61 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 6 | 6 | 494 | 35 | 166 | 35 | 117 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 997 | 997 | 258 | 0 | 58 | 4 | 50 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 12 | 12 | 400 | 6 | 120 | 6 | 105 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 505 | 505 | 191 | 0 | 63 | 9 | 58 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 5 | 5 | 256 | 64 | 122 | 64 | 97 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 891 | 891 | 283 | 0 | 18 | 0 | 10 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 17 | 17 | 440 | 24 | 109 | 27 | 57 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1028 | 1028 | 135 | 0 | 16 | 2 | 6 | 100% |
2021-2022 | KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 7 | 7 | 55 | 2 | 30 | 35 | 35 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 936 | 936 | 205 | 0 | 84 | 125 | 94 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 42 | 42 | 169 | 1 | 96 | 123 | 120 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 2664 | 2664 | 525 | 0 | 87 | 44 | 97 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 373 | 373 | 190 | 0 | 78 | 0 | 96 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 27 | 27 | 136 | 3 | 98 | 136 | 114 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1152 | 1152 | 649 | 0 | 61 | 0 | 52 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 1 | 1 | 176 | 176 | 176 | 176 | 176 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2189 | 2189 | 444 | 0 | 90 | 6 | 109 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 26 | 26 | 574 | 1 | 166 | 191 | 172 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2564 | 2564 | 237 | 0 | 87 | 121 | 104 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 22 | 22 | 283 | 3 | 90 | 36 | 38 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 407 | 407 | 275 | 0 | 52 | 0 | 17 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 1208 | 1208 | 202 | 0 | 98 | 116 | 114 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 1 | 1 | 14 | 14 | 14 | 14 | 14 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4256 | 4256 | 301 | 0 | 90 | 0 | 104 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 56 | 56 | 256 | 0 | 91 | 148 | 85 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 455 | 455 | 720 | 0 | 62 | 0 | 20 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 4993 | 4993 | 392 | 0 | 59 | 0 | 43 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 14 | 14 | 209 | 1 | 56 | 1 | 31 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 20 | 20 | 1 | 0 | 0 | 0 | 0 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 4690 | 4690 | 242 | 0 | 78 | 0 | 101 | 100% |
2021-2022 | KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 35 | 35 | 209 | 7 | 100 | 98 | 98 | 100% |
2021-2022 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 726 | 726 | 439 | 0 | 31 | 18 | 16 | 100% |
2021-2022 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 42 | 42 | 478 | 3 | 126 | 117 | 114 | 100% |
2021-2022 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 914 | 914 | 245 | 0 | 37 | 3 | 19 | 100% |
2021-2022 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 53 | 53 | 714 | 0 | 99 | 4 | 32 | 100% |
2021-2022 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1456 | 1456 | 316 | 0 | 36 | 0 | 12 | 100% |
2021-2022 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 56 | 56 | 580 | 0 | 92 | 3 | 16 | 100% |
2021-2022 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 781 | 781 | 432 | 0 | 17 | 2 | 4 | 100% |
2021-2022 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 63 | 63 | 604 | 0 | 87 | 0 | 34 | 100% |
2021-2022 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 748 | 748 | 734 | 0 | 28 | 0 | 15 | 100% |
2021-2022 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 40 | 40 | 515 | 0 | 80 | 25 | 43 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 771 | 771 | 308 | 0 | 94 | 0 | 96 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 28 | 28 | 259 | 18 | 103 | 199 | 68 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 587 | 587 | 274 | 0 | 95 | 64 | 91 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 1322 | 1322 | 484 | 0 | 31 | 0 | 10 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 41 | 41 | 325 | 1 | 87 | 37 | 50 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 20 | 20 | 209 | 0 | 92 | 38 | 77 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 773 | 773 | 697 | 0 | 70 | 0 | 53 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 24 | 24 | 469 | 1 | 88 | 23 | 36 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1679 | 1679 | 818 | 0 | 98 | 115 | 110 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 44 | 44 | 754 | 0 | 112 | 15 | 97 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 668 | 668 | 305 | 0 | 86 | 0 | 89 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 26 | 26 | 287 | 0 | 87 | 0 | 52 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 412 | 412 | 209 | 0 | 52 | 6 | 25 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 14 | 14 | 235 | 2 | 83 | 7 | 75 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 157 | 157 | 158 | 0 | 20 | 0 | 7 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 151 | 151 | 513 | 0 | 76 | 0 | 21 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 16 | 16 | 204 | 0 | 43 | 20 | 22 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 2 | 2 | 167 | 147 | 157 | 147 | 157 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 649 | 649 | 246 | 0 | 41 | 0 | 7 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 11 | 11 | 162 | 2 | 80 | 132 | 89 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 290 | 290 | 311 | 0 | 20 | 0 | 10 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 12 | 12 | 482 | 0 | 143 | 0 | 159 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 693 | 693 | 422 | 0 | 68 | 0 | 64 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 38 | 38 | 585 | 0 | 106 | 55 | 90 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1514 | 1514 | 458 | 0 | 88 | 0 | 101 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 85 | 85 | 567 | 0 | 110 | 0 | 98 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1309 | 1309 | 173 | 0 | 51 | 0 | 34 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 16 | 16 | 164 | 0 | 33 | 0 | 6 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 3289 | 3289 | 259 | 0 | 59 | 0 | 68 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1247 | 1247 | 288 | 0 | 67 | 0 | 81 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 50 | 50 | 217 | 0 | 86 | 113 | 113 | 100% |
2021-2022 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 31 | 31 | 388 | 0 | 77 | 0 | 48 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 755 | 755 | 653 | 0 | 70 | 0 | 53 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 18 | 18 | 231 | 1 | 79 | 123 | 66 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 878 | 878 | 760 | 0 | 54 | 0 | 26 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 12 | 12 | 158 | 0 | 67 | 0 | 54 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 316 | 316 | 444 | 0 | 84 | 0 | 64 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 7 | 7 | 267 | 45 | 164 | 45 | 194 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 900 | 900 | 822 | 0 | 89 | 1 | 78 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 37 | 37 | 577 | 0 | 99 | 83 | 83 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1322 | 1322 | 662 | 0 | 82 | 0 | 75 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 24 | 24 | 322 | 0 | 71 | 35 | 36 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 600 | 600 | 430 | 0 | 91 | 1 | 83 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 13 | 13 | 456 | 1 | 92 | 1 | 55 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 962 | 962 | 704 | 0 | 89 | 0 | 76 | 100% |
2021-2022 | NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 19 | 19 | 521 | 0 | 171 | 4 | 163 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1003 | 1003 | 272 | 0 | 52 | 0 | 37 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 10 | 10 | 362 | 0 | 113 | 0 | 89 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 681 | 681 | 786 | 0 | 70 | 102 | 71 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 36 | 36 | 622 | 4 | 169 | 108 | 108 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1052 | 1052 | 676 | 0 | 77 | 0 | 70 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 82 | 82 | 829 | 0 | 231 | 272 | 219 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MURSHI DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 465 | 465 | 143 | 0 | 43 | 1 | 31 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MURSHI DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 23 | 23 | 405 | 2 | 83 | 32 | 72 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 852 | 852 | 371 | 0 | 78 | 105 | 78 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 10 | 10 | 562 | 0 | 160 | 0 | 104 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 821 | 821 | 326 | 0 | 57 | 76 | 60 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 7 | 7 | 153 | 13 | 57 | 13 | 36 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1036 | 1036 | 533 | 0 | 102 | 136 | 109 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 15 | 15 | 167 | 22 | 53 | 33 | 33 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 768 | 768 | 583 | 0 | 73 | 78 | 76 | 100% |
2021-2022 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 7 | 7 | 464 | 70 | 226 | 227 | 227 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 605 | 605 | 349 | 0 | 72 | 0 | 74 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 19 | 19 | 431 | 19 | 257 | 400 | 400 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 308 | 308 | 289 | 0 | 53 | 0 | 37 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 427 | 427 | 228 | 0 | 38 | 2 | 21 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 5 | 5 | 68 | 0 | 25 | 0 | 10 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 2 | 2 | 116 | 11 | 64 | 11 | 64 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 561 | 561 | 218 | 0 | 64 | 11 | 56 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 6 | 6 | 834 | 20 | 323 | 20 | 263 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 450 | 450 | 580 | 0 | 74 | 0 | 32 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 17 | 17 | 176 | 0 | 96 | 107 | 107 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 334 | 334 | 210 | 0 | 67 | 4 | 55 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 2 | 2 | 16 | 2 | 9 | 2 | 9 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 416 | 416 | 226 | 0 | 88 | 2 | 77 | 100% |
2021-2022 | NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 10 | 10 | 486 | 6 | 112 | 6 | 72 | 100% |
2021-2022 | NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1082 | 1082 | 341 | 0 | 25 | 0 | 5 | 100% |
2021-2022 | NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 41 | 41 | 545 | 0 | 86 | 0 | 16 | 100% |
2021-2022 | NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 310 | 310 | 95 | 0 | 10 | 0 | 5 | 100% |
2021-2022 | NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 22 | 22 | 195 | 0 | 67 | 94 | 75 | 100% |
2021-2022 | NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 391 | 391 | 218 | 0 | 17 | 0 | 4 | 100% |
2021-2022 | NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 29 | 29 | 630 | 0 | 115 | 0 | 61 | 100% |
2021-2022 | NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 774 | 774 | 131 | 0 | 19 | 0 | 10 | 100% |
2021-2022 | NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 35 | 35 | 73 | 0 | 16 | 4 | 10 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 420 | 420 | 175 | 0 | 19 | 2 | 9 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 13 | 13 | 643 | 0 | 69 | 1 | 13 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1701 | 1701 | 655 | 0 | 62 | 0 | 63 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 18 | 18 | 236 | 1 | 128 | 125 | 125 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 758 | 758 | 206 | 0 | 34 | 28 | 29 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 25 | 25 | 658 | 0 | 50 | 11 | 21 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 598 | 598 | 207 | 0 | 39 | 0 | 38 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 18 | 18 | 323 | 15 | 98 | 110 | 108 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 229 | 229 | 105 | 0 | 19 | 0 | 8 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 766 | 766 | 210 | 0 | 53 | 5 | 57 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 35 | 35 | 68 | 9 | 36 | 40 | 40 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 24 | 24 | 122 | 3 | 50 | 45 | 45 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1351 | 1351 | 439 | 0 | 36 | 0 | 24 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 11 | 11 | 318 | 24 | 73 | 53 | 53 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 572 | 572 | 454 | 0 | 31 | 0 | 16 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1210 | 1210 | 707 | 0 | 46 | 0 | 32 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 4 | 4 | 10 | 10 | 10 | 10 | 10 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 3 | 3 | 125 | 18 | 54 | 18 | 20 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1121 | 1121 | 211 | 0 | 12 | 0 | 6 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 1 | 1 | 50 | 50 | 50 | 50 | 50 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1632 | 1632 | 294 | 0 | 44 | 0 | 38 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 353 | 353 | 181 | 0 | 20 | 1 | 11 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 16 | 16 | 137 | 0 | 32 | 0 | 17 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 473 | 473 | 461 | 0 | 13 | 0 | 4 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 22 | 22 | 631 | 0 | 142 | 6 | 60 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 827 | 827 | 233 | 0 | 36 | 0 | 26 | 100% |
2021-2022 | NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 31 | 31 | 146 | 0 | 40 | 42 | 42 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1475 | 1475 | 533 | 0 | 75 | 44 | 64 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 48 | 48 | 794 | 0 | 100 | 0 | 49 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1527 | 1527 | 893 | 0 | 89 | 0 | 98 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 121 | 121 | 591 | 3 | 169 | 265 | 119 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 746 | 746 | 224 | 0 | 60 | 0 | 58 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 55 | 55 | 259 | 0 | 88 | 69 | 69 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1341 | 1341 | 370 | 0 | 44 | 0 | 29 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 34 | 34 | 432 | 0 | 101 | 82 | 73 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 893 | 893 | 355 | 0 | 56 | 0 | 48 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 46 | 46 | 610 | 0 | 73 | 26 | 32 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1287 | 1287 | 328 | 0 | 46 | 0 | 37 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 128 | 128 | 868 | 2 | 251 | 139 | 146 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 512 | 512 | 770 | 0 | 64 | 0 | 52 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 27 | 27 | 657 | 0 | 165 | 1 | 127 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 428 | 428 | 172 | 0 | 51 | 0 | 46 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 36 | 36 | 711 | 3 | 102 | 15 | 62 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 501 | 501 | 365 | 0 | 105 | 135 | 118 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 16 | 16 | 598 | 17 | 149 | 151 | 110 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1425 | 1425 | 307 | 0 | 97 | 0 | 105 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 42 | 42 | 849 | 0 | 194 | 198 | 131 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1074 | 1074 | 369 | 0 | 74 | 0 | 66 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 94 | 94 | 645 | 0 | 173 | 0 | 113 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1217 | 1217 | 701 | 0 | 96 | 106 | 103 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 51 | 51 | 642 | 1 | 360 | 620 | 516 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 1151 | 1151 | 719 | 0 | 51 | 4 | 36 | 100% |
2021-2022 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 36 | 36 | 68 | 0 | 44 | 68 | 39 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 759 | 759 | 294 | 0 | 37 | 2 | 27 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 130 | 130 | 620 | 1 | 263 | 189 | 290 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 268 | 268 | 78 | 0 | 13 | 0 | 6 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 670 | 670 | 325 | 0 | 17 | 0 | 7 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 10 | 10 | 296 | 32 | 164 | 32 | 144 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 19 | 19 | 314 | 62 | 172 | 203 | 203 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 792 | 792 | 351 | 0 | 24 | 0 | 11 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 50 | 50 | 540 | 4 | 160 | 10 | 67 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1259 | 1259 | 785 | 0 | 43 | 0 | 40 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 29 | 29 | 460 | 1 | 137 | 59 | 63 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1550 | 1550 | 463 | 0 | 32 | 0 | 29 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 94 | 94 | 827 | 4 | 97 | 63 | 69 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 1125 | 1125 | 256 | 0 | 21 | 0 | 9 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 29 | 29 | 265 | 1 | 172 | 237 | 237 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 661 | 661 | 335 | 0 | 25 | 1 | 18 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 20 | 20 | 420 | 9 | 81 | 9 | 47 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 482 | 482 | 566 | 0 | 30 | 0 | 9 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 105 | 105 | 664 | 0 | 118 | 0 | 11 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 673 | 673 | 209 | 0 | 29 | 0 | 19 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 24 | 24 | 530 | 1 | 93 | 1 | 55 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 821 | 821 | 302 | 0 | 13 | 0 | 5 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 24 | 24 | 174 | 0 | 43 | 18 | 18 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 992 | 992 | 435 | 0 | 29 | 0 | 10 | 100% |
2021-2022 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 54 | 54 | 894 | 0 | 291 | 0 | 133 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 3642 | 3642 | 484 | 0 | 31 | 21 | 22 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 12 | 12 | 481 | 103 | 447 | 480 | 480 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 859 | 859 | 128 | 0 | 27 | 3 | 19 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 160 | 160 | 126 | 1 | 47 | 44 | 37 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 4130 | 4130 | 355 | 0 | 39 | 7 | 34 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 159 | 159 | 626 | 8 | 266 | 385 | 384 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1567 | 1567 | 172 | 0 | 21 | 20 | 19 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 8 | 8 | 230 | 125 | 138 | 125 | 125 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 822 | 822 | 252 | 0 | 66 | 86 | 74 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 52 | 52 | 858 | 4 | 218 | 9 | 122 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4522 | 4522 | 582 | 0 | 65 | 0 | 80 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 78 | 78 | 482 | 3 | 224 | 466 | 145 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3634 | 3634 | 269 | 0 | 67 | 0 | 75 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 51 | 51 | 384 | 0 | 69 | 7 | 17 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 2124 | 2124 | 339 | 0 | 48 | 55 | 55 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 2 | 2 | 10 | 7 | 9 | 7 | 9 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1477 | 1477 | 189 | 0 | 53 | 0 | 62 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 2 | 2 | 28 | 7 | 18 | 7 | 18 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1995 | 1995 | 652 | 0 | 56 | 0 | 54 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 23 | 23 | 69 | 24 | 54 | 69 | 69 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1065 | 1065 | 201 | 0 | 51 | 12 | 48 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 6 | 6 | 265 | 7 | 186 | 265 | 265 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 649 | 649 | 364 | 0 | 24 | 0 | 9 | 100% |
2021-2022 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 31 | 31 | 137 | 5 | 78 | 137 | 137 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 9120 | 9120 | 605 | 0 | 22 | 1 | 18 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 129 | 129 | 277 | 0 | 96 | 97 | 97 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 5320 | 5320 | 600 | 0 | 17 | 0 | 10 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 555 | 555 | 235 | 0 | 14 | 0 | 5 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 8479 | 8479 | 395 | 0 | 46 | 0 | 36 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 166 | 166 | 422 | 0 | 96 | 98 | 69 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3912 | 3912 | 746 | 0 | 41 | 0 | 24 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 120 | 120 | 503 | 0 | 86 | 63 | 57 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3737 | 3737 | 545 | 0 | 35 | 0 | 25 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 87 | 87 | 452 | 0 | 100 | 0 | 41 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3406 | 3406 | 630 | 0 | 31 | 24 | 24 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 26 | 26 | 278 | 1 | 56 | 1 | 27 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6483 | 6483 | 705 | 0 | 45 | 0 | 30 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 72 | 72 | 446 | 0 | 90 | 196 | 58 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3789 | 3789 | 304 | 0 | 19 | 0 | 10 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 79 | 79 | 251 | 0 | 91 | 251 | 55 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5089 | 5089 | 781 | 0 | 37 | 0 | 18 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 671 | 670 | 659 | 0 | 85 | 0 | 35 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6147 | 6147 | 468 | 0 | 40 | 0 | 19 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 572 | 572 | 531 | 0 | 42 | 0 | 8 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5584 | 5584 | 737 | 0 | 50 | 0 | 27 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 83 | 78 | 717 | 0 | 134 | 14 | 66 | 94% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3486 | 3486 | 450 | 0 | 43 | 0 | 17 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 90 | 90 | 515 | 0 | 146 | 515 | 83 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3790 | 3790 | 281 | 0 | 48 | 35 | 38 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 4260 | 4260 | 433 | 0 | 20 | 0 | 10 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 47 | 47 | 147 | 1 | 44 | 4 | 24 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 2 | 2 | 46 | 7 | 27 | 7 | 27 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4038 | 4038 | 468 | 0 | 57 | 7 | 44 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 46 | 46 | 498 | 1 | 63 | 31 | 37 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4830 | 4830 | 364 | 0 | 51 | 0 | 39 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 57 | 57 | 383 | 0 | 59 | 2 | 42 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6514 | 6514 | 558 | 0 | 27 | 0 | 17 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 78 | 78 | 322 | 0 | 62 | 64 | 53 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4466 | 4466 | 329 | 0 | 56 | 41 | 47 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 20 | 20 | 469 | 3 | 71 | 31 | 53 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4905 | 4905 | 645 | 0 | 48 | 0 | 38 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 18 | 18 | 353 | 0 | 77 | 6 | 43 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 411 | 411 | 295 | 0 | 50 | 17 | 40 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 8501 | 8501 | 619 | 0 | 19 | 3 | 13 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 7 | 7 | 184 | 19 | 73 | 19 | 52 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 35 | 35 | 87 | 4 | 50 | 38 | 50 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3108 | 3108 | 648 | 0 | 43 | 42 | 34 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 12 | 12 | 160 | 11 | 62 | 81 | 62 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2265 | 2265 | 370 | 0 | 37 | 0 | 20 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 3078 | 3078 | 511 | 0 | 19 | 0 | 10 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 78 | 78 | 619 | 10 | 162 | 181 | 136 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 6 | 6 | 132 | 3 | 69 | 3 | 72 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4498 | 4498 | 772 | 0 | 36 | 0 | 14 | 100% |
2022-2023 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - II | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 42 | 42 | 501 | 0 | 143 | 0 | 112 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6006 | 6006 | 487 | 0 | 34 | 0 | 24 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 134 | 134 | 386 | 0 | 46 | 0 | 11 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5169 | 5169 | 510 | 0 | 31 | 0 | 22 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 146 | 146 | 242 | 0 | 53 | 38 | 33 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 17262 | 17262 | 710 | 0 | 59 | 14 | 53 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 45 | 45 | 117 | 0 | 33 | 8 | 28 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5593 | 5593 | 488 | 0 | 42 | 0 | 38 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 61 | 61 | 250 | 0 | 39 | 1 | 15 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 4437 | 4437 | 255 | 0 | 26 | 13 | 21 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 52 | 52 | 37 | 2 | 20 | 20 | 20 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 4622 | 4622 | 250 | 0 | 31 | 27 | 22 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 72 | 72 | 232 | 1 | 15 | 10 | 10 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1787 | 1787 | 288 | 0 | 22 | 8 | 16 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 21 | 21 | 444 | 22 | 340 | 443 | 443 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 3869 | 3869 | 211 | 0 | 32 | 35 | 29 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 546 | 546 | 370 | 4 | 81 | 82 | 58 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 10831 | 10831 | 252 | 0 | 34 | 21 | 28 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 105 | 105 | 434 | 5 | 103 | 106 | 106 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 12274 | 12274 | 403 | 0 | 35 | 0 | 29 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 13 | 13 | 138 | 1 | 88 | 122 | 122 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 9852 | 9852 | 375 | 0 | 27 | 0 | 20 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 18401 | 18401 | 530 | 0 | 39 | 23 | 34 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 197 | 197 | 79 | 0 | 34 | 40 | 34 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 16 | 16 | 611 | 2 | 86 | 2 | 20 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 16066 | 16066 | 537 | 0 | 38 | 16 | 32 | 100% |
2022-2023 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 97 | 97 | 550 | 0 | 41 | 18 | 19 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3855 | 3855 | 449 | 0 | 44 | 0 | 31 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 299 | 299 | 430 | 0 | 40 | 9 | 17 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1780 | 1780 | 302 | 0 | 31 | 4 | 20 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 3527 | 3527 | 490 | 0 | 27 | 0 | 11 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 67 | 67 | 220 | 1 | 54 | 28 | 44 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 30 | 30 | 279 | 1 | 54 | 56 | 38 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3505 | 3505 | 337 | 0 | 23 | 0 | 12 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 67 | 67 | 428 | 0 | 90 | 2 | 66 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3723 | 3723 | 460 | 0 | 51 | 30 | 43 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 156 | 156 | 613 | 1 | 125 | 35 | 94 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4152 | 4152 | 340 | 0 | 44 | 4 | 38 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 83 | 83 | 273 | 2 | 57 | 51 | 48 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5240 | 5240 | 491 | 0 | 44 | 42 | 36 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 115 | 114 | 499 | 1 | 77 | 7 | 56 | 99% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1655 | 1655 | 437 | 0 | 60 | 52 | 52 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 4968 | 4968 | 488 | 0 | 43 | 0 | 35 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 43 | 43 | 697 | 7 | 112 | 37 | 75 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 181 | 181 | 298 | 1 | 98 | 120 | 87 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1334 | 1334 | 381 | 0 | 53 | 0 | 45 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 42 | 42 | 268 | 0 | 103 | 0 | 83 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5386 | 5386 | 620 | 0 | 50 | 41 | 42 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 84 | 84 | 337 | 1 | 78 | 2 | 50 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2564 | 2564 | 660 | 0 | 53 | 41 | 43 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 61 | 61 | 350 | 0 | 74 | 33 | 51 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3972 | 3972 | 649 | 0 | 18 | 5 | 13 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 100 | 100 | 535 | 3 | 92 | 88 | 83 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3489 | 3489 | 273 | 0 | 7 | 0 | 4 | 100% |
2022-2023 | KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 31 | 31 | 148 | 0 | 24 | 17 | 17 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 4656 | 4656 | 151 | 0 | 30 | 0 | 26 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 1239 | 1239 | 168 | 0 | 37 | 20 | 31 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 16572 | 16572 | 504 | 0 | 38 | 23 | 30 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 2446 | 2446 | 287 | 0 | 31 | 46 | 25 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 376 | 376 | 86 | 2 | 37 | 56 | 34 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 160 | 160 | 57 | 0 | 23 | 16 | 16 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 7130 | 7130 | 379 | 0 | 32 | 28 | 25 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 26 | 26 | 288 | 7 | 167 | 240 | 227 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 12721 | 12721 | 342 | 0 | 53 | 0 | 49 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 602 | 602 | 421 | 1 | 87 | 123 | 57 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 14126 | 14126 | 422 | 0 | 37 | 8 | 29 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 61 | 61 | 439 | 0 | 59 | 7 | 22 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 2363 | 2363 | 350 | 0 | 32 | 0 | 21 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 8271 | 8271 | 462 | 0 | 38 | 24 | 35 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 32 | 32 | 274 | 8 | 82 | 15 | 15 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 22638 | 22638 | 665 | 0 | 36 | 0 | 29 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 270 | 270 | 490 | 0 | 73 | 41 | 50 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2566 | 2566 | 321 | 0 | 41 | 0 | 26 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 28022 | 28022 | 322 | 0 | 32 | 0 | 24 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 67 | 67 | 318 | 0 | 67 | 2 | 47 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 171 | 171 | 246 | 7 | 112 | 191 | 86 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 24410 | 24410 | 592 | 0 | 36 | 0 | 31 | 100% |
2022-2023 | KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 240 | 240 | 284 | 1 | 88 | 74 | 74 | 100% |
2022-2023 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3836 | 3836 | 304 | 0 | 44 | 4 | 33 | 100% |
2022-2023 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 239 | 239 | 742 | 0 | 114 | 50 | 84 | 100% |
2022-2023 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4474 | 4474 | 320 | 0 | 33 | 2 | 22 | 100% |
2022-2023 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 322 | 322 | 600 | 0 | 135 | 3 | 86 | 100% |
2022-2023 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 7373 | 7373 | 859 | 0 | 33 | 0 | 21 | 100% |
2022-2023 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 612 | 612 | 640 | 0 | 118 | 143 | 86 | 100% |
2022-2023 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4696 | 4696 | 589 | 0 | 27 | 0 | 16 | 100% |
2022-2023 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 485 | 485 | 509 | 0 | 79 | 0 | 48 | 100% |
2022-2023 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4553 | 4553 | 465 | 0 | 22 | 12 | 18 | 100% |
2022-2023 | KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 231 | 231 | 609 | 0 | 77 | 7 | 36 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 7090 | 7090 | 453 | 0 | 54 | 0 | 43 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 249 | 249 | 457 | 0 | 107 | 173 | 75 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3788 | 3788 | 366 | 0 | 55 | 7 | 41 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 7296 | 7296 | 442 | 0 | 27 | 0 | 11 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 245 | 245 | 576 | 1 | 93 | 36 | 66 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 126 | 126 | 441 | 0 | 91 | 204 | 59 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4091 | 4091 | 419 | 0 | 50 | 0 | 39 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 128 | 128 | 581 | 6 | 118 | 6 | 75 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 8961 | 8961 | 447 | 0 | 50 | 44 | 43 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 288 | 288 | 427 | 0 | 80 | 161 | 70 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3718 | 3718 | 409 | 0 | 61 | 0 | 51 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 178 | 178 | 522 | 1 | 76 | 69 | 59 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1517 | 1517 | 301 | 0 | 23 | 3 | 13 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 123 | 123 | 449 | 0 | 83 | 44 | 44 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1432 | 1432 | 294 | 0 | 48 | 6 | 35 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 875 | 875 | 454 | 0 | 69 | 38 | 48 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 83 | 83 | 455 | 0 | 70 | 37 | 37 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 47 | 47 | 160 | 0 | 51 | 5 | 39 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2678 | 2678 | 492 | 0 | 42 | 0 | 32 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 182 | 182 | 483 | 0 | 57 | 67 | 48 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1417 | 1417 | 264 | 0 | 20 | 0 | 12 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 217 | 217 | 328 | 0 | 47 | 35 | 35 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3849 | 3849 | 350 | 0 | 32 | 0 | 22 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 241 | 241 | 614 | 0 | 86 | 10 | 47 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 7352 | 7352 | 523 | 0 | 38 | 0 | 27 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 833 | 833 | 790 | 0 | 92 | 8 | 66 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 7676 | 7676 | 173 | 0 | 27 | 0 | 23 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 107 | 107 | 146 | 0 | 36 | 32 | 32 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 16716 | 16716 | 472 | 0 | 29 | 0 | 27 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 7841 | 7841 | 306 | 0 | 30 | 0 | 25 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 112 | 112 | 353 | 0 | 60 | 29 | 43 | 100% |
2022-2023 | KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 238 | 238 | 437 | 0 | 63 | 73 | 45 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5074 | 5074 | 619 | 0 | 44 | 0 | 34 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 188 | 188 | 584 | 0 | 163 | 457 | 134 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 4852 | 4852 | 567 | 0 | 36 | 0 | 22 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 313 | 313 | 625 | 0 | 141 | 33 | 125 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2615 | 2615 | 621 | 0 | 41 | 0 | 24 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 84 | 84 | 769 | 0 | 164 | 239 | 121 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5719 | 5719 | 791 | 0 | 41 | 0 | 26 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 257 | 257 | 772 | 0 | 92 | 0 | 39 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5977 | 5977 | 640 | 0 | 52 | 0 | 34 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 277 | 277 | 676 | 0 | 143 | 0 | 96 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3978 | 3978 | 598 | 0 | 55 | 0 | 45 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 129 | 129 | 682 | 1 | 105 | 250 | 61 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 8711 | 8711 | 748 | 0 | 40 | 0 | 24 | 100% |
2022-2023 | NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 296 | 296 | 718 | 0 | 166 | 24 | 98 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6112 | 6112 | 504 | 0 | 41 | 0 | 36 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 168 | 167 | 812 | 0 | 174 | 722 | 109 | 99% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4212 | 4212 | 757 | 0 | 52 | 43 | 47 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 286 | 285 | 753 | 3 | 223 | 398 | 181 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 8275 | 8275 | 854 | 0 | 45 | 0 | 31 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 508 | 507 | 710 | 0 | 170 | 88 | 115 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MURSHI DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2903 | 2903 | 381 | 0 | 36 | 1 | 29 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MURSHI DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 150 | 150 | 637 | 0 | 94 | 1 | 76 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3743 | 3743 | 458 | 0 | 48 | 20 | 39 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 46 | 46 | 797 | 7 | 126 | 14 | 59 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4498 | 4498 | 606 | 0 | 39 | 27 | 33 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 104 | 104 | 722 | 2 | 182 | 259 | 168 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5508 | 5508 | 695 | 0 | 60 | 43 | 50 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 42 | 42 | 355 | 0 | 136 | 340 | 94 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3675 | 3675 | 510 | 0 | 42 | 16 | 31 | 100% |
2022-2023 | NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 85 | 85 | 628 | 0 | 166 | 625 | 78 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3739 | 3739 | 731 | 0 | 40 | 0 | 31 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 60 | 60 | 416 | 1 | 123 | 14 | 94 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2382 | 2382 | 541 | 0 | 41 | 0 | 27 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 2825 | 2825 | 404 | 0 | 27 | 0 | 15 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 44 | 44 | 389 | 0 | 98 | 229 | 50 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 83 | 83 | 506 | 0 | 145 | 0 | 59 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3325 | 3325 | 449 | 0 | 48 | 46 | 42 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 53 | 53 | 393 | 10 | 155 | 105 | 131 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3049 | 3049 | 822 | 0 | 49 | 0 | 36 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 29 | 29 | 525 | 4 | 93 | 21 | 58 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2407 | 2407 | 217 | 0 | 34 | 14 | 27 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 61 | 61 | 496 | 0 | 95 | 35 | 59 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3448 | 3448 | 419 | 0 | 49 | 0 | 32 | 100% |
2022-2023 | NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 88 | 88 | 654 | 1 | 105 | 7 | 74 | 100% |
2022-2023 | NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6033 | 6033 | 336 | 0 | 23 | 0 | 13 | 100% |
2022-2023 | NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 216 | 215 | 728 | 0 | 193 | 0 | 85 | 100% |
2022-2023 | NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2093 | 2093 | 197 | 0 | 11 | 2 | 6 | 100% |
2022-2023 | NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 77 | 77 | 667 | 0 | 119 | 4 | 57 | 100% |
2022-2023 | NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2741 | 2741 | 312 | 0 | 19 | 0 | 12 | 100% |
2022-2023 | NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 162 | 162 | 595 | 0 | 165 | 595 | 112 | 100% |
2022-2023 | NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5245 | 5245 | 454 | 0 | 22 | 0 | 17 | 100% |
2022-2023 | NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 192 | 192 | 582 | 0 | 110 | 582 | 38 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2246 | 2246 | 333 | 0 | 23 | 2 | 19 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 159 | 159 | 409 | 0 | 48 | 38 | 38 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 8021 | 8021 | 448 | 0 | 36 | 0 | 29 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 107 | 107 | 313 | 0 | 69 | 1 | 41 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3921 | 3921 | 420 | 0 | 30 | 0 | 24 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 118 | 118 | 478 | 0 | 52 | 4 | 22 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2928 | 2928 | 365 | 0 | 35 | 4 | 28 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 70 | 70 | 489 | 4 | 73 | 4 | 42 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 843 | 843 | 256 | 0 | 10 | 0 | 4 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5714 | 5714 | 397 | 0 | 27 | 0 | 17 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 20 | 20 | 116 | 8 | 43 | 26 | 31 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 394 | 394 | 399 | 0 | 209 | 260 | 246 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 7244 | 7244 | 611 | 0 | 27 | 4 | 16 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 122 | 122 | 302 | 1 | 43 | 2 | 14 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 3427 | 3427 | 498 | 0 | 23 | 0 | 9 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6513 | 6513 | 551 | 0 | 36 | 0 | 26 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 81 | 81 | 490 | 3 | 227 | 17 | 108 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 154 | 154 | 417 | 0 | 60 | 62 | 54 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 6016 | 6016 | 431 | 0 | 28 | 0 | 21 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 60 | 60 | 308 | 3 | 133 | 308 | 130 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 8935 | 8935 | 558 | 0 | 28 | 0 | 21 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 160 | 160 | 665 | 0 | 215 | 66 | 101 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2558 | 2558 | 278 | 0 | 20 | 7 | 15 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 127 | 127 | 309 | 2 | 63 | 38 | 46 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2390 | 2390 | 375 | 0 | 25 | 0 | 18 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 78 | 78 | 455 | 0 | 127 | 69 | 74 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4804 | 4804 | 467 | 0 | 23 | 0 | 15 | 100% |
2022-2023 | NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 373 | 373 | 391 | 0 | 88 | 100 | 99 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 8067 | 8067 | 313 | 0 | 35 | 0 | 25 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 398 | 397 | 750 | 0 | 89 | 7 | 58 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 8957 | 8957 | 846 | 0 | 52 | 1 | 41 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 412 | 412 | 620 | 0 | 136 | 97 | 97 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3748 | 3748 | 522 | 0 | 37 | 0 | 21 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 326 | 326 | 537 | 0 | 94 | 50 | 70 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 8088 | 8088 | 805 | 0 | 31 | 0 | 21 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 282 | 282 | 531 | 0 | 70 | 27 | 36 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4807 | 4807 | 727 | 0 | 31 | 0 | 24 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 401 | 401 | 587 | 0 | 121 | 122 | 61 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6945 | 6945 | 546 | 0 | 25 | 2 | 17 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 732 | 732 | 561 | 0 | 112 | 26 | 88 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4075 | 4075 | 580 | 0 | 36 | 0 | 24 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 205 | 205 | 592 | 1 | 146 | 1 | 91 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3245 | 3245 | 511 | 0 | 28 | 0 | 22 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 270 | 270 | 463 | 3 | 121 | 258 | 91 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2481 | 2481 | 318 | 0 | 49 | 41 | 39 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 147 | 147 | 669 | 4 | 153 | 458 | 79 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6689 | 6689 | 520 | 0 | 45 | 4 | 32 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 384 | 383 | 640 | 1 | 187 | 388 | 129 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5638 | 5638 | 471 | 0 | 42 | 0 | 34 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 497 | 496 | 631 | 0 | 190 | 320 | 152 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6614 | 6614 | 653 | 0 | 43 | 14 | 35 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 273 | 273 | 525 | 0 | 97 | 0 | 48 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 7755 | 7755 | 716 | 0 | 32 | 1 | 23 | 100% |
2022-2023 | PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 303 | 303 | 332 | 0 | 52 | 22 | 32 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3556 | 3556 | 407 | 0 | 25 | 2 | 21 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 409 | 409 | 446 | 1 | 114 | 29 | 76 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1271 | 1271 | 308 | 0 | 15 | 2 | 11 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 2864 | 2864 | 349 | 0 | 19 | 21 | 17 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 117 | 117 | 551 | 7 | 153 | 17 | 139 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 160 | 160 | 392 | 8 | 171 | 330 | 139 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4361 | 4361 | 513 | 0 | 25 | 0 | 18 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 376 | 376 | 726 | 0 | 134 | 40 | 90 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6902 | 6902 | 266 | 0 | 23 | 2 | 19 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 221 | 221 | 499 | 0 | 135 | 4 | 74 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 7568 | 7568 | 323 | 0 | 23 | 2 | 19 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 336 | 335 | 702 | 0 | 102 | 0 | 40 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 5319 | 5319 | 417 | 0 | 18 | 1 | 11 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 65 | 65 | 253 | 0 | 94 | 111 | 111 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4193 | 4193 | 493 | 0 | 29 | 9 | 23 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 207 | 206 | 656 | 2 | 107 | 15 | 70 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3658 | 3658 | 653 | 0 | 25 | 0 | 14 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 491 | 491 | 793 | 0 | 194 | 99 | 185 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4064 | 4064 | 420 | 0 | 29 | 0 | 20 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 270 | 270 | 599 | 1 | 122 | 13 | 85 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 5355 | 5355 | 752 | 0 | 16 | 0 | 7 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 733 | 733 | 545 | 0 | 53 | 2 | 25 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5357 | 5357 | 725 | 0 | 27 | 0 | 13 | 100% |
2022-2023 | PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 572 | 572 | 819 | 0 | 167 | 1 | 119 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 28306 | 28306 | 649 | 0 | 27 | 19 | 24 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 204 | 204 | 424 | 0 | 93 | 42 | 42 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 5861 | 5861 | 481 | 0 | 20 | 13 | 15 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 675 | 675 | 563 | 0 | 80 | 9 | 22 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 25415 | 25415 | 546 | 0 | 22 | 14 | 18 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 203 | 203 | 502 | 4 | 62 | 15 | 81 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 9008 | 9008 | 267 | 0 | 16 | 8 | 14 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 197 | 197 | 303 | 0 | 70 | 10 | 38 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5120 | 5120 | 462 | 0 | 37 | 0 | 30 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 255 | 255 | 752 | 0 | 196 | 11 | 87 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 29094 | 29094 | 542 | 0 | 30 | 37 | 27 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 1893 | 1893 | 744 | 0 | 253 | 559 | 337 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 21026 | 21026 | 580 | 0 | 27 | 14 | 21 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 495 | 494 | 624 | 0 | 75 | 35 | 25 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 17022 | 17022 | 434 | 0 | 26 | 1 | 21 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 144 | 144 | 604 | 1 | 258 | 323 | 323 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 13401 | 13401 | 546 | 0 | 21 | 7 | 17 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 350 | 350 | 538 | 1 | 104 | 74 | 74 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 11913 | 11913 | 267 | 0 | 23 | 0 | 18 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 85 | 85 | 445 | 15 | 289 | 207 | 244 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 9039 | 9039 | 454 | 0 | 27 | 8 | 22 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 132 | 132 | 605 | 4 | 289 | 321 | 321 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 5906 | 5906 | 737 | 0 | 24 | 14 | 14 | 100% |
2022-2023 | PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 170 | 170 | 591 | 1 | 168 | 345 | 95 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 9309 | 9309 | 191 | 0 | 9 | 1 | 6 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 220 | 215 | 237 | 0 | 45 | 7 | 34 | 98% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 5737 | 5737 | 248 | 0 | 9 | 4 | 7 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 181 | 180 | 300 | 0 | 27 | 7 | 13 | 99% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 9011 | 9011 | 357 | 0 | 16 | 10 | 14 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 332 | 321 | 299 | 0 | 55 | 93 | 39 | 97% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5022 | 5022 | 428 | 0 | 16 | 6 | 13 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 170 | 168 | 240 | 0 | 46 | 7 | 35 | 99% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3541 | 3541 | 188 | 0 | 16 | 9 | 13 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 422 | 399 | 288 | 0 | 49 | 11 | 30 | 95% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 2807 | 2807 | 247 | 0 | 14 | 8 | 11 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 66 | 63 | 129 | 2 | 35 | 40 | 35 | 95% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 7520 | 7520 | 400 | 0 | 15 | 4 | 8 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 181 | 173 | 191 | 0 | 39 | 22 | 22 | 96% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3959 | 3959 | 82 | 0 | 13 | 6 | 9 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 400 | 400 | 217 | 0 | 54 | 72 | 52 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4465 | 4464 | 421 | 0 | 16 | 4 | 10 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 691 | 657 | 418 | 0 | 61 | 14 | 37 | 95% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6068 | 6067 | 306 | 0 | 17 | 5 | 12 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 962 | 921 | 339 | 0 | 36 | 3 | 19 | 96% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4742 | 4742 | 469 | 0 | 15 | 0 | 10 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 380 | 343 | 473 | 0 | 68 | 28 | 42 | 90% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3029 | 3022 | 189 | 0 | 18 | 0 | 13 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 119 | 98 | 201 | 0 | 57 | 81 | 50 | 82% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3636 | 3636 | 143 | 0 | 17 | 11 | 14 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 3964 | 3964 | 170 | 0 | 12 | 6 | 9 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 141 | 132 | 461 | 2 | 53 | 79 | 27 | 94% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 33 | 33 | 144 | 1 | 17 | 1 | 11 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4390 | 4390 | 199 | 0 | 17 | 15 | 15 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 119 | 113 | 442 | 0 | 58 | 64 | 43 | 95% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5125 | 5125 | 426 | 0 | 18 | 14 | 14 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 121 | 89 | 205 | 0 | 29 | 14 | 16 | 74% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4517 | 4517 | 298 | 0 | 9 | 4 | 6 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 67 | 67 | 143 | 1 | 26 | 9 | 17 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4403 | 4403 | 112 | 0 | 18 | 18 | 16 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 82 | 76 | 182 | 1 | 52 | 1 | 36 | 93% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4560 | 4560 | 83 | 0 | 16 | 14 | 14 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 114 | 113 | 235 | 2 | 56 | 74 | 46 | 99% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 351 | 351 | 150 | 0 | 13 | 10 | 11 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 8066 | 8066 | 205 | 0 | 12 | 8 | 10 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 2 | 2 | 78 | 17 | 48 | 17 | 48 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 30 | 30 | 148 | 4 | 37 | 7 | 23 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 3012 | 3012 | 117 | 0 | 15 | 10 | 13 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 76 | 68 | 156 | 1 | 44 | 35 | 35 | 89% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 1618 | 1618 | 168 | 0 | 9 | 6 | 7 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Urban | 7 | 2862 | 2862 | 250 | 0 | 7 | 3 | 5 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 76 | 76 | 399 | 0 | 48 | 7 | 30 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA REQUIRED | Urban | 90 | 13 | 13 | 128 | 0 | 40 | 0 | 24 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 4170 | 4167 | 190 | 0 | 10 | 0 | 6 | 100% |
2023-2024 | CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - II | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 39 | 37 | 202 | 1 | 43 | 1 | 27 | 95% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 6626 | 6626 | 195 | 0 | 13 | 7 | 10 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 323 | 307 | 282 | 0 | 34 | 5 | 11 | 95% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 5324 | 5324 | 175 | 0 | 10 | 0 | 8 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 222 | 221 | 212 | 0 | 24 | 18 | 18 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 18392 | 18392 | 416 | 0 | 19 | 11 | 16 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 241 | 241 | 135 | 1 | 28 | 37 | 28 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 8062 | 8062 | 467 | 0 | 11 | 0 | 7 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Rural | 90 | 91 | 91 | 274 | 0 | 33 | 13 | 18 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 4568 | 4568 | 165 | 0 | 15 | 7 | 8 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 1402 | 1402 | 148 | 0 | 28 | 33 | 30 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 4753 | 4753 | 108 | 0 | 25 | 4 | 17 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 1853 | 1853 | 186 | 0 | 14 | 11 | 11 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 1692 | 1692 | 102 | 0 | 14 | 1 | 6 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 666 | 666 | 219 | 0 | 16 | 4 | 13 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 2269 | 2269 | 395 | 0 | 22 | 36 | 12 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 4735 | 4735 | 360 | 0 | 24 | 13 | 14 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 8866 | 8866 | 140 | 0 | 14 | 1 | 10 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 4492 | 4492 | 193 | 0 | 11 | 0 | 1 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 7563 | 7563 | 391 | 0 | 18 | 0 | 13 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | Metro | 90 | 3046 | 3046 | 148 | 0 | 13 | 6 | 11 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Metro | 3 | 7401 | 7401 | 271 | 0 | 13 | 4 | 7 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | Rural | 15 | 14665 | 14665 | 227 | 0 | 15 | 5 | 9 | 100% |
2023-2024 | KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection |