Maharashtra State Electricity Distribution Co. Ltd.
| एलटी नवीन सेवा कनेक्शन (नॉन एजी) अर्जांची राज्य आकडेवारी.29-Jul-2026 रोजी तयार केलेला अहवाल | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| सेवा | इन्फ्रा स्थिती | क्षेत्र | अधिसूचित टाइमलाइन (दिवस) | प्राप्त झालेल्या अर्जांची संख्या | मंजूर अर्जांची संख्या | कमाल (दिवस) | किमान (दिवस) | मीन (दिवस) | मोड (दिवस) | मीडियन(दिवस) | अनुपालन |
| Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 117253 | 117218 | 266 | 0 | 24 | 5 | 6 | 100% |
| Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 594273 | 593685 | 313 | 0 | 28 | 11 | 15 | 100% |
| Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 109268 | 109202 | 290 | 1 | 17 | 14 | 10 | 100% |
| Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 197741 | 197466 | 304 | 0 | 32 | 2 | 7 | 100% |
| Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 117346 | 115888 | 306 | 4 | 93 | 168 | 83 | 99% |
| Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 14192 | 14117 | 246 | 2 | 87 | 184 | 121 | 99% |
| Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 2199 | 2188 | 82 | 3 | 9 | 3 | 8 | 99% |
| Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7123 | 7047 | 281 | 4 | 20 | 10 | 15 | 99% |
| Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 1527 | 1493 | 83 | 0 | 9 | 1 | 4 | 98% |
| Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1951 | 1928 | 162 | 6 | 18 | 6 | 6 | 99% |
| Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 837 | 798 | 158 | 65 | 81 | 65 | 83 | 95% |
| Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 168 | 164 | 122 | 46 | 46 | 46 | 46 | 98% |
| एल टी नवीन सेवा कनेक्शन (नॉन ए जी) अर्जांची आकडेवारी 29-Jul-2026 रोजी तयार केलेला अहवाल |
|||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| प्रभाग | परिमंडळ | मंडल | विभाग | सेवा | इन्फ्रा स्थिती | क्षेत्र | अधिसूचित टाइमलाइन (दिवस) | प्राप्त झालेल्या अर्जांची संख्या | मंजूर अर्जांची संख्या | कमाल (दिवस) | किमान (दिवस) | मीन (दिवस) | मोड (दिवस) | मीडियन(दिवस) | अनुपालन |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1930 | 1902 | 203 | 0 | 15 | 1 | 6 | 99% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6611 | 6583 | 304 | 0 | 7 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 35 | 28 | 18 | 0 | 4 | 0 | 1 | 80% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 115 | 109 | 71 | 0 | 3 | 0 | 0 | 95% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 430 | 429 | 98 | 0 | 7 | 2 | 4 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1475 | 1475 | 117 | 0 | 6 | 2 | 3 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 323 | 323 | 116 | 0 | 29 | 0 | 5 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 2308 | 2304 | 209 | 0 | 6 | 0 | 4 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 6 | 5 | 15 | 1 | 9 | 1 | 8 | 83% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 34 | 34 | 63 | 0 | 6 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 22 | 22 | 12 | 0 | 1 | 0 | 0 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 11681 | 11675 | 201 | 0 | 8 | 1 | 5 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 955 | 924 | 204 | 0 | 11 | 0 | 2 | 97% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 59 | 54 | 21 | 0 | 5 | 1 | 4 | 92% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 7 | 62 | 0 | 14 | 13 | 9 | 78% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4922 | 4917 | 267 | 0 | 8 | 2 | 5 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1140 | 1122 | 174 | 0 | 23 | 10 | 16 | 98% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 41 | 40 | 22 | 0 | 3 | 0 | 1 | 98% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 1 | 0 | 0 | 0 | 0 | 0 | 33% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3995 | 3949 | 261 | 0 | 9 | 3 | 5 | 99% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1127 | 1123 | 293 | 0 | 22 | 0 | 7 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 23 | 23 | 26 | 0 | 7 | 0 | 2 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 9 | 24 | 0 | 4 | 0 | 0 | 90% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3173 | 3161 | 99 | 0 | 6 | 2 | 4 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 120 | 113 | 160 | 0 | 44 | 25 | 39 | 94% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 8 | 11 | 0 | 4 | 3 | 3 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1903 | 1897 | 163 | 0 | 6 | 0 | 2 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 7496 | 7472 | 155 | 0 | 6 | 0 | 3 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 2 | 1 | 0 | 0 | 0 | 0 | 0 | 50% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 11 | 73 | 0 | 28 | 3 | 6 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2215 | 2203 | 199 | 0 | 9 | 0 | 3 | 99% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3456 | 3437 | 306 | 0 | 19 | 0 | 7 | 99% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 4 | 5 | 0 | 2 | 0 | 2 | 67% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 11 | 60 | 0 | 8 | 0 | 1 | 92% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1912 | 1906 | 251 | 0 | 20 | 1 | 7 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2434 | 2417 | 238 | 0 | 20 | 2 | 10 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 11 | 33 | 0 | 7 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 9 | 31 | 0 | 7 | 2 | 4 | 90% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2658 | 2633 | 234 | 0 | 13 | 1 | 6 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1284 | 1261 | 285 | 0 | 20 | 0 | 6 | 98% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 20 | 18 | 12 | 0 | 2 | 0 | 1 | 90% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 9 | 61 | 0 | 7 | 0 | 0 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3249 | 3236 | 242 | 0 | 14 | 1 | 7 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1905 | 1890 | 289 | 0 | 17 | 1 | 10 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 28 | 24 | 32 | 0 | 5 | 1 | 2 | 86% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 17 | 16 | 9 | 0 | 2 | 0 | 2 | 94% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2493 | 2483 | 227 | 0 | 28 | 4 | 10 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3392 | 3381 | 167 | 0 | 11 | 1 | 6 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 7 | 15 | 0 | 5 | 0 | 3 | 88% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 11 | 77 | 0 | 8 | 2 | 2 | 92% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1255 | 1252 | 243 | 0 | 19 | 1 | 11 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1741 | 1736 | 159 | 0 | 16 | 1 | 10 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2456 | 2456 | 195 | 0 | 14 | 1 | 9 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 2326 | 2326 | 183 | 0 | 9 | 1 | 4 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 4 | 25 | 1 | 9 | 1 | 5 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 42 | 41 | 25 | 0 | 1 | 0 | 0 | 98% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 12 | 60 | 0 | 8 | 0 | 2 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 52 | 52 | 15 | 0 | 2 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2370 | 2342 | 215 | 0 | 23 | 10 | 15 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3524 | 3493 | 300 | 0 | 26 | 3 | 16 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 9 | 7 | 15 | 0 | 4 | 1 | 1 | 78% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 9 | 30 | 0 | 8 | 0 | 3 | 82% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2662 | 2646 | 180 | 0 | 13 | 0 | 7 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2552 | 2546 | 213 | 0 | 20 | 5 | 14 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 16 | 16 | 31 | 0 | 6 | 0 | 2 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 6 | 39 | 1 | 12 | 1 | 8 | 86% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6275 | 6250 | 310 | 0 | 12 | 2 | 5 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 146 | 141 | 186 | 0 | 16 | 0 | 6 | 97% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 25 | 17 | 43 | 0 | 9 | 1 | 4 | 68% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 11 | 0 | 6 | 0 | 6 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4193 | 4156 | 252 | 0 | 11 | 1 | 5 | 99% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 107 | 97 | 201 | 0 | 33 | 39 | 18 | 91% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 20 | 15 | 37 | 0 | 10 | 1 | 5 | 75% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 2 | 0 | 1 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5644 | 5619 | 307 | 0 | 19 | 4 | 10 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 70 | 66 | 112 | 0 | 28 | 28 | 22 | 94% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 9 | 9 | 8 | 0 | 3 | 1 | 2 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 406 | 405 | 129 | 0 | 16 | 5 | 7 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 6726 | 6713 | 242 | 0 | 12 | 0 | 7 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2 | 2 | 20 | 4 | 12 | 4 | 12 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 44 | 44 | 62 | 0 | 16 | 0 | 8 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 4 | 9 | 4 | 5 | 4 | 4 | 80% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 22 | 21 | 31 | 0 | 7 | 1 | 4 | 95% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2822 | 2820 | 205 | 0 | 11 | 3 | 4 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 342 | 339 | 115 | 0 | 14 | 5 | 9 | 99% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 46 | 44 | 35 | 0 | 2 | 0 | 1 | 96% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3486 | 3470 | 292 | 0 | 27 | 1 | 10 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2186 | 2181 | 267 | 0 | 17 | 2 | 8 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 65 | 46 | 203 | 0 | 23 | 0 | 8 | 71% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 8 | 8 | 40 | 0 | 15 | 0 | 13 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 6 | 103 | 0 | 20 | 0 | 4 | 86% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 21 | 19 | 81 | 0 | 9 | 0 | 1 | 90% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 8 | 8 | 8 | 8 | 8 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3858 | 3853 | 278 | 0 | 15 | 0 | 7 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 72 | 68 | 63 | 0 | 15 | 11 | 11 | 94% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 13 | 9 | 48 | 0 | 10 | 0 | 4 | 69% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 2 | 1 | 0 | 1 | 0 | 1 | 67% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6449 | 6449 | 261 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 485 | 483 | 234 | 0 | 21 | 2 | 13 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 232 | 232 | 57 | 0 | 8 | 1 | 5 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 16 | 16 | 110 | 0 | 28 | 0 | 6 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4492 | 4492 | 67 | 0 | 4 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 219 | 217 | 117 | 0 | 38 | 84 | 23 | 99% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 224 | 224 | 28 | 0 | 4 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 8 | 64 | 0 | 23 | 2 | 5 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 16184 | 16184 | 137 | 0 | 6 | 2 | 4 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1691 | 1673 | 216 | 0 | 11 | 1 | 4 | 99% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 150 | 150 | 86 | 0 | 10 | 0 | 6 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 12 | 84 | 0 | 23 | 17 | 14 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5903 | 5902 | 61 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 316 | 309 | 218 | 0 | 22 | 3 | 10 | 98% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 141 | 141 | 33 | 0 | 3 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 9 | 42 | 1 | 20 | 4 | 18 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 986 | 986 | 63 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6711 | 6710 | 150 | 0 | 6 | 1 | 3 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 63 | 63 | 9 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 141 | 141 | 84 | 0 | 4 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 475 | 475 | 10 | 0 | 1 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6293 | 6293 | 61 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 58 | 58 | 5 | 0 | 1 | 0 | 0 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 183 | 183 | 42 | 0 | 2 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 881 | 881 | 34 | 0 | 1 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 646 | 646 | 260 | 0 | 3 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 79 | 79 | 14 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 75 | 75 | 25 | 0 | 1 | 0 | 0 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 862 | 862 | 9 | 0 | 1 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 4613 | 4612 | 154 | 0 | 9 | 0 | 3 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 72 | 72 | 7 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 110 | 110 | 44 | 0 | 5 | 0 | 0 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1468 | 1468 | 15 | 0 | 1 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 10599 | 10595 | 248 | 0 | 5 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 103 | 103 | 6 | 0 | 1 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 111 | 111 | 75 | 0 | 4 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 8067 | 8067 | 266 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3235 | 3233 | 156 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 391 | 391 | 37 | 0 | 2 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 78 | 78 | 28 | 0 | 2 | 0 | 0 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 4303 | 4303 | 26 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7096 | 7096 | 72 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 5501 | 5498 | 244 | 0 | 11 | 1 | 3 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 10133 | 10128 | 126 | 0 | 5 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 146 | 146 | 58 | 0 | 2 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 149 | 149 | 38 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 169 | 169 | 90 | 0 | 5 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 137 | 137 | 46 | 0 | 5 | 0 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2399 | 2399 | 98 | 0 | 3 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 7335 | 7333 | 114 | 0 | 5 | 1 | 3 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 65 | 65 | 82 | 0 | 9 | 2 | 3 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 291 | 291 | 150 | 0 | 7 | 0 | 1 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4987 | 4980 | 248 | 0 | 16 | 1 | 8 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 144 | 117 | 167 | 0 | 28 | 0 | 1 | 81% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 4 | 2 | 1 | 2 | 1 | 2 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2959 | 2954 | 278 | 0 | 18 | 0 | 10 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2654 | 2638 | 276 | 0 | 15 | 1 | 5 | 99% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 86 | 80 | 151 | 0 | 37 | 0 | 26 | 93% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 34 | 32 | 96 | 0 | 14 | 5 | 5 | 94% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 8 | 50 | 0 | 16 | 0 | 15 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 22 | 21 | 41 | 0 | 3 | 0 | 1 | 95% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3977 | 3976 | 178 | 0 | 11 | 1 | 6 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 531 | 520 | 102 | 0 | 12 | 0 | 5 | 98% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 42 | 41 | 60 | 0 | 3 | 0 | 0 | 98% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4393 | 4389 | 281 | 0 | 12 | 2 | 8 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 249 | 231 | 183 | 0 | 37 | 22 | 27 | 93% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 22 | 22 | 25 | 0 | 8 | 0 | 2 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 46 | 46 | 46 | 46 | 46 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4016 | 4015 | 213 | 0 | 9 | 1 | 4 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 149 | 149 | 190 | 0 | 28 | 0 | 17 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 19 | 49 | 0 | 6 | 0 | 1 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6200 | 6183 | 274 | 0 | 18 | 3 | 10 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 201 | 185 | 169 | 0 | 31 | 1 | 17 | 92% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 32 | 30 | 30 | 0 | 7 | 3 | 4 | 94% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 50 | 50 | 50 | 50 | 50 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2134 | 2119 | 288 | 0 | 25 | 5 | 11 | 99% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 4097 | 4090 | 234 | 0 | 8 | 0 | 3 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 66 | 54 | 185 | 1 | 93 | 168 | 83 | 82% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 388 | 366 | 187 | 0 | 50 | 17 | 43 | 94% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 4 | 15 | 0 | 5 | 0 | 2 | 80% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 171 | 162 | 49 | 0 | 3 | 0 | 1 | 95% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 65 | 65 | 65 | 65 | 65 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 2 | 1 | 0 | 0 | 0 | 0 | 0 | 50% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2171 | 2167 | 299 | 0 | 17 | 3 | 10 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 142 | 106 | 272 | 0 | 43 | 35 | 35 | 75% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 3 | 9 | 2 | 6 | 2 | 7 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 13 | 13 | 13 | 13 | 13 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3605 | 3594 | 244 | 0 | 16 | 2 | 9 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 41 | 36 | 143 | 0 | 47 | 0 | 35 | 88% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 14 | 43 | 0 | 8 | 0 | 3 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3937 | 3935 | 137 | 0 | 9 | 3 | 6 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 88 | 87 | 204 | 0 | 38 | 26 | 26 | 99% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 7 | 18 | 0 | 6 | 4 | 4 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 5 | 3 | 1 | 1 | 1 | 1 | 100% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3242 | 3214 | 280 | 0 | 14 | 3 | 8 | 99% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 196 | 186 | 188 | 0 | 33 | 2 | 14 | 95% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 48 | 47 | 42 | 0 | 7 | 0 | 3 | 98% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3014 | 2998 | 200 | 0 | 6 | 0 | 2 | 99% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1266 | 1259 | 193 | 0 | 71 | 42 | 45 | 99% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 27 | 27 | 16 | 0 | 2 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 4152 | 4152 | 61 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 498 | 498 | 22 | 0 | 4 | 1 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 186 | 186 | 30 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 5 | 5 | 2 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 23499 | 23499 | 101 | 0 | 3 | 1 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 1420 | 1388 | 275 | 0 | 8 | 1 | 2 | 98% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 162 | 162 | 76 | 0 | 6 | 0 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 6 | 4 | 6 | 0 | 2 | 1 | 1 | 67% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 6762 | 6762 | 160 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 957 | 956 | 80 | 0 | 6 | 0 | 5 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 103 | 103 | 55 | 0 | 2 | 0 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 1 | 6 | 6 | 6 | 6 | 6 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 13748 | 13748 | 250 | 0 | 4 | 2 | 3 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 185 | 183 | 181 | 0 | 15 | 3 | 4 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 159 | 159 | 60 | 0 | 6 | 3 | 3 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 17103 | 17103 | 128 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 196 | 195 | 201 | 0 | 15 | 1 | 5 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 51 | 51 | 118 | 0 | 10 | 1 | 4 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3230 | 3230 | 279 | 0 | 5 | 2 | 3 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 32 | 32 | 167 | 2 | 87 | 121 | 121 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 26 | 26 | 27 | 0 | 4 | 0 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 6248 | 6248 | 101 | 0 | 2 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 333 | 333 | 111 | 0 | 6 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 89 | 89 | 15 | 0 | 3 | 0 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 17 | 17 | 122 | 0 | 7 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 28769 | 28769 | 219 | 0 | 6 | 1 | 3 | 100% |
| KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 11757 | 11669 | 202 | 0 | 17 | 1 | 10 | 99% |
| KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 466 | 466 | 80 | 0 | 7 | 0 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 15 | 15 | 89 | 0 | 11 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3385 | 3385 | 207 | 0 | 9 | 3 | 6 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 23281 | 23281 | 128 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 289 | 282 | 306 | 0 | 16 | 0 | 1 | 98% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 1100 | 1099 | 186 | 0 | 15 | 2 | 4 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 53 | 53 | 65 | 0 | 14 | 2 | 9 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 139 | 139 | 33 | 0 | 4 | 0 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 6 | 32 | 0 | 10 | 0 | 6 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 13 | 12 | 18 | 0 | 5 | 0 | 1 | 92% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 23759 | 23759 | 143 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 627 | 624 | 196 | 0 | 53 | 1 | 7 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 286 | 286 | 47 | 0 | 3 | 0 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 5 | 5 | 27 | 0 | 11 | 0 | 7 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3314 | 3314 | 226 | 0 | 8 | 1 | 3 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 816 | 801 | 244 | 0 | 58 | 5 | 50 | 98% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 39 | 39 | 121 | 0 | 16 | 0 | 6 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 3 | 3 | 3 | 3 | 3 | 50% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3580 | 3580 | 118 | 0 | 5 | 1 | 3 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 478 | 454 | 250 | 0 | 46 | 6 | 27 | 95% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 116 | 116 | 83 | 0 | 11 | 1 | 7 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 5 | 82 | 0 | 17 | 0 | 2 | 56% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5978 | 5978 | 262 | 0 | 6 | 1 | 4 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 778 | 718 | 272 | 0 | 68 | 2 | 41 | 92% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 303 | 301 | 85 | 0 | 8 | 0 | 4 | 99% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 30 | 28 | 79 | 0 | 10 | 0 | 5 | 93% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3765 | 3765 | 204 | 0 | 7 | 1 | 4 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 414 | 406 | 184 | 0 | 38 | 5 | 27 | 98% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 242 | 241 | 281 | 0 | 16 | 0 | 5 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 22 | 15 | 96 | 0 | 21 | 0 | 13 | 68% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3729 | 3729 | 236 | 0 | 10 | 1 | 5 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 433 | 423 | 279 | 0 | 34 | 3 | 16 | 98% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 266 | 265 | 177 | 0 | 14 | 1 | 7 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 22 | 20 | 99 | 0 | 25 | 0 | 8 | 91% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5073 | 5062 | 176 | 0 | 12 | 4 | 8 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 272 | 269 | 126 | 0 | 21 | 0 | 7 | 99% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 10 | 9 | 24 | 2 | 9 | 6 | 6 | 90% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3419 | 3402 | 251 | 0 | 8 | 1 | 4 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 6439 | 6430 | 290 | 0 | 8 | 1 | 5 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 499 | 483 | 111 | 0 | 12 | 0 | 2 | 97% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 136 | 124 | 132 | 0 | 31 | 0 | 13 | 91% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 14 | 12 | 0 | 3 | 0 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 57 | 55 | 31 | 0 | 4 | 1 | 1 | 96% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 9 | 18 | 0 | 4 | 0 | 0 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 1 | 1 | 46 | 46 | 46 | 46 | 46 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3390 | 3376 | 175 | 0 | 7 | 0 | 3 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 417 | 401 | 244 | 0 | 22 | 0 | 12 | 96% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 6 | 2 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 8358 | 8351 | 223 | 0 | 6 | 0 | 4 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1028 | 1020 | 126 | 0 | 8 | 0 | 3 | 99% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 59 | 56 | 27 | 0 | 4 | 0 | 2 | 95% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 4 | 2 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5140 | 5140 | 120 | 0 | 6 | 1 | 4 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 327 | 324 | 148 | 0 | 15 | 0 | 7 | 99% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 16 | 13 | 12 | 0 | 1 | 0 | 0 | 81% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2564 | 2564 | 148 | 0 | 4 | 1 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 156 | 154 | 177 | 0 | 28 | 0 | 3 | 99% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 62 | 62 | 18 | 0 | 3 | 2 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2479 | 2473 | 165 | 0 | 18 | 11 | 13 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 133 | 122 | 108 | 1 | 26 | 7 | 18 | 92% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 28 | 4 | 14 | 9 | 9 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 9 | 9 | 9 | 9 | 9 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3307 | 3300 | 242 | 0 | 15 | 3 | 11 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 60 | 56 | 139 | 0 | 18 | 0 | 8 | 93% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 16 | 68 | 0 | 10 | 1 | 2 | 84% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1937 | 1937 | 213 | 0 | 7 | 0 | 4 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 114 | 113 | 170 | 0 | 20 | 0 | 9 | 99% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 14 | 9 | 0 | 2 | 2 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4020 | 4020 | 51 | 0 | 5 | 2 | 4 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 296 | 288 | 171 | 0 | 19 | 0 | 7 | 97% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 65 | 64 | 41 | 0 | 3 | 0 | 2 | 98% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 19 | 19 | 55 | 0 | 5 | 3 | 3 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 8334 | 8331 | 281 | 0 | 6 | 1 | 3 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1275 | 1232 | 217 | 0 | 14 | 0 | 5 | 97% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 95 | 91 | 44 | 0 | 4 | 0 | 2 | 96% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 1 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 8513 | 8513 | 28 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 360 | 357 | 120 | 0 | 7 | 0 | 0 | 99% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 121 | 121 | 6 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 3 | 3 | 2 | 2 | 2 | 2 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 17015 | 17009 | 103 | 0 | 1 | 1 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7271 | 7267 | 112 | 0 | 6 | 1 | 3 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 1655 | 1635 | 139 | 0 | 4 | 0 | 0 | 99% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1261 | 1257 | 165 | 0 | 4 | 0 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 120 | 117 | 58 | 0 | 1 | 0 | 0 | 98% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 69 | 61 | 72 | 0 | 3 | 0 | 1 | 88% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 10 | 8 | 1 | 0 | 0 | 0 | 0 | 80% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 25 | 23 | 15 | 0 | 2 | 0 | 1 | 92% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4922 | 4916 | 265 | 0 | 15 | 1 | 9 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 184 | 163 | 273 | 0 | 59 | 0 | 33 | 89% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 25 | 25 | 76 | 0 | 12 | 0 | 8 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 26 | 26 | 26 | 26 | 26 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3236 | 3236 | 166 | 0 | 9 | 2 | 5 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 292 | 284 | 225 | 0 | 76 | 184 | 53 | 97% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 88 | 88 | 83 | 0 | 2 | 0 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2800 | 2799 | 283 | 0 | 10 | 2 | 5 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 140 | 129 | 233 | 0 | 52 | 71 | 43 | 92% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 21 | 21 | 25 | 0 | 4 | 0 | 2 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4692 | 4691 | 233 | 0 | 8 | 0 | 4 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 345 | 341 | 195 | 0 | 29 | 0 | 21 | 99% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 41 | 41 | 31 | 0 | 2 | 0 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 6 | 6 | 6 | 6 | 6 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5287 | 5283 | 245 | 0 | 12 | 1 | 5 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 542 | 531 | 219 | 0 | 31 | 38 | 19 | 98% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 72 | 72 | 11 | 0 | 2 | 0 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 4 | 45 | 0 | 11 | 0 | 0 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4488 | 4473 | 234 | 0 | 13 | 0 | 6 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 201 | 185 | 217 | 0 | 55 | 97 | 40 | 92% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 17 | 17 | 13 | 0 | 3 | 1 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 4 | 4 | 4 | 4 | 4 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6152 | 6142 | 299 | 0 | 13 | 0 | 6 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 388 | 356 | 257 | 0 | 68 | 10 | 51 | 92% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 27 | 27 | 28 | 0 | 5 | 0 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 8438 | 8396 | 313 | 0 | 17 | 4 | 10 | 100% |
| NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 250 | 222 | 246 | 0 | 47 | 0 | 21 | 89% |
| NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 23 | 23 | 127 | 0 | 10 | 0 | 1 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7789 | 7789 | 200 | 0 | 7 | 1 | 4 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 241 | 227 | 194 | 0 | 39 | 20 | 28 | 94% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 73 | 73 | 40 | 0 | 4 | 1 | 2 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4577 | 4573 | 259 | 0 | 6 | 1 | 3 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 438 | 422 | 223 | 0 | 19 | 0 | 1 | 96% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 48 | 46 | 27 | 0 | 3 | 0 | 1 | 96% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 3 | 0 | 0 | 0 | 0 | 0 | 75% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 5700 | 5690 | 217 | 0 | 8 | 0 | 3 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 481 | 475 | 172 | 0 | 42 | 0 | 23 | 99% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 80 | 80 | 20 | 0 | 2 | 0 | 1 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 4 | 4 | 3 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3044 | 3044 | 248 | 0 | 4 | 2 | 3 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 160 | 160 | 93 | 0 | 23 | 0 | 20 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 27 | 27 | 8 | 0 | 2 | 1 | 1 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 2 | 1 | 2 | 1 | 2 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6811 | 6811 | 189 | 0 | 6 | 1 | 4 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 142 | 139 | 166 | 0 | 35 | 35 | 35 | 98% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 22 | 22 | 20 | 0 | 4 | 1 | 2 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 3 | 33 | 1 | 15 | 1 | 11 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4923 | 4923 | 189 | 0 | 7 | 3 | 5 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 140 | 132 | 157 | 0 | 42 | 1 | 23 | 94% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 55 | 55 | 20 | 0 | 5 | 0 | 3 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7048 | 7043 | 215 | 0 | 11 | 5 | 8 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 148 | 144 | 191 | 0 | 55 | 0 | 34 | 97% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 28 | 28 | 35 | 0 | 7 | 10 | 5 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4178 | 4171 | 257 | 0 | 12 | 1 | 4 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 128 | 107 | 237 | 0 | 40 | 0 | 15 | 84% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 58 | 57 | 52 | 0 | 3 | 0 | 1 | 98% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4330 | 4330 | 257 | 0 | 7 | 5 | 6 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 167 | 161 | 193 | 0 | 30 | 8 | 10 | 96% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 74 | 74 | 19 | 0 | 3 | 1 | 1 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 3 | 1 | 0 | 0 | 0 | 0 | 60% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2035 | 2034 | 127 | 0 | 7 | 0 | 5 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2273 | 2273 | 119 | 0 | 5 | 2 | 4 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 94 | 92 | 237 | 0 | 47 | 0 | 25 | 98% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 148 | 137 | 171 | 0 | 31 | 4 | 13 | 93% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 55 | 54 | 15 | 0 | 2 | 0 | 1 | 98% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 107 | 89 | 32 | 0 | 3 | 0 | 1 | 83% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 4 | 2 | 3 | 1 | 2 | 1 | 2 | 50% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3069 | 3069 | 174 | 0 | 7 | 5 | 6 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 204 | 194 | 256 | 0 | 25 | 0 | 8 | 95% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 43 | 43 | 32 | 0 | 6 | 2 | 4 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 3 | 2 | 3 | 2 | 3 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5131 | 5129 | 183 | 0 | 10 | 4 | 6 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 129 | 118 | 152 | 0 | 14 | 1 | 2 | 91% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 102 | 102 | 54 | 0 | 4 | 0 | 1 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 35 | 35 | 35 | 35 | 35 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2699 | 2699 | 91 | 0 | 2 | 1 | 2 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 197 | 193 | 174 | 0 | 17 | 0 | 5 | 98% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 85 | 85 | 13 | 0 | 2 | 1 | 1 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 6 | 3 | 0 | 1 | 0 | 0 | 86% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3834 | 3834 | 78 | 0 | 5 | 2 | 4 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 82 | 78 | 129 | 0 | 17 | 0 | 7 | 95% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 412 | 411 | 64 | 0 | 8 | 1 | 4 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 21 | 21 | 39 | 0 | 6 | 0 | 2 | 100% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5137 | 5137 | 177 | 0 | 6 | 1 | 4 | 100% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 287 | 275 | 171 | 0 | 32 | 0 | 24 | 96% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 111 | 111 | 186 | 0 | 6 | 0 | 1 | 100% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1728 | 1728 | 36 | 0 | 3 | 1 | 2 | 100% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 145 | 139 | 182 | 0 | 36 | 0 | 25 | 96% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 27 | 27 | 25 | 0 | 3 | 2 | 2 | 100% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2944 | 2944 | 175 | 0 | 7 | 2 | 4 | 100% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 316 | 308 | 209 | 0 | 28 | 2 | 10 | 97% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 81 | 81 | 17 | 0 | 2 | 0 | 1 | 100% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 36 | 2 | 19 | 2 | 19 | 100% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5076 | 5071 | 149 | 0 | 6 | 2 | 4 | 100% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 195 | 176 | 196 | 0 | 39 | 0 | 26 | 90% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 129 | 129 | 29 | 0 | 2 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1971 | 1971 | 107 | 0 | 4 | 1 | 3 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 105 | 104 | 110 | 0 | 10 | 0 | 2 | 99% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 36 | 36 | 11 | 0 | 1 | 0 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7952 | 7951 | 183 | 0 | 5 | 0 | 3 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 204 | 189 | 245 | 0 | 29 | 1 | 7 | 93% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 88 | 88 | 32 | 0 | 5 | 0 | 4 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 12 | 54 | 0 | 12 | 2 | 7 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3445 | 3445 | 94 | 0 | 4 | 2 | 3 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 240 | 233 | 217 | 0 | 21 | 0 | 3 | 97% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 115 | 115 | 15 | 0 | 2 | 0 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 13 | 13 | 12 | 0 | 3 | 2 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2927 | 2927 | 15 | 0 | 2 | 1 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 106 | 98 | 131 | 0 | 31 | 0 | 23 | 92% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 167 | 167 | 17 | 0 | 1 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 8 | 23 | 0 | 8 | 2 | 3 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 895 | 895 | 11 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5647 | 5647 | 237 | 0 | 4 | 1 | 3 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 218 | 218 | 82 | 0 | 10 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 284 | 275 | 144 | 0 | 14 | 2 | 5 | 97% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 9 | 9 | 5 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 134 | 134 | 31 | 0 | 3 | 1 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 3 | 3 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 14 | 13 | 20 | 0 | 4 | 0 | 2 | 93% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 4897 | 4897 | 90 | 0 | 1 | 0 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 1873 | 1873 | 87 | 0 | 2 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 56 | 56 | 17 | 0 | 1 | 0 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 27 | 27 | 7 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 3724 | 3724 | 38 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6700 | 6700 | 98 | 0 | 2 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 169 | 166 | 78 | 0 | 13 | 0 | 6 | 98% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 354 | 354 | 172 | 0 | 15 | 0 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 164 | 164 | 21 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 64 | 64 | 7 | 0 | 1 | 0 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 2 | 1 | 0 | 0 | 0 | 0 | 0 | 50% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 45 | 0 | 23 | 0 | 23 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 4863 | 4863 | 132 | 0 | 1 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 46 | 46 | 227 | 0 | 24 | 2 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 67 | 67 | 30 | 0 | 2 | 0 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 6701 | 6701 | 169 | 0 | 1 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 433 | 433 | 189 | 0 | 32 | 1 | 7 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 98 | 98 | 18 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 1 | 6 | 6 | 6 | 6 | 6 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1961 | 1961 | 77 | 0 | 4 | 1 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 166 | 158 | 151 | 0 | 24 | 1 | 11 | 95% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 35 | 35 | 16 | 0 | 2 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 6 | 1 | 4 | 1 | 4 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2473 | 2473 | 36 | 0 | 3 | 2 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 148 | 126 | 155 | 0 | 34 | 2 | 24 | 85% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 15 | 10 | 0 | 5 | 1 | 4 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4087 | 4087 | 231 | 0 | 4 | 1 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 268 | 252 | 184 | 0 | 19 | 0 | 4 | 94% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 119 | 119 | 11 | 0 | 2 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 4 | 0 | 2 | 0 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6086 | 6086 | 172 | 0 | 7 | 2 | 5 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3042 | 3020 | 242 | 0 | 11 | 2 | 3 | 99% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 22 | 22 | 42 | 0 | 9 | 0 | 5 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 16 | 0 | 7 | 0 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7832 | 7832 | 213 | 0 | 7 | 1 | 5 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1886 | 1851 | 240 | 0 | 17 | 1 | 4 | 98% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 56 | 56 | 58 | 0 | 12 | 0 | 8 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 19 | 17 | 45 | 0 | 16 | 3 | 5 | 89% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2448 | 2448 | 245 | 0 | 7 | 1 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1485 | 1465 | 213 | 0 | 16 | 1 | 4 | 99% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 11 | 45 | 0 | 10 | 0 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 59 | 6 | 33 | 6 | 33 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6067 | 6067 | 175 | 0 | 5 | 1 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 897 | 883 | 242 | 0 | 15 | 1 | 3 | 98% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 43 | 43 | 19 | 0 | 2 | 1 | 1 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 130 | 0 | 20 | 1 | 1 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4568 | 4568 | 137 | 0 | 4 | 1 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 816 | 778 | 233 | 0 | 14 | 1 | 3 | 95% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 38 | 38 | 19 | 0 | 2 | 0 | 1 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 8 | 61 | 0 | 13 | 0 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5460 | 5460 | 139 | 0 | 4 | 1 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2718 | 2707 | 212 | 0 | 7 | 0 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 106 | 106 | 16 | 0 | 3 | 0 | 1 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 20 | 20 | 20 | 0 | 4 | 0 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3540 | 3540 | 169 | 0 | 7 | 2 | 5 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 496 | 489 | 230 | 0 | 54 | 77 | 49 | 99% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 86 | 86 | 23 | 0 | 6 | 1 | 1 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 4 | 158 | 1 | 81 | 1 | 83 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3003 | 3003 | 184 | 0 | 6 | 1 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 293 | 273 | 252 | 0 | 35 | 6 | 25 | 93% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 42 | 42 | 45 | 0 | 5 | 0 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 6 | 8 | 0 | 3 | 0 | 0 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4114 | 4114 | 147 | 0 | 4 | 1 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 469 | 452 | 242 | 0 | 68 | 2 | 35 | 96% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 11 | 31 | 0 | 7 | 1 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 36 | 0 | 5 | 0 | 0 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6452 | 6450 | 238 | 0 | 9 | 2 | 6 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1162 | 1124 | 271 | 0 | 34 | 5 | 16 | 97% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 36 | 36 | 197 | 0 | 12 | 1 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 5 | 20 | 5 | 11 | 5 | 11 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6119 | 6119 | 160 | 0 | 5 | 1 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1866 | 1858 | 232 | 0 | 19 | 0 | 9 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 76 | 76 | 14 | 0 | 4 | 0 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 16 | 16 | 154 | 0 | 16 | 0 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6057 | 6057 | 138 | 0 | 7 | 1 | 5 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1877 | 1870 | 232 | 0 | 20 | 2 | 10 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 33 | 33 | 31 | 0 | 7 | 0 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 8 | 84 | 2 | 24 | 2 | 14 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 5840 | 5839 | 108 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 2187 | 2184 | 194 | 0 | 8 | 1 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 101 | 101 | 54 | 0 | 2 | 0 | 0 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 21 | 21 | 3 | 0 | 1 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3043 | 3043 | 17 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1029 | 1007 | 206 | 0 | 28 | 2 | 15 | 98% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 57 | 57 | 15 | 0 | 3 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 10 | 71 | 0 | 16 | 0 | 5 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1293 | 1293 | 10 | 0 | 1 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2171 | 2171 | 18 | 0 | 1 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 221 | 220 | 154 | 0 | 19 | 0 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 349 | 349 | 204 | 0 | 15 | 1 | 4 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 14 | 10 | 1 | 3 | 1 | 3 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 15 | 15 | 4 | 0 | 1 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 5 | 5 | 5 | 5 | 5 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 8 | 8 | 48 | 0 | 9 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4404 | 4404 | 154 | 0 | 2 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 728 | 725 | 164 | 0 | 20 | 1 | 7 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 71 | 71 | 9 | 0 | 2 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 3 | 0 | 0 | 0 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6436 | 6436 | 55 | 0 | 2 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 571 | 559 | 249 | 0 | 50 | 1 | 47 | 98% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 46 | 46 | 15 | 0 | 3 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7552 | 7552 | 18 | 0 | 2 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1279 | 1276 | 143 | 0 | 16 | 1 | 4 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 67 | 67 | 12 | 0 | 3 | 1 | 3 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 8 | 38 | 0 | 7 | 0 | 3 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 5059 | 5059 | 59 | 0 | 2 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 359 | 358 | 165 | 0 | 25 | 0 | 4 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 155 | 155 | 58 | 0 | 1 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 2 | 2 | 2 | 0 | 1 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4071 | 4071 | 125 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 242 | 239 | 229 | 0 | 44 | 2 | 28 | 99% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 28 | 28 | 11 | 0 | 2 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3501 | 3501 | 83 | 0 | 4 | 2 | 3 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 837 | 837 | 276 | 0 | 66 | 5 | 53 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 31 | 31 | 17 | 0 | 2 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 9 | 9 | 9 | 9 | 9 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3671 | 3671 | 104 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 976 | 966 | 212 | 0 | 21 | 1 | 5 | 99% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 11 | 21 | 0 | 5 | 0 | 4 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 3 | 0 | 2 | 0 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3112 | 3112 | 28 | 0 | 2 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 2865 | 2864 | 246 | 0 | 9 | 1 | 4 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 66 | 66 | 5 | 0 | 1 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 16 | 16 | 2 | 0 | 0 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4732 | 4732 | 137 | 0 | 4 | 1 | 3 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 913 | 904 | 266 | 0 | 28 | 5 | 16 | 99% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 84 | 84 | 36 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 8 | 38 | 0 | 13 | 0 | 10 | 89% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 961 | 961 | 232 | 0 | 24 | 1 | 3 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 33994 | 33943 | 260 | 0 | 7 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 3 | 3 | 4 | 0 | 1 | 0 | 0 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 95 | 94 | 110 | 0 | 14 | 0 | 2 | 99% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 187 | 187 | 88 | 0 | 3 | 3 | 2 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6781 | 6780 | 162 | 0 | 7 | 1 | 3 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 23 | 23 | 4 | 0 | 1 | 1 | 1 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 102 | 102 | 93 | 0 | 18 | 0 | 4 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1176 | 1176 | 155 | 0 | 7 | 0 | 3 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 34062 | 33950 | 217 | 0 | 6 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 2 | 2 | 9 | 3 | 6 | 3 | 6 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 81 | 76 | 91 | 0 | 12 | 0 | 2 | 94% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 604 | 604 | 36 | 0 | 4 | 1 | 3 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 41 | 41 | 36 | 1 | 8 | 14 | 6 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 10573 | 10573 | 178 | 0 | 7 | 1 | 3 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 175 | 174 | 125 | 0 | 14 | 3 | 8 | 99% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 8 | 8 | 9 | 0 | 2 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 6 | 6 | 1 | 0 | 0 | 0 | 0 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 89 | 85 | 162 | 0 | 15 | 0 | 0 | 96% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5990 | 5988 | 109 | 0 | 5 | 1 | 3 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 447 | 436 | 254 | 0 | 15 | 0 | 3 | 98% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 19 | 12 | 0 | 5 | 0 | 5 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 6 | 20 | 0 | 6 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 32154 | 32154 | 223 | 0 | 5 | 1 | 3 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2612 | 2599 | 285 | 0 | 9 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 51 | 51 | 15 | 0 | 4 | 1 | 4 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 10 | 96 | 0 | 12 | 0 | 2 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 12791 | 12791 | 201 | 0 | 6 | 1 | 4 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 13514 | 13505 | 152 | 0 | 2 | 0 | 0 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 39 | 39 | 16 | 0 | 4 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 73 | 73 | 25 | 0 | 1 | 0 | 0 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2458 | 2458 | 27 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 16414 | 16408 | 227 | 0 | 3 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 6 | 6 | 4 | 0 | 1 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 43 | 43 | 101 | 0 | 15 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2306 | 2306 | 26 | 0 | 2 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 12103 | 12098 | 210 | 0 | 4 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 17 | 17 | 11 | 0 | 2 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 44 | 42 | 37 | 0 | 4 | 0 | 1 | 95% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 5285 | 5285 | 118 | 0 | 3 | 1 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6166 | 6166 | 158 | 0 | 4 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 17 | 17 | 20 | 0 | 4 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 35 | 35 | 103 | 0 | 15 | 1 | 4 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 770 | 770 | 50 | 0 | 5 | 5 | 5 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 11070 | 11070 | 207 | 0 | 8 | 1 | 4 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 93 | 93 | 75 | 0 | 7 | 0 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 684 | 684 | 152 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 7082 | 7082 | 164 | 0 | 5 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 18 | 18 | 7 | 0 | 2 | 1 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 37 | 37 | 72 | 0 | 6 | 0 | 2 | 100% |
| एलटी न्यू सर्व्हिस कनेक्शन (नॉन एजी) अर्जांची माहिती | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| सेवा प्रकार | अर्ज ओळख क्रमांक | पायाभूत सुविधांची स्थिती | अर्जाची तारीख | पावतीची तारीख | पुरवठ्याची तारीख | सुरक्षा ठेव रक्कम | प्रक्रिया शुल्काची रक्कम | जीएसटी रक्कम | एकूण रक्कम |