Dashboard for New Service Connections(non AG)

Dashboard for New Service Connections(non AG) pending as on 30-Apr-2025
Application Source New connection(A1) application received Technical Feasibility Done Estimate generated but payment not received Payment received but meter not assigned Total Applications at various stages
Infra not required / Infra Completed Infra required Infra not required / Infra Completed Infra required Infra not required / Infra Completed Infra required
Aaple Sarkar 5 0 0 8 0 0 0 13
MAHAVITARAN 57,760 1,329 2,953 39,691 17,017 53,456 16,541 1,88,747
MAITRI 1,785 29 162 366 875 1,067 1,109 5,393
Total 59,550 1,358 3,115 40,065 17,892 54,523 17,650 1,94,153