Statistics of LT New Service connections (Non AG) Applications From 01-Jan-2022
Statistics of LT New Service connections (Non AG) Applications Report generated as on 27-Jul-2024 |
||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Region | Zone | Circle | Division | Service | Infra Status | Notified Timeline (Days) | Number Of Applications Received | Number Of Applications Approved | Maximum (Days) | Minimum (Days) | Mean (Days) | Mode (Days) | Median (Days) | Compliance |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 21877 | 21648 | 605 | 0 | 15 | 1 | 9 | 99% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 394 | 356 | 350 | 0 | 63 | 97 | 48 | 90% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 13321 | 13182 | 600 | 0 | 12 | 0 | 7 | 99% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1067 | 1027 | 300 | 0 | 15 | 0 | 7 | 96% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 20637 | 20495 | 404 | 0 | 30 | 15 | 19 | 99% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 541 | 496 | 422 | 0 | 65 | 93 | 45 | 92% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 10388 | 10265 | 421 | 0 | 27 | 5 | 15 | 99% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 345 | 321 | 503 | 0 | 62 | 63 | 40 | 93% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 8578 | 8516 | 458 | 0 | 24 | 0 | 16 | 99% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 586 | 539 | 452 | 0 | 57 | 6 | 30 | 92% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 7278 | 7126 | 630 | 0 | 23 | 8 | 17 | 98% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 105 | 101 | 278 | 1 | 44 | 40 | 30 | 96% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 16659 | 16543 | 721 | 0 | 29 | 4 | 15 | 99% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 293 | 259 | 446 | 0 | 51 | 7 | 23 | 88% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9077 | 9054 | 304 | 0 | 16 | 7 | 9 | 100% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 668 | 609 | 294 | 0 | 59 | 72 | 34 | 91% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 11760 | 11532 | 777 | 0 | 27 | 7 | 12 | 98% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1656 | 1521 | 581 | 0 | 74 | 8 | 37 | 92% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 14589 | 14392 | 468 | 0 | 26 | 0 | 12 | 99% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1787 | 1620 | 547 | 0 | 33 | 0 | 14 | 91% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 12402 | 12206 | 737 | 0 | 33 | 0 | 13 | 98% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 563 | 442 | 579 | 0 | 65 | 28 | 34 | 79% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 7764 | 7526 | 588 | 0 | 31 | 0 | 14 | 97% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 244 | 188 | 545 | 0 | 106 | 26 | 59 | 77% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 18399 | 18263 | 433 | 0 | 24 | 0 | 13 | 99% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 259 | 222 | 314 | 1 | 37 | 79 | 20 | 86% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 10118 | 9974 | 468 | 0 | 37 | 15 | 21 | 99% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 218 | 169 | 498 | 0 | 47 | 64 | 31 | 78% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 11736 | 11643 | 379 | 0 | 34 | 6 | 19 | 99% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 246 | 165 | 383 | 0 | 39 | 14 | 19 | 67% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 13394 | 13335 | 457 | 0 | 18 | 0 | 9 | 100% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 158 | 153 | 322 | 0 | 44 | 11 | 24 | 97% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 10869 | 10750 | 529 | 0 | 37 | 18 | 22 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 140 | 108 | 469 | 1 | 52 | 25 | 31 | 77% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 11116 | 10976 | 423 | 0 | 36 | 0 | 20 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 152 | 126 | 353 | 0 | 51 | 74 | 41 | 83% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 20237 | 19979 | 619 | 0 | 16 | 7 | 11 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 79 | 76 | 184 | 4 | 45 | 7 | 38 | 96% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 7045 | 6970 | 337 | 0 | 27 | 9 | 17 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 102 | 87 | 160 | 1 | 43 | 35 | 35 | 85% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 11680 | 11574 | 567 | 0 | 18 | 0 | 8 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - I | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 313 | 271 | 812 | 0 | 89 | 26 | 48 | 87% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - II | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 10312 | 10177 | 558 | 0 | 24 | 0 | 8 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION - II | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 130 | 99 | 806 | 0 | 109 | 1 | 53 | 76% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 15282 | 14894 | 692 | 0 | 24 | 0 | 13 | 97% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 538 | 496 | 389 | 0 | 37 | 11 | 12 | 92% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 12638 | 12534 | 510 | 0 | 21 | 0 | 13 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 404 | 388 | 242 | 0 | 34 | 18 | 21 | 96% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 41827 | 41150 | 710 | 0 | 41 | 14 | 21 | 98% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 678 | 477 | 740 | 0 | 34 | 30 | 30 | 70% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 16128 | 15977 | 525 | 0 | 27 | 0 | 14 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 198 | 179 | 524 | 0 | 35 | 13 | 17 | 90% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 10275 | 10266 | 255 | 0 | 23 | 7 | 15 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 3336 | 3274 | 174 | 0 | 29 | 24 | 24 | 98% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9838 | 9834 | 250 | 0 | 28 | 4 | 18 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 3228 | 3059 | 232 | 0 | 13 | 10 | 11 | 95% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 4091 | 4082 | 288 | 0 | 16 | 1 | 8 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 765 | 763 | 444 | 0 | 24 | 4 | 12 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 6591 | 6591 | 307 | 0 | 28 | 35 | 26 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 7031 | 6057 | 370 | 0 | 29 | 13 | 16 | 86% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 21946 | 21928 | 286 | 0 | 29 | 1 | 21 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 6914 | 6240 | 434 | 0 | 13 | 0 | 1 | 90% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 22311 | 22267 | 403 | 0 | 31 | 0 | 22 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 4498 | 4196 | 148 | 0 | 16 | 6 | 12 | 93% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 60997 | 60360 | 530 | 0 | 28 | 5 | 16 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 5526 | 4951 | 311 | 0 | 12 | 10 | 10 | 90% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 35825 | 35711 | 578 | 0 | 29 | 4 | 19 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 5562 | 5120 | 550 | 0 | 18 | 8 | 15 | 92% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 7679 | 7578 | 449 | 0 | 34 | 7 | 21 | 99% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 547 | 493 | 430 | 0 | 45 | 9 | 25 | 90% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 12324 | 12098 | 411 | 0 | 21 | 0 | 11 | 98% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 318 | 278 | 279 | 0 | 51 | 27 | 36 | 87% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 7731 | 7646 | 337 | 0 | 20 | 0 | 12 | 99% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 260 | 216 | 428 | 0 | 60 | 6 | 41 | 83% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 8668 | 8539 | 460 | 0 | 38 | 6 | 26 | 99% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 504 | 335 | 613 | 1 | 105 | 101 | 90 | 66% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9393 | 9276 | 340 | 0 | 32 | 6 | 22 | 99% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 231 | 221 | 273 | 1 | 46 | 44 | 39 | 96% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 11703 | 11462 | 491 | 0 | 36 | 8 | 24 | 98% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 453 | 373 | 499 | 1 | 67 | 31 | 48 | 82% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 15492 | 15259 | 493 | 0 | 36 | 7 | 23 | 98% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 891 | 690 | 616 | 0 | 92 | 51 | 77 | 77% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 3154 | 3090 | 381 | 0 | 39 | 3 | 23 | 98% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 120 | 98 | 494 | 0 | 95 | 44 | 85 | 82% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 12476 | 12378 | 282 | 0 | 35 | 11 | 25 | 99% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 224 | 208 | 400 | 1 | 72 | 37 | 50 | 93% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 6416 | 6372 | 319 | 0 | 34 | 4 | 19 | 99% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 181 | 169 | 350 | 0 | 60 | 23 | 47 | 93% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9373 | 9297 | 649 | 0 | 15 | 6 | 10 | 99% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 328 | 308 | 535 | 1 | 76 | 9 | 51 | 94% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 7442 | 7420 | 273 | 0 | 8 | 0 | 4 | 100% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 121 | 94 | 148 | 0 | 28 | 17 | 18 | 78% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 11699 | 11675 | 205 | 0 | 22 | 1 | 7 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 3429 | 3428 | 169 | 0 | 20 | 2 | 11 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 46241 | 45988 | 525 | 0 | 24 | 1 | 9 | 99% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1577 | 1575 | 136 | 0 | 18 | 5 | 7 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 16108 | 16047 | 649 | 0 | 22 | 1 | 10 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 115 | 114 | 288 | 0 | 55 | 35 | 35 | 99% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 29384 | 29111 | 444 | 0 | 36 | 1 | 18 | 99% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 879 | 868 | 574 | 0 | 74 | 123 | 54 | 99% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 35507 | 35175 | 422 | 0 | 26 | 1 | 11 | 99% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 309 | 299 | 439 | 0 | 46 | 91 | 38 | 97% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 6091 | 6081 | 350 | 0 | 19 | 1 | 5 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 3 | 3 | 49 | 16 | 30 | 16 | 24 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 19855 | 19769 | 462 | 0 | 26 | 0 | 14 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 229 | 222 | 274 | 1 | 28 | 4 | 15 | 97% |
KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 55025 | 54776 | 665 | 0 | 26 | 1 | 11 | 100% |
KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 850 | 718 | 490 | 0 | 55 | 22 | 41 | 84% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 72634 | 72177 | 720 | 0 | 23 | 0 | 10 | 99% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1303 | 1189 | 318 | 0 | 49 | 28 | 28 | 91% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 57920 | 57579 | 592 | 0 | 27 | 0 | 13 | 99% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1465 | 1346 | 284 | 0 | 49 | 33 | 33 | 92% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9462 | 9332 | 439 | 0 | 27 | 4 | 13 | 99% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1110 | 948 | 742 | 0 | 79 | 10 | 60 | 85% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 10891 | 10770 | 348 | 0 | 24 | 3 | 13 | 99% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1201 | 937 | 714 | 0 | 85 | 23 | 37 | 78% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 17920 | 17800 | 684 | 0 | 22 | 0 | 10 | 99% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 2058 | 1748 | 609 | 0 | 76 | 1 | 43 | 85% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 11288 | 11160 | 589 | 0 | 21 | 0 | 12 | 99% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1661 | 1408 | 604 | 0 | 60 | 0 | 34 | 85% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 11069 | 10870 | 734 | 0 | 19 | 7 | 14 | 98% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 796 | 655 | 515 | 0 | 53 | 11 | 29 | 82% |
KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 15611 | 15510 | 453 | 0 | 37 | 7 | 19 | 99% |
KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1170 | 1105 | 457 | 0 | 55 | 9 | 32 | 94% |
KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 25968 | 25750 | 484 | 0 | 26 | 0 | 11 | 99% |
KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | AHMEDNAGAR URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1098 | 1006 | 576 | 0 | 64 | 10 | 41 | 92% |
KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 8408 | 8223 | 697 | 0 | 39 | 0 | 24 | 98% |
KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 417 | 328 | 581 | 0 | 80 | 6 | 48 | 79% |
KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 21825 | 21720 | 818 | 0 | 36 | 5 | 20 | 100% |
KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 858 | 774 | 427 | 0 | 53 | 19 | 30 | 90% |
KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9226 | 9198 | 409 | 0 | 39 | 7 | 17 | 100% |
KOKAN REGION | NASIK ZONE | A-NAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 625 | 608 | 522 | 0 | 39 | 6 | 17 | 97% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 3831 | 3808 | 301 | 0 | 19 | 0 | 8 | 99% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 535 | 496 | 449 | 0 | 55 | 4 | 30 | 93% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 5119 | 5106 | 513 | 0 | 35 | 3 | 16 | 100% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 350 | 337 | 455 | 0 | 45 | 54 | 31 | 96% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 7399 | 7327 | 492 | 0 | 27 | 0 | 15 | 99% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 479 | 449 | 483 | 0 | 40 | 67 | 24 | 94% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 3591 | 3577 | 311 | 0 | 14 | 0 | 8 | 100% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 356 | 332 | 482 | 0 | 48 | 35 | 33 | 93% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9659 | 9588 | 422 | 0 | 25 | 8 | 14 | 99% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 835 | 783 | 614 | 0 | 59 | 28 | 34 | 94% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 19977 | 19903 | 498 | 0 | 27 | 8 | 12 | 100% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 2294 | 2161 | 658 | 0 | 59 | 3 | 33 | 94% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 18522 | 18372 | 173 | 0 | 21 | 5 | 13 | 99% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 866 | 839 | 164 | 0 | 26 | 4 | 18 | 97% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 60170 | 59521 | 472 | 0 | 24 | 9 | 16 | 99% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 2181 | 1972 | 437 | 0 | 30 | 15 | 15 | 90% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 15611 | 15335 | 619 | 0 | 26 | 7 | 13 | 98% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 742 | 593 | 584 | 0 | 93 | 68 | 68 | 80% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 11793 | 11628 | 760 | 0 | 26 | 1 | 14 | 99% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1210 | 1000 | 625 | 0 | 88 | 21 | 52 | 83% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 6604 | 6506 | 621 | 0 | 29 | 0 | 14 | 99% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 323 | 247 | 614 | 0 | 110 | 62 | 84 | 76% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 16471 | 16211 | 822 | 0 | 28 | 0 | 14 | 98% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 924 | 809 | 772 | 0 | 73 | 9 | 48 | 88% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 19430 | 19047 | 662 | 0 | 31 | 14 | 15 | 98% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1106 | 877 | 676 | 0 | 92 | 8 | 61 | 79% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 10196 | 9982 | 430 | 0 | 37 | 11 | 18 | 98% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 616 | 488 | 682 | 0 | 80 | 61 | 61 | 79% |
NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 20127 | 19858 | 704 | 0 | 28 | 7 | 14 | 99% |
NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 877 | 694 | 587 | 0 | 105 | 3 | 62 | 79% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 14174 | 13832 | 504 | 0 | 32 | 0 | 21 | 98% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 658 | 442 | 722 | 0 | 129 | 231 | 92 | 67% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9774 | 9487 | 786 | 0 | 38 | 14 | 28 | 97% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 826 | 622 | 714 | 1 | 146 | 398 | 85 | 75% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 18512 | 18124 | 676 | 0 | 31 | 7 | 15 | 98% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1474 | 1101 | 829 | 0 | 123 | 68 | 75 | 75% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MURSHI DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 7314 | 7123 | 381 | 0 | 28 | 7 | 19 | 97% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MURSHI DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 436 | 377 | 637 | 0 | 77 | 45 | 61 | 86% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 8934 | 8867 | 371 | 0 | 37 | 20 | 24 | 99% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 165 | 119 | 614 | 0 | 88 | 3 | 49 | 72% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 10294 | 10165 | 606 | 0 | 32 | 0 | 26 | 99% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 268 | 221 | 722 | 0 | 120 | 259 | 70 | 82% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 12507 | 12334 | 695 | 0 | 47 | 21 | 31 | 99% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 222 | 161 | 355 | 0 | 70 | 61 | 40 | 73% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 8793 | 8524 | 583 | 0 | 35 | 14 | 24 | 97% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 371 | 263 | 628 | 0 | 101 | 13 | 50 | 71% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9519 | 9276 | 403 | 0 | 28 | 1 | 16 | 97% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 290 | 230 | 431 | 1 | 91 | 2 | 55 | 79% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 12240 | 12096 | 541 | 0 | 24 | 0 | 13 | 99% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 599 | 499 | 437 | 0 | 66 | 0 | 34 | 83% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 7981 | 7822 | 449 | 0 | 34 | 7 | 22 | 98% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 249 | 208 | 834 | 0 | 90 | 15 | 61 | 84% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 8320 | 7991 | 608 | 0 | 36 | 0 | 24 | 96% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 280 | 173 | 525 | 0 | 60 | 45 | 43 | 62% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 6069 | 5976 | 217 | 0 | 24 | 5 | 14 | 98% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 162 | 129 | 496 | 0 | 63 | 3 | 29 | 80% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 8630 | 8362 | 419 | 0 | 33 | 0 | 16 | 97% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 455 | 296 | 654 | 1 | 74 | 14 | 44 | 65% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 14806 | 14588 | 341 | 0 | 17 | 1 | 9 | 99% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 604 | 425 | 725 | 0 | 127 | 0 | 47 | 70% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 5020 | 4997 | 197 | 0 | 9 | 2 | 5 | 100% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 359 | 306 | 667 | 0 | 68 | 4 | 40 | 85% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 7078 | 7016 | 312 | 0 | 14 | 0 | 9 | 99% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 503 | 434 | 630 | 0 | 110 | 5 | 76 | 86% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 12735 | 12453 | 454 | 0 | 18 | 0 | 13 | 98% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 529 | 408 | 582 | 0 | 81 | 8 | 36 | 77% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 5355 | 5312 | 333 | 0 | 16 | 2 | 11 | 99% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 354 | 322 | 643 | 0 | 53 | 38 | 34 | 91% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 19953 | 19780 | 655 | 0 | 27 | 2 | 14 | 99% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 392 | 336 | 313 | 0 | 64 | 1 | 47 | 86% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9939 | 9835 | 420 | 0 | 22 | 7 | 13 | 99% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 453 | 411 | 658 | 0 | 41 | 4 | 20 | 91% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 6859 | 6822 | 365 | 0 | 24 | 4 | 14 | 99% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 257 | 219 | 489 | 0 | 71 | 14 | 50 | 85% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 16097 | 16013 | 397 | 0 | 18 | 0 | 8 | 99% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1033 | 991 | 399 | 0 | 103 | 40 | 42 | 96% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 17778 | 17687 | 611 | 0 | 18 | 1 | 7 | 99% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 422 | 422 | 318 | 0 | 24 | 5 | 8 | 100% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 24878 | 24718 | 707 | 0 | 21 | 0 | 10 | 99% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1541 | 1517 | 490 | 0 | 42 | 19 | 19 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 14603 | 14550 | 431 | 0 | 16 | 1 | 6 | 100% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 208 | 205 | 308 | 1 | 104 | 13 | 70 | 99% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 21669 | 21564 | 480 | 0 | 19 | 0 | 9 | 100% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 415 | 339 | 665 | 0 | 124 | 47 | 47 | 82% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 5844 | 5794 | 278 | 0 | 15 | 7 | 10 | 99% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 353 | 321 | 309 | 0 | 56 | 52 | 45 | 91% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 6081 | 6030 | 461 | 0 | 17 | 8 | 11 | 99% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 366 | 306 | 631 | 0 | 80 | 95 | 54 | 84% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 11405 | 11344 | 467 | 0 | 16 | 1 | 7 | 99% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 969 | 921 | 406 | 0 | 65 | 24 | 45 | 95% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 18743 | 18701 | 533 | 0 | 26 | 4 | 13 | 100% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 2498 | 2197 | 794 | 0 | 37 | 4 | 14 | 88% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 21948 | 21573 | 660 | 0 | 35 | 1 | 15 | 98% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1286 | 1067 | 620 | 0 | 97 | 5 | 57 | 83% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9754 | 9715 | 487 | 0 | 24 | 0 | 8 | 100% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1367 | 1221 | 537 | 0 | 47 | 1 | 25 | 89% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 18989 | 18660 | 531 | 0 | 23 | 0 | 14 | 98% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 842 | 693 | 531 | 0 | 66 | 27 | 43 | 82% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 11727 | 11585 | 355 | 0 | 23 | 7 | 14 | 99% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 959 | 818 | 610 | 0 | 81 | 122 | 40 | 85% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 17254 | 17059 | 362 | 0 | 20 | 2 | 12 | 99% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1894 | 1742 | 868 | 0 | 119 | 197 | 92 | 92% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9833 | 9713 | 770 | 0 | 25 | 1 | 11 | 99% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 703 | 510 | 657 | 0 | 99 | 6 | 62 | 73% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 7844 | 7797 | 511 | 0 | 20 | 0 | 11 | 99% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 843 | 674 | 711 | 0 | 88 | 146 | 61 | 80% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 6340 | 6304 | 365 | 0 | 34 | 3 | 14 | 99% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 652 | 389 | 669 | 0 | 101 | 92 | 66 | 60% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 16295 | 16106 | 520 | 0 | 33 | 3 | 13 | 99% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1300 | 796 | 820 | 0 | 126 | 388 | 75 | 61% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 13915 | 13781 | 471 | 0 | 31 | 5 | 18 | 99% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1549 | 1165 | 645 | 0 | 149 | 181 | 122 | 75% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 15756 | 15651 | 701 | 0 | 31 | 4 | 16 | 99% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 3102 | 846 | 642 | 0 | 83 | 4 | 37 | 27% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 18974 | 18771 | 719 | 0 | 23 | 3 | 13 | 99% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1032 | 860 | 399 | 0 | 44 | 18 | 30 | 83% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 8854 | 8813 | 407 | 0 | 19 | 6 | 12 | 100% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1472 | 1279 | 620 | 0 | 99 | 13 | 61 | 87% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 10449 | 10388 | 349 | 0 | 13 | 5 | 8 | 99% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 684 | 558 | 551 | 2 | 125 | 17 | 95 | 82% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 10767 | 10657 | 513 | 0 | 17 | 7 | 10 | 99% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 980 | 820 | 726 | 0 | 113 | 40 | 71 | 84% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 16935 | 16797 | 785 | 0 | 19 | 7 | 13 | 99% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1024 | 803 | 499 | 0 | 85 | 4 | 58 | 78% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 19101 | 18951 | 463 | 0 | 17 | 1 | 11 | 99% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1334 | 1041 | 702 | 0 | 66 | 5 | 44 | 78% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 13468 | 13360 | 417 | 0 | 14 | 1 | 8 | 99% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 594 | 497 | 265 | 0 | 82 | 180 | 53 | 84% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 10272 | 10215 | 493 | 0 | 19 | 5 | 11 | 99% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 650 | 475 | 656 | 0 | 92 | 21 | 62 | 73% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 8220 | 8180 | 566 | 0 | 17 | 1 | 7 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1841 | 1357 | 664 | 0 | 125 | 0 | 81 | 74% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 9820 | 9741 | 420 | 0 | 19 | 1 | 9 | 99% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 931 | 774 | 599 | 0 | 77 | 5 | 44 | 83% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 12024 | 11983 | 752 | 0 | 11 | 0 | 4 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 3797 | 2861 | 545 | 0 | 55 | 2 | 32 | 75% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 12306 | 12194 | 642 | 0 | 18 | 0 | 7 | 99% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 1831 | 1542 | 771 | 0 | 106 | 0 | 81 | 84% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 79247 | 78658 | 484 | 0 | 21 | 13 | 18 | 99% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 2825 | 2459 | 481 | 0 | 46 | 35 | 36 | 87% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 14571 | 14472 | 481 | 0 | 17 | 8 | 13 | 99% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 2136 | 1777 | 563 | 0 | 60 | 17 | 20 | 83% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 66888 | 66320 | 546 | 0 | 18 | 14 | 14 | 99% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 558 | 515 | 626 | 3 | 118 | 15 | 71 | 92% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 29499 | 28039 | 267 | 0 | 15 | 13 | 13 | 95% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 486 | 355 | 303 | 0 | 58 | 34 | 34 | 73% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 12910 | 12755 | 462 | 0 | 28 | 0 | 20 | 99% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 824 | 686 | 858 | 0 | 125 | 30 | 50 | 83% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 65919 | 65037 | 582 | 0 | 27 | 12 | 19 | 99% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 4027 | 3786 | 639 | 0 | 141 | 14 | 32 | 94% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 49470 | 48757 | 580 | 0 | 24 | 10 | 16 | 99% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 2385 | 2067 | 543 | 0 | 41 | 9 | 19 | 87% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 43003 | 42820 | 434 | 0 | 19 | 8 | 14 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 785 | 567 | 376 | 1 | 145 | 323 | 113 | 72% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 30521 | 30142 | 546 | 0 | 19 | 7 | 14 | 99% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 2321 | 1994 | 538 | 0 | 61 | 38 | 38 | 86% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 29527 | 29373 | 652 | 0 | 20 | 10 | 14 | 99% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 268 | 224 | 445 | 3 | 151 | 91 | 91 | 84% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 25939 | 25928 | 454 | 0 | 19 | 7 | 13 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 243 | 219 | 605 | 2 | 200 | 73 | 84 | 90% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection | INFRA NOT REQUIRED | 15 | 14172 | 14099 | 520 | 0 | 19 | 10 | 14 | 99% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection | INFRA REQUIRED | 90 | 3164 | 2701 | 591 | 0 | 37 | 18 | 23 | 85% |