Statistics of LT New Service connections (Non AG) Applications from 01-APR-2024
State Statistics of LT New Service connections (Non AG) Applications Report generated as on 18-Sep-2025 |
|||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Service | Infra Status | Area | Notified Timeline (Days) | Number Of Applications Received | Number Of Applications Approved | Maximum (Days) | Minimum (Days) | Mean (Days) | Mode (Days) | Median (Days) | Compliance |
Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 58454 | 57446 | 148 | 0 | 11 | 9 | 8 | 98% |
Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 265568 | 256317 | 162 | 1 | 25 | 15 | 20 | 97% |
Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 47987 | 46958 | 159 | 0 | 21 | 8 | 14 | 98% |
Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 97086 | 84132 | 155 | 1 | 37 | 11 | 23 | 87% |
Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 56490 | 43712 | 167 | 11 | 65 | 119 | 78 | 77% |
Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 7680 | 6408 | 140 | 18 | 48 | 64 | 45 | 83% |
Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 1062 | 1006 | 111 | 13 | 14 | 13 | 14 | 95% |
Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 2867 | 2674 | 125 | 30 | 32 | 30 | 30 | 93% |
Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 778 | 677 | 124 | 0 | 16 | 1 | 5 | 87% |
Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1066 | 919 | 144 | 18 | 43 | 18 | 19 | 86% |
Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 410 | 301 | 141 | 87 | 87 | 87 | 87 | 73% |
Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 105 | 84 | 69 | 2 | 20 | 6 | 14 | 80% |
Statistics of LT New Service connections (Non AG) Applications Report generated as on 18-Sep-2025 |
|||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Region | Zone | Circle | Division | Service | Infra Status | Area | Notified Timeline (Days) | Number Of Applications Received | Number Of Applications Approved | Maximum (Days) | Minimum (Days) | Mean (Days) | Mode (Days) | Median (Days) | Compliance |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 451 | 439 | 102 | 0 | 4 | 1 | 2 | 97% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3528 | 3301 | 126 | 0 | 8 | 2 | 5 | 94% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 14 | 13 | 25 | 0 | 3 | 0 | 0 | 93% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 32 | 26 | 33 | 0 | 7 | 0 | 4 | 81% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 926 | 918 | 107 | 0 | 8 | 1 | 5 | 99% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 1152 | 1042 | 86 | 0 | 12 | 1 | 8 | 90% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 19 | 12 | 23 | 0 | 7 | 1 | 3 | 63% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 14 | 8 | 11 | 0 | 6 | 6 | 6 | 57% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5385 | 5121 | 43 | 0 | 9 | 7 | 8 | 95% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 409 | 325 | 89 | 0 | 6 | 0 | 1 | 79% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 27 | 27 | 32 | 1 | 11 | 7 | 7 | 100% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 5 | 88 | 3 | 30 | 3 | 21 | 71% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2827 | 2660 | 95 | 0 | 11 | 5 | 8 | 94% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 141 | 81 | 141 | 0 | 36 | 18 | 33 | 57% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 30 | 29 | 30 | 0 | 4 | 0 | 2 | 97% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2070 | 2020 | 105 | 0 | 11 | 3 | 8 | 98% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 495 | 303 | 99 | 0 | 25 | 11 | 11 | 61% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 11 | 41 | 0 | 8 | 1 | 1 | 73% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 4 | 1 | 0 | 0 | 0 | 0 | 80% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1528 | 1458 | 58 | 0 | 7 | 2 | 6 | 95% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 72 | 53 | 85 | 2 | 47 | 35 | 57 | 74% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 643 | 639 | 34 | 0 | 6 | 1 | 3 | 99% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 4363 | 4182 | 101 | 0 | 5 | 1 | 3 | 96% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 1 | 5 | 5 | 5 | 5 | 5 | 17% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1240 | 1218 | 111 | 0 | 7 | 0 | 4 | 98% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2065 | 1951 | 130 | 0 | 20 | 3 | 14 | 94% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 3 | 9 | 0 | 5 | 0 | 6 | 100% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 2 | 9 | 1 | 5 | 1 | 5 | 40% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 536 | 486 | 133 | 0 | 9 | 1 | 4 | 91% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1638 | 1372 | 126 | 0 | 23 | 2 | 16 | 84% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 3 | 1 | 0 | 0 | 0 | 0 | 75% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 4 | 19 | 1 | 8 | 1 | 7 | 80% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1093 | 985 | 116 | 0 | 12 | 1 | 7 | 90% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 861 | 673 | 123 | 0 | 21 | 1 | 10 | 78% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 10 | 10 | 20 | 0 | 4 | 0 | 2 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 87 | 87 | 87 | 87 | 87 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1180 | 1134 | 144 | 0 | 14 | 1 | 9 | 96% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 989 | 770 | 156 | 0 | 22 | 1 | 16 | 78% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 9 | 9 | 44 | 0 | 9 | 0 | 1 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 8 | 24 | 1 | 9 | 13 | 8 | 89% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 414 | 377 | 120 | 0 | 14 | 2 | 9 | 91% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1411 | 1227 | 156 | 0 | 15 | 3 | 9 | 87% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 4 | 19 | 1 | 9 | 1 | 7 | 80% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 1 | 1 | 1 | 1 | 1 | 1 | 25% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 243 | 241 | 124 | 0 | 12 | 0 | 8 | 99% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 190 | 190 | 33 | 0 | 6 | 7 | 6 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1472 | 1335 | 167 | 0 | 17 | 1 | 13 | 91% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 1493 | 1455 | 106 | 0 | 8 | 1 | 5 | 97% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 1 | 1 | 10 | 10 | 10 | 10 | 10 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 15 | 15 | 4 | 0 | 1 | 0 | 1 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 19 | 1 | 5 | 1 | 2 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 39 | 39 | 15 | 0 | 3 | 1 | 1 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 625 | 582 | 59 | 0 | 14 | 2 | 14 | 93% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1664 | 1173 | 122 | 0 | 25 | 26 | 21 | 70% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 50% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 6 | 27 | 0 | 10 | 0 | 4 | 67% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1072 | 1036 | 96 | 0 | 18 | 3 | 13 | 97% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1504 | 1238 | 149 | 0 | 25 | 1 | 17 | 82% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 9 | 41 | 0 | 13 | 0 | 9 | 82% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 1 | 16 | 16 | 16 | 16 | 16 | 33% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3043 | 2972 | 122 | 0 | 12 | 2 | 8 | 98% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 33 | 24 | 109 | 0 | 31 | 0 | 24 | 73% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 27 | 0 | 8 | 0 | 4 | 100% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2104 | 2092 | 118 | 0 | 11 | 2 | 6 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 80 | 60 | 92 | 3 | 31 | 24 | 25 | 75% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 53 | 4 | 23 | 4 | 23 | 100% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2331 | 2305 | 155 | 0 | 20 | 4 | 14 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 18 | 5 | 121 | 11 | 61 | 11 | 44 | 28% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 8 | 1 | 4 | 1 | 3 | 100% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 3 | 3 | 3 | 3 | 3 | 100% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 125 | 123 | 103 | 1 | 17 | 4 | 9 | 98% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2517 | 2484 | 156 | 0 | 12 | 4 | 8 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2 | 1 | 6 | 6 | 6 | 6 | 6 | 50% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 51 | 23 | 73 | 0 | 16 | 0 | 11 | 45% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 9 | 8 | 25 | 0 | 7 | 0 | 5 | 89% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1476 | 1446 | 134 | 0 | 10 | 2 | 6 | 98% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 49 | 35 | 155 | 0 | 31 | 9 | 15 | 71% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 2 | 2 | 4 | 0 | 2 | 0 | 2 | 100% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1757 | 1744 | 162 | 0 | 23 | 1 | 14 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 786 | 782 | 159 | 0 | 21 | 8 | 14 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 38 | 9 | 92 | 10 | 49 | 44 | 44 | 24% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 7 | 2 | 47 | 18 | 33 | 18 | 33 | 29% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 2 | 15 | 0 | 8 | 0 | 8 | 67% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 8 | 8 | 54 | 0 | 16 | 1 | 3 | 100% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2153 | 2033 | 154 | 0 | 16 | 0 | 9 | 94% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 33 | 18 | 91 | 0 | 33 | 51 | 34 | 55% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2958 | 2879 | 116 | 0 | 5 | 1 | 3 | 97% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 167 | 138 | 90 | 1 | 19 | 1 | 10 | 83% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 90 | 89 | 71 | 0 | 14 | 1 | 7 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 7 | 55 | 0 | 27 | 55 | 20 | 70% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1896 | 1840 | 83 | 0 | 7 | 2 | 5 | 97% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 78 | 45 | 137 | 1 | 55 | 95 | 47 | 58% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 93 | 90 | 47 | 0 | 6 | 0 | 1 | 97% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 12 | 12 | 12 | 12 | 12 | 50% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7429 | 6957 | 79 | 0 | 9 | 4 | 7 | 94% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 678 | 598 | 86 | 0 | 29 | 26 | 21 | 88% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 58 | 49 | 78 | 0 | 17 | 0 | 13 | 84% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 3 | 31 | 13 | 20 | 13 | 17 | 50% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2785 | 2708 | 89 | 0 | 4 | 1 | 3 | 97% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 131 | 93 | 66 | 1 | 20 | 35 | 14 | 71% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 50 | 45 | 28 | 0 | 6 | 3 | 4 | 90% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 5 | 58 | 6 | 35 | 6 | 28 | 83% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 825 | 817 | 20 | 0 | 4 | 1 | 3 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3010 | 2786 | 78 | 0 | 10 | 4 | 5 | 93% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 42 | 42 | 8 | 0 | 2 | 1 | 1 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 63 | 60 | 83 | 0 | 4 | 0 | 1 | 95% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 480 | 479 | 15 | 0 | 3 | 1 | 2 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 2698 | 2459 | 119 | 0 | 7 | 3 | 4 | 91% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 35 | 34 | 7 | 0 | 1 | 0 | 0 | 97% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 122 | 110 | 38 | 0 | 2 | 1 | 1 | 90% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 384 | 380 | 19 | 0 | 2 | 0 | 1 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 330 | 319 | 21 | 0 | 3 | 1 | 2 | 97% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 35 | 32 | 20 | 0 | 2 | 0 | 1 | 91% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 45 | 40 | 35 | 0 | 2 | 0 | 1 | 89% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 244 | 241 | 14 | 0 | 2 | 1 | 1 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 2567 | 2255 | 115 | 0 | 15 | 0 | 8 | 88% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 27 | 27 | 9 | 0 | 1 | 0 | 0 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 50 | 45 | 69 | 0 | 8 | 3 | 3 | 90% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 527 | 522 | 8 | 0 | 2 | 2 | 2 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 4867 | 4392 | 94 | 0 | 8 | 1 | 3 | 90% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 52 | 49 | 8 | 0 | 1 | 0 | 1 | 94% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 64 | 49 | 107 | 0 | 5 | 0 | 1 | 77% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 5044 | 4989 | 84 | 0 | 4 | 1 | 3 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 2484 | 2214 | 103 | 0 | 14 | 1 | 9 | 89% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 174 | 160 | 56 | 0 | 6 | 0 | 2 | 92% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 36 | 32 | 81 | 0 | 13 | 1 | 4 | 89% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1508 | 1493 | 37 | 0 | 4 | 1 | 3 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2986 | 2935 | 42 | 0 | 5 | 3 | 4 | 98% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3414 | 3042 | 122 | 0 | 8 | 1 | 5 | 89% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 5034 | 4436 | 117 | 0 | 11 | 2 | 8 | 88% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 68 | 62 | 81 | 0 | 5 | 0 | 1 | 91% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 56 | 53 | 25 | 0 | 4 | 2 | 3 | 95% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 101 | 96 | 68 | 0 | 9 | 0 | 4 | 95% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 45 | 43 | 45 | 0 | 9 | 2 | 5 | 96% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 861 | 860 | 43 | 0 | 6 | 2 | 4 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 4823 | 4639 | 120 | 0 | 8 | 1 | 5 | 96% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 23 | 23 | 53 | 0 | 11 | 2 | 4 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 162 | 143 | 69 | 0 | 6 | 1 | 3 | 88% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1497 | 1438 | 130 | 0 | 14 | 7 | 10 | 96% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 43 | 28 | 121 | 0 | 30 | 0 | 21 | 65% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 1 | 1 | 3 | 3 | 3 | 3 | 3 | 100% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1117 | 1087 | 100 | 0 | 17 | 3 | 13 | 97% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1183 | 1177 | 123 | 0 | 15 | 2 | 9 | 99% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 31 | 19 | 136 | 0 | 41 | 0 | 36 | 61% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 24 | 21 | 44 | 1 | 7 | 7 | 7 | 88% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 1 | 1 | 30 | 30 | 30 | 30 | 30 | 100% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 12 | 10 | 3 | 0 | 1 | 0 | 2 | 83% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1664 | 1640 | 114 | 0 | 14 | 1 | 8 | 99% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 249 | 215 | 79 | 0 | 19 | 12 | 12 | 86% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 12 | 18 | 0 | 3 | 0 | 0 | 100% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 35 | 35 | 35 | 35 | 35 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1868 | 1754 | 123 | 0 | 21 | 7 | 16 | 94% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 163 | 106 | 138 | 1 | 39 | 32 | 32 | 65% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 12 | 0 | 5 | 0 | 1 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1897 | 1877 | 158 | 0 | 9 | 1 | 5 | 99% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 109 | 92 | 132 | 0 | 28 | 4 | 27 | 84% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 14 | 0 | 5 | 0 | 1 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2768 | 2710 | 139 | 0 | 18 | 6 | 14 | 98% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 105 | 50 | 144 | 0 | 24 | 3 | 6 | 48% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 22 | 20 | 42 | 4 | 13 | 6 | 7 | 91% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 827 | 782 | 137 | 0 | 17 | 4 | 12 | 95% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1891 | 1836 | 149 | 0 | 11 | 0 | 5 | 97% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 23 | 8 | 71 | 6 | 37 | 31 | 31 | 35% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 264 | 134 | 125 | 0 | 44 | 64 | 45 | 51% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 1 | 1 | 4 | 4 | 4 | 4 | 4 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 85 | 83 | 74 | 0 | 7 | 0 | 3 | 98% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1008 | 918 | 162 | 0 | 24 | 12 | 19 | 91% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 70 | 24 | 141 | 0 | 38 | 2 | 15 | 34% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 2 | 2 | 9 | 3 | 6 | 3 | 6 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1349 | 1314 | 152 | 0 | 15 | 3 | 11 | 97% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 33 | 13 | 74 | 1 | 28 | 1 | 20 | 39% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 6 | 67 | 1 | 21 | 1 | 9 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 23 | 23 | 23 | 23 | 23 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1871 | 1850 | 139 | 0 | 15 | 4 | 10 | 99% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 62 | 55 | 107 | 1 | 33 | 19 | 23 | 89% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 1 | 1 | 28 | 28 | 28 | 28 | 28 | 100% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1370 | 1320 | 118 | 0 | 16 | 6 | 11 | 96% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 54 | 21 | 102 | 5 | 42 | 56 | 35 | 39% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 13 | 39 | 0 | 12 | 0 | 6 | 93% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 49 | 49 | 49 | 49 | 49 | 100% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1310 | 1284 | 101 | 0 | 7 | 1 | 4 | 98% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1142 | 199 | 93 | 0 | 65 | 77 | 78 | 17% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 6 | 22 | 1 | 12 | 1 | 15 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1686 | 1660 | 34 | 0 | 4 | 2 | 3 | 98% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 220 | 218 | 26 | 0 | 4 | 1 | 3 | 99% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 95 | 94 | 42 | 0 | 3 | 1 | 1 | 99% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 4 | 4 | 2 | 0 | 1 | 2 | 2 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 10765 | 10639 | 85 | 0 | 5 | 1 | 3 | 99% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 479 | 428 | 155 | 0 | 14 | 1 | 4 | 89% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 68 | 59 | 111 | 0 | 12 | 1 | 2 | 87% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 3 | 3 | 121 | 0 | 43 | 0 | 8 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2979 | 2899 | 54 | 0 | 5 | 2 | 3 | 97% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 316 | 116 | 119 | 1 | 12 | 10 | 10 | 37% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 47 | 47 | 14 | 0 | 2 | 0 | 1 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 1 | 9 | 9 | 9 | 9 | 9 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6779 | 6695 | 109 | 0 | 6 | 2 | 5 | 99% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 134 | 107 | 77 | 2 | 27 | 7 | 18 | 80% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 65 | 63 | 40 | 0 | 10 | 0 | 6 | 97% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6057 | 5975 | 98 | 0 | 4 | 0 | 2 | 99% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 129 | 111 | 139 | 0 | 17 | 1 | 9 | 86% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 20 | 19 | 34 | 0 | 8 | 3 | 4 | 95% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1693 | 1667 | 96 | 0 | 8 | 2 | 5 | 98% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 17 | 13 | 42 | 0 | 9 | 0 | 0 | 76% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3222 | 3167 | 73 | 0 | 4 | 0 | 1 | 98% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 142 | 110 | 90 | 0 | 20 | 1 | 14 | 77% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 58 | 50 | 27 | 0 | 4 | 0 | 1 | 86% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 17 | 8 | 69 | 0 | 19 | 0 | 5 | 47% |
KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 14138 | 13489 | 106 | 0 | 11 | 2 | 7 | 95% |
KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 808 | 535 | 128 | 0 | 15 | 1 | 6 | 66% |
KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 223 | 204 | 125 | 0 | 13 | 0 | 2 | 91% |
KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 4 | 22 | 5 | 14 | 22 | 15 | 57% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1747 | 1633 | 128 | 0 | 18 | 5 | 13 | 93% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 10735 | 10483 | 122 | 0 | 6 | 1 | 4 | 98% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 121 | 49 | 96 | 0 | 10 | 0 | 0 | 40% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 377 | 267 | 101 | 1 | 28 | 5 | 18 | 71% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 24 | 24 | 95 | 0 | 32 | 0 | 24 | 100% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 87 | 81 | 48 | 0 | 6 | 1 | 2 | 93% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 2 | 45 | 0 | 23 | 0 | 23 | 67% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 7 | 6 | 47 | 0 | 20 | 0 | 14 | 86% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 11600 | 11289 | 106 | 0 | 5 | 2 | 4 | 97% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 528 | 424 | 98 | 0 | 10 | 2 | 3 | 80% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 151 | 101 | 60 | 0 | 7 | 0 | 5 | 67% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 3 | 2 | 26 | 2 | 14 | 2 | 14 | 67% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1581 | 1503 | 51 | 0 | 9 | 2 | 6 | 95% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 603 | 348 | 162 | 1 | 18 | 2 | 10 | 58% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 11 | 34 | 1 | 13 | 1 | 6 | 73% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 3 | 99 | 4 | 42 | 4 | 22 | 75% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1773 | 1699 | 75 | 0 | 8 | 2 | 5 | 96% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 349 | 172 | 143 | 1 | 22 | 10 | 14 | 49% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 52 | 48 | 59 | 1 | 15 | 2 | 12 | 92% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 19 | 19 | 19 | 19 | 19 | 50% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2957 | 2846 | 78 | 0 | 9 | 3 | 6 | 96% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 429 | 185 | 152 | 0 | 54 | 86 | 42 | 43% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 143 | 138 | 93 | 0 | 11 | 0 | 6 | 97% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 5 | 33 | 0 | 15 | 0 | 8 | 50% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1943 | 1839 | 84 | 0 | 9 | 2 | 6 | 95% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 237 | 149 | 144 | 0 | 36 | 27 | 27 | 63% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 81 | 73 | 124 | 0 | 20 | 0 | 9 | 90% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 4 | 43 | 0 | 14 | 0 | 7 | 44% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1727 | 1651 | 113 | 0 | 15 | 1 | 10 | 96% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 264 | 203 | 124 | 2 | 41 | 26 | 33 | 77% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 104 | 90 | 85 | 0 | 17 | 3 | 13 | 87% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 10 | 59 | 0 | 26 | 34 | 34 | 91% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2277 | 2090 | 136 | 0 | 11 | 7 | 8 | 92% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 138 | 112 | 119 | 0 | 50 | 86 | 39 | 81% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 5 | 24 | 3 | 11 | 3 | 7 | 83% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 26 | 26 | 26 | 26 | 26 | 100% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1551 | 1524 | 79 | 0 | 9 | 0 | 7 | 98% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3120 | 3086 | 139 | 0 | 9 | 1 | 7 | 99% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 256 | 181 | 137 | 0 | 28 | 32 | 22 | 71% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 99 | 53 | 134 | 0 | 28 | 12 | 20 | 54% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 7 | 30 | 0 | 10 | 0 | 10 | 100% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 27 | 19 | 34 | 0 | 5 | 1 | 1 | 70% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 6 | 42 | 0 | 17 | 0 | 13 | 86% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1974 | 1890 | 73 | 0 | 6 | 0 | 3 | 96% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 215 | 174 | 165 | 0 | 29 | 17 | 17 | 81% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 4 | 4 | 0 | 1 | 0 | 0 | 100% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3895 | 3838 | 119 | 0 | 7 | 0 | 5 | 99% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 579 | 527 | 93 | 0 | 12 | 0 | 7 | 91% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 32 | 32 | 29 | 0 | 3 | 0 | 2 | 100% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 5 | 3 | 4 | 3 | 4 | 100% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2251 | 2216 | 118 | 0 | 6 | 1 | 4 | 98% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 146 | 123 | 84 | 0 | 16 | 1 | 8 | 84% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 6 | 20 | 0 | 3 | 0 | 0 | 86% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1265 | 1237 | 131 | 0 | 5 | 1 | 3 | 98% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 74 | 50 | 137 | 0 | 12 | 1 | 2 | 68% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 35 | 35 | 7 | 0 | 2 | 2 | 2 | 100% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1092 | 990 | 73 | 0 | 15 | 7 | 13 | 91% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 78 | 45 | 124 | 1 | 30 | 26 | 25 | 58% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 34 | 6 | 20 | 6 | 14 | 100% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1436 | 1394 | 133 | 0 | 15 | 6 | 12 | 97% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 45 | 26 | 86 | 5 | 29 | 6 | 22 | 58% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 6 | 8 | 1 | 3 | 1 | 2 | 100% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 914 | 870 | 56 | 0 | 10 | 0 | 8 | 95% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 88 | 62 | 90 | 0 | 12 | 0 | 1 | 70% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 13 | 1 | 7 | 13 | 5 | 100% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1712 | 1672 | 45 | 0 | 6 | 2 | 5 | 98% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 160 | 133 | 139 | 0 | 39 | 56 | 34 | 83% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 30 | 29 | 15 | 0 | 4 | 0 | 2 | 97% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 61 | 61 | 61 | 61 | 61 | 100% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3633 | 3565 | 99 | 0 | 6 | 1 | 4 | 98% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 900 | 682 | 111 | 0 | 22 | 8 | 14 | 76% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 34 | 31 | 16 | 0 | 5 | 2 | 3 | 91% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 73 | 19 | 46 | 19 | 46 | 100% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 3560 | 3505 | 23 | 0 | 1 | 0 | 0 | 98% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 283 | 266 | 103 | 0 | 9 | 0 | 0 | 94% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 56 | 55 | 5 | 0 | 0 | 0 | 0 | 98% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 1 | 4 | 4 | 4 | 4 | 4 | 100% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 8418 | 8110 | 33 | 0 | 2 | 1 | 1 | 96% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3264 | 3138 | 67 | 0 | 5 | 3 | 4 | 96% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 844 | 701 | 87 | 0 | 7 | 1 | 2 | 83% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 741 | 650 | 137 | 0 | 12 | 4 | 9 | 88% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 46 | 43 | 3 | 0 | 1 | 0 | 1 | 93% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 26 | 26 | 9 | 0 | 2 | 0 | 1 | 100% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 2 | 2 | 6 | 3 | 5 | 3 | 5 | 100% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 7 | 52 | 2 | 11 | 2 | 3 | 88% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2161 | 2088 | 135 | 0 | 24 | 7 | 17 | 97% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 136 | 45 | 131 | 0 | 60 | 119 | 52 | 33% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 12 | 60 | 1 | 20 | 1 | 18 | 100% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 37 | 37 | 37 | 37 | 37 | 100% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1625 | 1607 | 109 | 0 | 17 | 6 | 11 | 99% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 335 | 90 | 140 | 0 | 48 | 21 | 42 | 27% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 45 | 44 | 124 | 0 | 5 | 0 | 2 | 98% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1313 | 1275 | 154 | 0 | 18 | 6 | 12 | 97% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 82 | 45 | 134 | 2 | 60 | 69 | 69 | 55% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 4 | 28 | 3 | 10 | 3 | 5 | 80% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2158 | 2129 | 159 | 0 | 12 | 0 | 7 | 99% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 161 | 123 | 98 | 0 | 31 | 0 | 24 | 76% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 11 | 27 | 0 | 4 | 0 | 1 | 92% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1669 | 1638 | 141 | 0 | 18 | 0 | 11 | 98% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 250 | 160 | 155 | 0 | 40 | 106 | 29 | 64% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 24 | 23 | 7 | 0 | 2 | 0 | 1 | 96% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 17 | 17 | 17 | 17 | 17 | 100% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1846 | 1797 | 127 | 0 | 20 | 3 | 15 | 97% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 112 | 71 | 143 | 5 | 51 | 20 | 40 | 63% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 5 | 6 | 0 | 2 | 0 | 2 | 83% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2288 | 1981 | 140 | 0 | 19 | 0 | 12 | 87% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 260 | 63 | 82 | 0 | 24 | 5 | 9 | 24% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 4 | 26 | 18 | 23 | 18 | 24 | 100% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3006 | 2832 | 158 | 0 | 25 | 5 | 20 | 94% |
NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 98 | 47 | 128 | 0 | 41 | 18 | 31 | 48% |
NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 6 | 60 | 0 | 19 | 0 | 13 | 100% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3406 | 3323 | 161 | 0 | 12 | 6 | 9 | 98% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 133 | 95 | 157 | 0 | 63 | 109 | 58 | 71% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 29 | 29 | 59 | 1 | 7 | 2 | 4 | 100% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1924 | 1853 | 132 | 0 | 10 | 0 | 6 | 96% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 204 | 117 | 117 | 0 | 31 | 0 | 21 | 57% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 6 | 5 | 0 | 2 | 1 | 1 | 75% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 10 | 0 | 5 | 0 | 5 | 100% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2829 | 2767 | 134 | 0 | 10 | 0 | 6 | 98% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 209 | 85 | 76 | 0 | 22 | 8 | 10 | 41% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 33 | 29 | 31 | 0 | 4 | 0 | 1 | 88% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 2 | 2 | 19 | 18 | 19 | 18 | 19 | 100% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1462 | 1450 | 66 | 0 | 8 | 2 | 5 | 99% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 106 | 83 | 128 | 0 | 39 | 11 | 32 | 78% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 11 | 10 | 0 | 2 | 2 | 2 | 100% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2335 | 2247 | 111 | 0 | 11 | 5 | 8 | 96% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 81 | 51 | 151 | 0 | 41 | 12 | 38 | 63% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 3 | 6 | 1 | 3 | 1 | 1 | 100% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 51 | 21 | 36 | 21 | 36 | 100% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1980 | 1929 | 104 | 0 | 13 | 6 | 11 | 97% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 73 | 29 | 68 | 0 | 34 | 47 | 34 | 40% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 16 | 10 | 28 | 2 | 16 | 2 | 16 | 63% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 3 | 3 | 3 | 3 | 3 | 100% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2428 | 2342 | 131 | 0 | 16 | 15 | 15 | 96% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 95 | 69 | 132 | 0 | 37 | 25 | 32 | 73% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 12 | 49 | 0 | 15 | 16 | 13 | 100% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1357 | 1344 | 139 | 0 | 13 | 1 | 7 | 99% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 113 | 87 | 128 | 0 | 22 | 28 | 17 | 77% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 17 | 14 | 0 | 3 | 1 | 1 | 89% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2376 | 2302 | 91 | 0 | 11 | 7 | 10 | 97% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 145 | 101 | 105 | 0 | 26 | 12 | 13 | 70% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 28 | 28 | 27 | 0 | 6 | 0 | 4 | 100% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 30 | 30 | 30 | 30 | 30 | 100% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 995 | 952 | 86 | 0 | 11 | 2 | 9 | 96% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1106 | 1063 | 76 | 0 | 9 | 4 | 7 | 96% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 36 | 13 | 90 | 6 | 44 | 55 | 50 | 36% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 69 | 40 | 140 | 0 | 32 | 8 | 13 | 58% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 20 | 19 | 18 | 0 | 5 | 0 | 3 | 95% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 51 | 39 | 27 | 0 | 4 | 0 | 1 | 76% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 1 | 1 | 2 | 2 | 2 | 2 | 2 | 100% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1425 | 1371 | 117 | 0 | 12 | 9 | 10 | 96% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 105 | 65 | 127 | 0 | 34 | 24 | 27 | 62% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 15 | 47 | 1 | 8 | 2 | 4 | 100% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 1 | 47 | 47 | 47 | 47 | 47 | 33% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2398 | 2226 | 104 | 0 | 14 | 5 | 12 | 93% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 61 | 36 | 74 | 0 | 17 | 0 | 13 | 59% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 15 | 65 | 1 | 12 | 7 | 7 | 100% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 52 | 52 | 52 | 52 | 52 | 100% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1360 | 1337 | 59 | 0 | 3 | 1 | 2 | 98% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 93 | 70 | 112 | 0 | 20 | 2 | 9 | 75% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 48 | 47 | 14 | 0 | 2 | 1 | 2 | 98% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 4 | 3 | 1 | 2 | 3 | 3 | 80% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2246 | 2175 | 113 | 0 | 9 | 7 | 7 | 97% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 57 | 37 | 82 | 0 | 31 | 2 | 33 | 65% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 166 | 156 | 59 | 0 | 13 | 6 | 10 | 94% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 9 | 44 | 1 | 19 | 1 | 18 | 82% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2511 | 2468 | 126 | 0 | 11 | 1 | 7 | 98% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 162 | 95 | 124 | 0 | 44 | 0 | 38 | 59% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 42 | 39 | 18 | 0 | 4 | 0 | 2 | 93% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 947 | 927 | 33 | 0 | 5 | 1 | 4 | 98% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 81 | 45 | 121 | 0 | 46 | 13 | 34 | 56% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 11 | 24 | 0 | 3 | 2 | 2 | 92% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 54 | 54 | 54 | 54 | 54 | 100% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1506 | 1426 | 70 | 0 | 13 | 2 | 9 | 95% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 223 | 185 | 148 | 0 | 28 | 14 | 14 | 83% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 21 | 20 | 14 | 0 | 3 | 1 | 1 | 95% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2618 | 2484 | 106 | 0 | 11 | 4 | 8 | 95% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 110 | 65 | 147 | 1 | 46 | 1 | 36 | 59% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 42 | 38 | 41 | 0 | 5 | 1 | 1 | 90% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 940 | 919 | 94 | 0 | 5 | 1 | 4 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 65 | 49 | 117 | 0 | 25 | 1 | 12 | 75% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 10 | 9 | 19 | 0 | 4 | 0 | 2 | 90% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3955 | 3839 | 91 | 0 | 7 | 0 | 6 | 97% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 85 | 34 | 153 | 1 | 44 | 41 | 41 | 40% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 30 | 27 | 42 | 0 | 9 | 0 | 7 | 90% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 7 | 91 | 37 | 52 | 42 | 42 | 64% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1582 | 1534 | 47 | 0 | 6 | 1 | 5 | 97% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 123 | 81 | 148 | 0 | 27 | 6 | 15 | 66% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 44 | 33 | 13 | 0 | 2 | 0 | 1 | 75% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 19 | 19 | 19 | 19 | 19 | 50% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1561 | 1537 | 23 | 0 | 3 | 1 | 2 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 60 | 29 | 113 | 0 | 49 | 37 | 46 | 48% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 60 | 57 | 25 | 0 | 3 | 1 | 1 | 95% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 376 | 358 | 5 | 0 | 0 | 0 | 0 | 95% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2572 | 2511 | 85 | 0 | 4 | 2 | 3 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 172 | 138 | 71 | 0 | 11 | 7 | 7 | 80% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 177 | 135 | 111 | 0 | 13 | 11 | 6 | 76% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 5 | 4 | 2 | 0 | 1 | 0 | 0 | 80% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 51 | 47 | 38 | 0 | 3 | 1 | 2 | 92% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 2 | 1 | 0 | 0 | 0 | 0 | 0 | 50% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 6 | 45 | 0 | 16 | 0 | 3 | 55% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1884 | 1838 | 118 | 0 | 2 | 1 | 1 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 1301 | 1216 | 57 | 0 | 2 | 2 | 1 | 93% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 31 | 30 | 18 | 0 | 2 | 1 | 1 | 97% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 12 | 11 | 5 | 0 | 1 | 0 | 0 | 92% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1841 | 1816 | 56 | 0 | 1 | 0 | 1 | 99% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3115 | 3038 | 91 | 0 | 4 | 1 | 3 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 102 | 60 | 81 | 0 | 12 | 1 | 3 | 59% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 136 | 104 | 56 | 0 | 15 | 18 | 10 | 76% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 62 | 61 | 15 | 0 | 1 | 0 | 0 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 18 | 18 | 6 | 0 | 2 | 0 | 2 | 100% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2399 | 2361 | 34 | 0 | 1 | 1 | 1 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 30 | 14 | 106 | 0 | 37 | 7 | 15 | 47% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 24 | 20 | 2 | 0 | 1 | 0 | 0 | 83% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2870 | 2831 | 40 | 0 | 2 | 1 | 1 | 99% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 207 | 146 | 119 | 0 | 18 | 10 | 10 | 71% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 46 | 43 | 27 | 0 | 2 | 0 | 1 | 93% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 887 | 865 | 98 | 0 | 6 | 1 | 4 | 98% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 94 | 59 | 105 | 0 | 37 | 23 | 29 | 63% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 15 | 16 | 0 | 4 | 0 | 2 | 100% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 50% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1093 | 1066 | 34 | 0 | 5 | 2 | 4 | 98% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 56 | 32 | 124 | 3 | 40 | 56 | 39 | 57% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 7 | 17 | 0 | 8 | 0 | 8 | 100% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 16 | 16 | 16 | 16 | 16 | 100% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1785 | 1749 | 38 | 0 | 6 | 1 | 5 | 98% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 140 | 88 | 140 | 0 | 27 | 0 | 19 | 63% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 53 | 37 | 15 | 0 | 5 | 0 | 3 | 70% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 115 | 13 | 64 | 13 | 64 | 100% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2966 | 2883 | 92 | 0 | 11 | 2 | 8 | 97% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1294 | 975 | 147 | 0 | 21 | 11 | 14 | 75% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 9 | 9 | 60 | 0 | 17 | 0 | 2 | 100% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 3 | 41 | 0 | 14 | 0 | 2 | 100% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3567 | 3407 | 126 | 0 | 12 | 13 | 10 | 96% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 837 | 436 | 139 | 0 | 34 | 3 | 25 | 52% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 21 | 21 | 35 | 0 | 11 | 5 | 9 | 100% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 4 | 31 | 0 | 9 | 0 | 2 | 50% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1170 | 1138 | 98 | 0 | 10 | 1 | 7 | 97% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 877 | 660 | 159 | 0 | 24 | 12 | 17 | 75% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 2 | 8 | 0 | 4 | 0 | 4 | 67% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 39 | 39 | 39 | 39 | 39 | 100% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2951 | 2825 | 66 | 0 | 7 | 2 | 6 | 96% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 376 | 214 | 122 | 1 | 21 | 14 | 14 | 57% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 18 | 33 | 0 | 4 | 1 | 1 | 95% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 4 | 92 | 4 | 36 | 4 | 23 | 80% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2113 | 2031 | 81 | 0 | 6 | 1 | 4 | 96% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 335 | 227 | 114 | 1 | 28 | 97 | 15 | 68% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 20 | 20 | 7 | 0 | 1 | 0 | 0 | 100% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 1 | 49 | 49 | 49 | 49 | 49 | 20% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2673 | 2616 | 106 | 0 | 8 | 2 | 5 | 98% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 741 | 619 | 97 | 0 | 12 | 1 | 7 | 84% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 44 | 43 | 22 | 0 | 3 | 0 | 1 | 98% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 4 | 31 | 3 | 13 | 3 | 9 | 80% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1879 | 1766 | 91 | 0 | 11 | 7 | 9 | 94% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 332 | 103 | 145 | 5 | 44 | 25 | 28 | 31% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 50 | 49 | 31 | 0 | 2 | 1 | 1 | 98% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1343 | 1275 | 116 | 0 | 9 | 2 | 7 | 95% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 165 | 88 | 105 | 0 | 39 | 14 | 36 | 53% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 24 | 24 | 48 | 0 | 8 | 1 | 5 | 100% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 27 | 0 | 10 | 11 | 11 | 100% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1613 | 1521 | 59 | 0 | 5 | 2 | 3 | 94% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 336 | 96 | 104 | 0 | 25 | 27 | 18 | 29% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 3 | 5 | 0 | 2 | 0 | 1 | 100% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2780 | 2629 | 111 | 0 | 11 | 3 | 8 | 95% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 769 | 491 | 144 | 0 | 26 | 12 | 19 | 64% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 22 | 18 | 15 | 0 | 4 | 1 | 3 | 82% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 28 | 28 | 28 | 28 | 28 | 50% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2714 | 2626 | 159 | 0 | 8 | 0 | 6 | 97% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1004 | 674 | 130 | 0 | 26 | 7 | 18 | 67% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 38 | 36 | 22 | 0 | 8 | 6 | 6 | 95% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 7 | 54 | 0 | 13 | 0 | 6 | 58% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2988 | 2897 | 155 | 0 | 11 | 5 | 7 | 97% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1200 | 846 | 126 | 0 | 22 | 5 | 14 | 71% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 13 | 13 | 39 | 0 | 13 | 10 | 10 | 100% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 5 | 24 | 2 | 12 | 2 | 14 | 83% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2470 | 2422 | 67 | 0 | 5 | 1 | 3 | 98% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 1225 | 1058 | 87 | 0 | 9 | 5 | 6 | 86% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 23 | 23 | 12 | 0 | 4 | 1 | 2 | 100% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 3 | 3 | 32 | 0 | 12 | 0 | 4 | 100% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1396 | 1354 | 27 | 0 | 5 | 2 | 4 | 97% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 615 | 420 | 116 | 1 | 29 | 4 | 19 | 68% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 22 | 22 | 34 | 0 | 4 | 0 | 2 | 100% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 3 | 18 | 4 | 13 | 4 | 17 | 75% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 590 | 582 | 14 | 0 | 2 | 1 | 1 | 99% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1044 | 1016 | 26 | 0 | 3 | 1 | 2 | 97% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 71 | 45 | 149 | 0 | 39 | 19 | 42 | 63% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 179 | 135 | 99 | 0 | 21 | 2 | 11 | 75% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 8 | 17 | 1 | 6 | 2 | 4 | 100% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 6 | 6 | 4 | 0 | 1 | 0 | 1 | 100% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 5 | 5 | 2 | 0 | 0 | 0 | 0 | 100% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1981 | 1937 | 28 | 0 | 4 | 1 | 3 | 98% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 355 | 247 | 116 | 0 | 29 | 4 | 16 | 70% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 39 | 38 | 13 | 0 | 3 | 0 | 2 | 97% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 3 | 3 | 3 | 3 | 3 | 50% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2914 | 2843 | 82 | 0 | 4 | 1 | 3 | 98% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 340 | 186 | 144 | 1 | 50 | 4 | 49 | 55% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 23 | 22 | 21 | 1 | 4 | 1 | 3 | 96% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3486 | 3409 | 25 | 0 | 3 | 1 | 2 | 98% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 694 | 523 | 132 | 0 | 22 | 4 | 11 | 75% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 34 | 32 | 23 | 0 | 6 | 1 | 3 | 94% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 2 | 7 | 4 | 6 | 4 | 6 | 67% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2630 | 2551 | 86 | 0 | 3 | 1 | 2 | 97% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 207 | 171 | 123 | 0 | 29 | 3 | 9 | 83% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 115 | 115 | 12 | 0 | 1 | 0 | 1 | 100% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1862 | 1811 | 36 | 0 | 5 | 2 | 4 | 97% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 132 | 65 | 140 | 1 | 35 | 8 | 18 | 49% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 12 | 13 | 0 | 4 | 0 | 3 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 23 | 18 | 21 | 18 | 21 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1613 | 1554 | 121 | 0 | 7 | 3 | 5 | 96% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 622 | 173 | 160 | 1 | 34 | 25 | 24 | 28% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 3 | 25 | 8 | 15 | 8 | 11 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 75 | 15 | 45 | 15 | 45 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1798 | 1722 | 51 | 0 | 5 | 1 | 4 | 96% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 422 | 285 | 133 | 1 | 21 | 2 | 9 | 68% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 6 | 31 | 0 | 9 | 7 | 7 | 86% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 12 | 12 | 12 | 12 | 12 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1249 | 1220 | 23 | 0 | 3 | 1 | 2 | 98% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 1528 | 1383 | 113 | 0 | 14 | 7 | 8 | 91% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 50 | 50 | 8 | 0 | 2 | 0 | 1 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 14 | 12 | 4 | 0 | 1 | 0 | 1 | 86% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2318 | 2244 | 79 | 0 | 6 | 1 | 4 | 97% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 450 | 252 | 140 | 0 | 29 | 8 | 20 | 56% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 42 | 41 | 22 | 0 | 4 | 1 | 2 | 98% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 2 | 39 | 32 | 36 | 32 | 36 | 50% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 897 | 895 | 40 | 0 | 6 | 1 | 5 | 100% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 16423 | 13729 | 140 | 0 | 17 | 1 | 10 | 84% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 2 | 2 | 7 | 1 | 4 | 1 | 4 | 100% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 68 | 48 | 115 | 0 | 15 | 0 | 6 | 71% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 75 | 75 | 8 | 0 | 3 | 1 | 1 | 100% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3232 | 2867 | 134 | 0 | 17 | 9 | 10 | 89% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 21 | 21 | 6 | 0 | 2 | 1 | 1 | 100% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 56 | 48 | 53 | 0 | 9 | 0 | 5 | 86% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 966 | 956 | 148 | 0 | 10 | 2 | 7 | 99% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 13803 | 11273 | 149 | 0 | 30 | 4 | 23 | 82% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 2 | 2 | 15 | 13 | 14 | 13 | 14 | 100% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 46 | 32 | 144 | 0 | 24 | 0 | 6 | 70% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 186 | 185 | 52 | 0 | 11 | 7 | 7 | 99% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6425 | 5638 | 136 | 0 | 17 | 10 | 14 | 88% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 13 | 13 | 14 | 0 | 3 | 0 | 1 | 100% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 49 | 40 | 77 | 0 | 12 | 0 | 7 | 82% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2595 | 2516 | 110 | 0 | 8 | 2 | 6 | 97% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 297 | 221 | 153 | 2 | 26 | 4 | 20 | 74% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 10 | 19 | 0 | 8 | 0 | 8 | 83% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 60 | 60 | 60 | 60 | 60 | 100% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 15371 | 14894 | 104 | 0 | 9 | 2 | 6 | 97% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 586 | 469 | 116 | 0 | 19 | 5 | 12 | 80% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 30 | 29 | 41 | 0 | 9 | 1 | 7 | 97% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 7 | 141 | 8 | 31 | 10 | 10 | 78% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3271 | 3164 | 133 | 0 | 9 | 0 | 7 | 97% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 7724 | 7390 | 158 | 0 | 13 | 7 | 9 | 96% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 18 | 12 | 0 | 3 | 0 | 2 | 95% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 52 | 47 | 112 | 0 | 10 | 0 | 2 | 90% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2426 | 2425 | 41 | 0 | 6 | 2 | 5 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 7328 | 6415 | 114 | 0 | 13 | 9 | 10 | 88% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 5 | 5 | 6 | 0 | 2 | 0 | 2 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 24 | 21 | 33 | 0 | 9 | 0 | 7 | 88% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1032 | 1025 | 26 | 0 | 3 | 2 | 2 | 99% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 5406 | 5060 | 89 | 0 | 13 | 1 | 8 | 94% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 12 | 12 | 15 | 0 | 3 | 0 | 1 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 24 | 20 | 77 | 0 | 12 | 3 | 3 | 83% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2220 | 2165 | 57 | 0 | 4 | 1 | 2 | 98% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3718 | 3486 | 115 | 0 | 7 | 2 | 4 | 94% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 9 | 9 | 35 | 0 | 7 | 1 | 1 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 19 | 15 | 72 | 0 | 14 | 3 | 13 | 79% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 438 | 438 | 16 | 0 | 8 | 9 | 8 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 5650 | 4115 | 122 | 0 | 15 | 6 | 11 | 73% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 1 | 1 | 3 | 3 | 3 | 3 | 3 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 55 | 50 | 31 | 0 | 8 | 1 | 2 | 91% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 283 | 278 | 37 | 0 | 5 | 1 | 3 | 98% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3217 | 2754 | 140 | 0 | 16 | 11 | 11 | 86% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 14 | 14 | 4 | 0 | 1 | 1 | 1 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 22 | 19 | 107 | 0 | 11 | 2 | 3 | 86% |