Maharashtra State Electricity Distribution Co. Ltd.
| एलटी नवीन सेवा कनेक्शन (नॉन एजी) अर्जांची राज्य आकडेवारी.26-Sep-2026 रोजी तयार केलेला अहवाल | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| सेवा | इन्फ्रा स्थिती | क्षेत्र | अधिसूचित टाइमलाइन (दिवस) | प्राप्त झालेल्या अर्जांची संख्या | मंजूर अर्जांची संख्या | कमाल (दिवस) | किमान (दिवस) | मीन (दिवस) | मोड (दिवस) | मीडियन(दिवस) | अनुपालन |
| Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 117370 | 117357 | 285 | 0 | 24 | 5 | 7 | 100% |
| Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 596837 | 596052 | 339 | 0 | 32 | 11 | 16 | 100% |
| Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 109548 | 109496 | 318 | 1 | 19 | 14 | 10 | 100% |
| Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 198438 | 198326 | 322 | 0 | 32 | 2 | 7 | 100% |
| Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 118142 | 117087 | 351 | 4 | 96 | 168 | 105 | 99% |
| Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 14447 | 14404 | 304 | 2 | 90 | 184 | 121 | 100% |
| Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 2198 | 2191 | 82 | 3 | 9 | 3 | 8 | 100% |
| Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7125 | 7062 | 281 | 4 | 20 | 10 | 15 | 99% |
| Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 1526 | 1494 | 83 | 0 | 9 | 1 | 4 | 98% |
| Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1952 | 1940 | 265 | 6 | 18 | 6 | 6 | 99% |
| Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 836 | 802 | 280 | 65 | 81 | 65 | 83 | 96% |
| Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 168 | 164 | 122 | 46 | 46 | 46 | 46 | 98% |
| एल टी नवीन सेवा कनेक्शन (नॉन ए जी) अर्जांची आकडेवारी 26-Sep-2026 रोजी तयार केलेला अहवाल |
|||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| प्रभाग | परिमंडळ | मंडल | विभाग | सेवा | इन्फ्रा स्थिती | क्षेत्र | अधिसूचित टाइमलाइन (दिवस) | प्राप्त झालेल्या अर्जांची संख्या | मंजूर अर्जांची संख्या | कमाल (दिवस) | किमान (दिवस) | मीन (दिवस) | मोड (दिवस) | मीडियन(दिवस) | अनुपालन |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1984 | 1978 | 285 | 0 | 18 | 1 | 7 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6668 | 6651 | 304 | 0 | 8 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 34 | 29 | 18 | 0 | 4 | 0 | 1 | 85% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 115 | 109 | 71 | 0 | 3 | 0 | 0 | 95% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 431 | 431 | 124 | 0 | 7 | 2 | 4 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1482 | 1482 | 132 | 0 | 6 | 2 | 3 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 323 | 323 | 116 | 0 | 29 | 0 | 5 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 2317 | 2312 | 287 | 0 | 7 | 0 | 4 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 5 | 5 | 15 | 1 | 9 | 1 | 8 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 34 | 34 | 63 | 0 | 6 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 22 | 22 | 12 | 0 | 1 | 0 | 0 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 11893 | 11856 | 201 | 0 | 9 | 1 | 5 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 957 | 940 | 204 | 0 | 13 | 0 | 2 | 98% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 59 | 54 | 21 | 0 | 5 | 1 | 4 | 92% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 7 | 62 | 0 | 14 | 13 | 9 | 78% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4977 | 4961 | 267 | 0 | 8 | 2 | 5 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1150 | 1135 | 174 | 0 | 24 | 10 | 16 | 99% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 41 | 40 | 22 | 0 | 3 | 0 | 1 | 98% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 1 | 0 | 0 | 0 | 0 | 0 | 33% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4095 | 4033 | 261 | 0 | 10 | 3 | 5 | 98% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1153 | 1141 | 293 | 0 | 23 | 0 | 8 | 99% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 23 | 23 | 26 | 0 | 7 | 0 | 2 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 9 | 24 | 0 | 4 | 0 | 0 | 90% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3214 | 3208 | 199 | 0 | 8 | 2 | 4 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 125 | 116 | 160 | 0 | 46 | 25 | 39 | 93% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 8 | 11 | 0 | 4 | 3 | 3 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1912 | 1909 | 163 | 0 | 7 | 0 | 2 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 7511 | 7494 | 186 | 0 | 6 | 0 | 3 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 2 | 1 | 0 | 0 | 0 | 0 | 0 | 50% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 11 | 73 | 0 | 28 | 3 | 6 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2230 | 2220 | 275 | 0 | 10 | 0 | 3 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3476 | 3451 | 307 | 0 | 19 | 0 | 7 | 99% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 4 | 5 | 0 | 2 | 0 | 2 | 67% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 11 | 60 | 0 | 8 | 0 | 1 | 92% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1988 | 1976 | 279 | 0 | 25 | 1 | 7 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2442 | 2432 | 270 | 0 | 20 | 2 | 10 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 11 | 33 | 0 | 7 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 9 | 31 | 0 | 7 | 2 | 4 | 82% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2780 | 2727 | 266 | 0 | 17 | 1 | 6 | 98% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1310 | 1288 | 351 | 0 | 24 | 0 | 7 | 98% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 18 | 18 | 12 | 0 | 2 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 9 | 61 | 0 | 7 | 0 | 0 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3437 | 3387 | 258 | 0 | 17 | 1 | 8 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1910 | 1896 | 289 | 0 | 18 | 1 | 10 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 28 | 24 | 32 | 0 | 5 | 1 | 2 | 86% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 17 | 16 | 9 | 0 | 2 | 0 | 2 | 94% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2742 | 2620 | 227 | 0 | 32 | 4 | 11 | 96% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3395 | 3388 | 170 | 0 | 12 | 1 | 6 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 7 | 15 | 0 | 5 | 0 | 3 | 88% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 11 | 77 | 0 | 8 | 2 | 2 | 92% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1274 | 1271 | 243 | 0 | 20 | 1 | 11 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1751 | 1750 | 159 | 0 | 16 | 1 | 10 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2460 | 2459 | 195 | 0 | 14 | 1 | 9 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 2328 | 2328 | 183 | 0 | 9 | 1 | 4 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 4 | 25 | 1 | 9 | 1 | 5 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 42 | 41 | 25 | 0 | 1 | 0 | 0 | 98% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 12 | 60 | 0 | 8 | 0 | 2 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 52 | 52 | 15 | 0 | 2 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2454 | 2437 | 229 | 0 | 27 | 10 | 16 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3535 | 3524 | 300 | 0 | 27 | 3 | 16 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 9 | 8 | 15 | 0 | 4 | 1 | 1 | 89% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 9 | 30 | 0 | 8 | 0 | 3 | 82% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2688 | 2681 | 225 | 0 | 14 | 0 | 7 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2557 | 2549 | 213 | 0 | 20 | 5 | 14 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 16 | 16 | 31 | 0 | 6 | 0 | 2 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 6 | 39 | 1 | 12 | 1 | 8 | 86% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6329 | 6319 | 312 | 0 | 13 | 2 | 6 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 146 | 144 | 186 | 0 | 17 | 0 | 6 | 99% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 26 | 17 | 43 | 0 | 9 | 1 | 4 | 65% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 11 | 0 | 6 | 0 | 6 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4222 | 4214 | 279 | 0 | 12 | 1 | 5 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 108 | 98 | 201 | 0 | 34 | 39 | 19 | 91% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 15 | 37 | 0 | 10 | 1 | 5 | 79% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 2 | 0 | 1 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5703 | 5668 | 339 | 0 | 20 | 4 | 10 | 99% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 71 | 66 | 112 | 0 | 28 | 28 | 22 | 93% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 9 | 9 | 8 | 0 | 3 | 1 | 2 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 408 | 405 | 129 | 0 | 16 | 5 | 7 | 99% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 6769 | 6760 | 253 | 0 | 13 | 0 | 7 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2 | 2 | 20 | 4 | 12 | 4 | 12 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 44 | 44 | 62 | 0 | 16 | 0 | 8 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 4 | 9 | 4 | 5 | 4 | 4 | 80% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 22 | 21 | 31 | 0 | 7 | 1 | 4 | 95% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2825 | 2823 | 273 | 0 | 11 | 3 | 4 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 343 | 340 | 311 | 0 | 15 | 5 | 10 | 99% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 46 | 44 | 35 | 0 | 2 | 0 | 1 | 96% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3542 | 3524 | 323 | 0 | 29 | 1 | 10 | 99% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2195 | 2193 | 267 | 0 | 18 | 2 | 8 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 67 | 48 | 203 | 0 | 22 | 0 | 9 | 72% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 8 | 8 | 40 | 0 | 15 | 0 | 13 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 6 | 103 | 0 | 20 | 0 | 4 | 86% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 21 | 19 | 81 | 0 | 9 | 0 | 1 | 90% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 8 | 8 | 8 | 8 | 8 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3859 | 3853 | 278 | 0 | 15 | 0 | 7 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 72 | 69 | 192 | 0 | 18 | 11 | 11 | 96% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 13 | 9 | 48 | 0 | 10 | 0 | 4 | 69% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 1 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6450 | 6450 | 261 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 486 | 485 | 234 | 0 | 21 | 2 | 13 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 232 | 232 | 57 | 0 | 8 | 1 | 5 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 16 | 16 | 110 | 0 | 28 | 0 | 6 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4493 | 4492 | 67 | 0 | 4 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 225 | 224 | 125 | 0 | 40 | 84 | 25 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 224 | 224 | 28 | 0 | 4 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 8 | 64 | 0 | 23 | 2 | 5 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 16187 | 16185 | 137 | 0 | 6 | 2 | 4 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1689 | 1681 | 216 | 0 | 12 | 1 | 4 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 150 | 150 | 86 | 0 | 10 | 0 | 6 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 12 | 84 | 0 | 23 | 17 | 14 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5903 | 5903 | 87 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 311 | 309 | 218 | 0 | 22 | 3 | 10 | 99% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 141 | 141 | 33 | 0 | 3 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 9 | 42 | 1 | 20 | 4 | 18 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 986 | 986 | 63 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6721 | 6721 | 253 | 0 | 6 | 1 | 3 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 63 | 63 | 9 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 141 | 141 | 84 | 0 | 4 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 476 | 476 | 10 | 0 | 1 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6293 | 6293 | 61 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 58 | 58 | 5 | 0 | 1 | 0 | 0 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 183 | 183 | 42 | 0 | 2 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 881 | 881 | 34 | 0 | 1 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 646 | 646 | 260 | 0 | 3 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 79 | 79 | 14 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 75 | 75 | 25 | 0 | 1 | 0 | 0 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 862 | 862 | 9 | 0 | 1 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 4616 | 4612 | 154 | 0 | 9 | 0 | 3 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 72 | 72 | 7 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 110 | 110 | 44 | 0 | 5 | 0 | 0 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1468 | 1468 | 15 | 0 | 1 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 10616 | 10611 | 277 | 0 | 5 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 103 | 103 | 6 | 0 | 1 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 111 | 111 | 75 | 0 | 4 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 8067 | 8067 | 266 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3235 | 3234 | 156 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 391 | 391 | 37 | 0 | 2 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 78 | 78 | 28 | 0 | 2 | 0 | 0 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 4303 | 4303 | 26 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7096 | 7096 | 72 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 5502 | 5499 | 244 | 0 | 11 | 1 | 3 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 10131 | 10131 | 126 | 0 | 5 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 146 | 146 | 58 | 0 | 2 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 149 | 149 | 38 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 169 | 169 | 90 | 0 | 5 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 137 | 137 | 46 | 0 | 5 | 0 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2399 | 2399 | 98 | 0 | 3 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 7336 | 7335 | 301 | 0 | 5 | 1 | 3 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 65 | 65 | 82 | 0 | 9 | 2 | 3 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 291 | 291 | 150 | 0 | 7 | 0 | 1 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5015 | 5007 | 280 | 0 | 16 | 1 | 9 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 149 | 124 | 259 | 0 | 34 | 0 | 2 | 83% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 4 | 2 | 1 | 2 | 1 | 2 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3026 | 2995 | 278 | 0 | 20 | 0 | 10 | 99% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2729 | 2709 | 276 | 0 | 19 | 1 | 5 | 99% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 94 | 90 | 201 | 0 | 44 | 0 | 28 | 96% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 41 | 39 | 153 | 0 | 28 | 5 | 5 | 95% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 8 | 50 | 0 | 16 | 0 | 15 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 22 | 21 | 41 | 0 | 3 | 0 | 1 | 95% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4018 | 4007 | 195 | 0 | 11 | 1 | 6 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 535 | 527 | 273 | 0 | 13 | 0 | 5 | 99% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 42 | 41 | 60 | 0 | 3 | 0 | 0 | 98% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4444 | 4433 | 281 | 0 | 13 | 2 | 8 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 251 | 235 | 206 | 0 | 38 | 22 | 27 | 94% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 22 | 22 | 25 | 0 | 8 | 0 | 2 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 46 | 46 | 46 | 46 | 46 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4039 | 4031 | 293 | 0 | 10 | 1 | 4 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 151 | 151 | 212 | 0 | 29 | 0 | 17 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 19 | 49 | 0 | 6 | 0 | 1 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6277 | 6268 | 274 | 0 | 19 | 3 | 10 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 205 | 190 | 177 | 0 | 33 | 1 | 18 | 93% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 32 | 30 | 30 | 0 | 7 | 3 | 4 | 94% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 50 | 50 | 50 | 50 | 50 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2148 | 2137 | 288 | 0 | 26 | 5 | 11 | 99% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 4123 | 4120 | 234 | 0 | 8 | 0 | 3 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 71 | 60 | 185 | 1 | 96 | 168 | 105 | 85% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 452 | 448 | 301 | 0 | 68 | 17 | 53 | 99% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 4 | 15 | 0 | 5 | 0 | 2 | 80% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 171 | 162 | 49 | 0 | 3 | 0 | 1 | 95% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 65 | 65 | 65 | 65 | 65 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 2 | 1 | 0 | 0 | 0 | 0 | 0 | 50% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2185 | 2183 | 299 | 0 | 17 | 3 | 10 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 144 | 115 | 272 | 0 | 50 | 35 | 35 | 80% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 3 | 9 | 2 | 6 | 2 | 7 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 13 | 13 | 13 | 13 | 13 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3667 | 3663 | 305 | 0 | 17 | 2 | 9 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 41 | 38 | 143 | 0 | 49 | 0 | 42 | 93% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 14 | 43 | 0 | 8 | 0 | 3 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3951 | 3948 | 157 | 0 | 10 | 3 | 6 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 93 | 93 | 204 | 0 | 41 | 26 | 27 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 7 | 18 | 0 | 6 | 4 | 4 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 5 | 3 | 1 | 1 | 1 | 1 | 100% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3280 | 3255 | 299 | 0 | 16 | 3 | 8 | 99% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 199 | 192 | 192 | 0 | 35 | 2 | 14 | 96% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 48 | 47 | 42 | 0 | 7 | 0 | 3 | 98% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3032 | 3022 | 224 | 0 | 6 | 0 | 2 | 100% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1265 | 1261 | 193 | 0 | 71 | 42 | 45 | 100% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 27 | 27 | 16 | 0 | 2 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 4152 | 4152 | 61 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 498 | 498 | 22 | 0 | 4 | 1 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 186 | 186 | 30 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 5 | 5 | 2 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 23499 | 23499 | 101 | 0 | 3 | 1 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 1486 | 1484 | 275 | 0 | 18 | 1 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 162 | 162 | 76 | 0 | 6 | 0 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 6 | 5 | 6 | 0 | 2 | 1 | 1 | 83% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 6767 | 6767 | 171 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 972 | 972 | 80 | 0 | 6 | 0 | 4 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 103 | 103 | 55 | 0 | 2 | 0 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 1 | 6 | 6 | 6 | 6 | 6 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 13748 | 13748 | 250 | 0 | 4 | 2 | 3 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 185 | 184 | 181 | 0 | 15 | 3 | 4 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 159 | 159 | 60 | 0 | 6 | 3 | 3 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 17104 | 17104 | 161 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 201 | 197 | 273 | 0 | 17 | 1 | 5 | 98% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 51 | 51 | 118 | 0 | 10 | 1 | 4 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3230 | 3230 | 279 | 0 | 5 | 2 | 3 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 32 | 32 | 167 | 2 | 87 | 121 | 121 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 26 | 26 | 27 | 0 | 4 | 0 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 6248 | 6248 | 101 | 0 | 2 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 333 | 333 | 111 | 0 | 6 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 89 | 89 | 15 | 0 | 3 | 0 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 17 | 17 | 122 | 0 | 7 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 28774 | 28774 | 279 | 0 | 6 | 1 | 3 | 100% |
| KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 11772 | 11691 | 251 | 0 | 17 | 1 | 10 | 99% |
| KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 467 | 467 | 136 | 0 | 7 | 0 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 15 | 15 | 89 | 0 | 11 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3385 | 3385 | 207 | 0 | 9 | 3 | 6 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 23281 | 23281 | 128 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 290 | 283 | 306 | 0 | 17 | 0 | 1 | 98% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 1101 | 1099 | 186 | 0 | 15 | 2 | 4 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 53 | 53 | 65 | 0 | 14 | 2 | 9 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 139 | 139 | 33 | 0 | 4 | 0 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 6 | 32 | 0 | 10 | 0 | 6 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 13 | 12 | 18 | 0 | 5 | 0 | 1 | 92% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 23759 | 23759 | 143 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 634 | 632 | 263 | 0 | 54 | 1 | 7 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 286 | 286 | 47 | 0 | 3 | 0 | 2 | 100% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 5 | 5 | 27 | 0 | 11 | 0 | 7 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3315 | 3315 | 226 | 0 | 8 | 1 | 3 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 840 | 834 | 244 | 0 | 62 | 5 | 62 | 99% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 39 | 39 | 121 | 0 | 16 | 0 | 6 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 3 | 3 | 3 | 3 | 3 | 50% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3582 | 3581 | 118 | 0 | 5 | 1 | 3 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 473 | 464 | 250 | 0 | 48 | 6 | 28 | 98% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 116 | 116 | 83 | 0 | 11 | 1 | 7 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 5 | 82 | 0 | 17 | 0 | 2 | 56% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5988 | 5978 | 262 | 0 | 6 | 1 | 4 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 799 | 774 | 280 | 0 | 78 | 2 | 42 | 97% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 303 | 303 | 133 | 0 | 9 | 0 | 4 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 30 | 29 | 79 | 0 | 10 | 0 | 6 | 97% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3771 | 3769 | 233 | 0 | 7 | 1 | 4 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 434 | 423 | 255 | 0 | 42 | 5 | 30 | 97% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 244 | 243 | 281 | 0 | 16 | 0 | 5 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 22 | 16 | 164 | 0 | 30 | 0 | 15 | 73% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3738 | 3737 | 266 | 0 | 10 | 1 | 5 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 448 | 444 | 290 | 0 | 39 | 3 | 18 | 99% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 267 | 265 | 177 | 0 | 14 | 1 | 7 | 99% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 22 | 20 | 99 | 0 | 25 | 0 | 8 | 91% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5152 | 5146 | 211 | 0 | 13 | 4 | 8 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 284 | 282 | 201 | 0 | 24 | 0 | 8 | 99% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 10 | 9 | 24 | 2 | 9 | 6 | 6 | 90% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3478 | 3454 | 251 | 0 | 9 | 1 | 4 | 99% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 6505 | 6496 | 318 | 0 | 9 | 1 | 5 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 507 | 494 | 144 | 0 | 14 | 0 | 2 | 97% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 139 | 136 | 271 | 0 | 41 | 0 | 17 | 98% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 14 | 12 | 0 | 3 | 0 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 57 | 55 | 31 | 0 | 4 | 1 | 1 | 96% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 9 | 18 | 0 | 4 | 0 | 0 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 1 | 1 | 46 | 46 | 46 | 46 | 46 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3448 | 3444 | 236 | 0 | 8 | 0 | 3 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 424 | 412 | 244 | 0 | 23 | 0 | 13 | 97% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 6 | 2 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 8372 | 8372 | 303 | 0 | 6 | 0 | 4 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1032 | 1028 | 126 | 0 | 8 | 0 | 3 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 59 | 58 | 91 | 0 | 6 | 0 | 2 | 98% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 4 | 2 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5148 | 5146 | 120 | 0 | 6 | 1 | 4 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 331 | 328 | 148 | 0 | 16 | 0 | 7 | 99% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 13 | 12 | 0 | 1 | 0 | 0 | 93% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2564 | 2564 | 148 | 0 | 4 | 1 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 158 | 156 | 177 | 0 | 29 | 0 | 3 | 99% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 62 | 62 | 18 | 0 | 3 | 2 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2489 | 2484 | 304 | 0 | 19 | 11 | 13 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 137 | 129 | 145 | 1 | 29 | 7 | 20 | 94% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 28 | 4 | 14 | 9 | 9 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 9 | 9 | 9 | 9 | 9 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3390 | 3379 | 242 | 0 | 16 | 3 | 11 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 62 | 59 | 139 | 0 | 21 | 0 | 8 | 95% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 16 | 68 | 0 | 10 | 1 | 2 | 84% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1940 | 1938 | 213 | 0 | 7 | 0 | 4 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 113 | 113 | 170 | 0 | 20 | 0 | 9 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 14 | 9 | 0 | 2 | 2 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4021 | 4021 | 51 | 0 | 5 | 2 | 4 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 297 | 291 | 185 | 0 | 20 | 0 | 7 | 98% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 65 | 64 | 41 | 0 | 3 | 0 | 2 | 98% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 19 | 19 | 55 | 0 | 5 | 3 | 3 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 8405 | 8400 | 281 | 0 | 6 | 1 | 4 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1297 | 1271 | 299 | 0 | 17 | 0 | 5 | 98% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 95 | 92 | 103 | 0 | 5 | 0 | 2 | 97% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 1 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 8513 | 8513 | 28 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 363 | 361 | 148 | 0 | 7 | 0 | 0 | 99% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 121 | 121 | 6 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 3 | 3 | 2 | 2 | 2 | 2 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 17065 | 17060 | 124 | 0 | 1 | 1 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7305 | 7302 | 160 | 0 | 6 | 1 | 3 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 1676 | 1668 | 258 | 0 | 5 | 0 | 0 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1270 | 1265 | 165 | 0 | 4 | 0 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 120 | 119 | 58 | 0 | 1 | 0 | 0 | 99% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 69 | 64 | 72 | 0 | 3 | 0 | 1 | 93% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 10 | 9 | 50 | 0 | 6 | 0 | 0 | 90% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 25 | 23 | 15 | 0 | 2 | 0 | 1 | 92% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4940 | 4935 | 280 | 0 | 16 | 1 | 9 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 188 | 172 | 284 | 0 | 64 | 0 | 39 | 91% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 25 | 25 | 76 | 0 | 12 | 0 | 8 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 26 | 26 | 26 | 26 | 26 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3239 | 3238 | 166 | 0 | 9 | 2 | 5 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 327 | 322 | 304 | 0 | 90 | 184 | 65 | 98% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 88 | 88 | 83 | 0 | 2 | 0 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2806 | 2806 | 283 | 0 | 10 | 2 | 5 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 154 | 145 | 338 | 0 | 64 | 71 | 46 | 94% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 21 | 21 | 25 | 0 | 4 | 0 | 2 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4695 | 4694 | 233 | 0 | 8 | 0 | 4 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 348 | 345 | 195 | 0 | 30 | 0 | 21 | 99% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 41 | 41 | 31 | 0 | 2 | 0 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 6 | 6 | 6 | 6 | 6 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5305 | 5303 | 326 | 0 | 12 | 1 | 5 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 557 | 544 | 240 | 0 | 33 | 38 | 21 | 98% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 72 | 72 | 11 | 0 | 2 | 0 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 4 | 45 | 0 | 11 | 0 | 0 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4517 | 4511 | 234 | 0 | 13 | 0 | 7 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 212 | 202 | 230 | 0 | 62 | 97 | 48 | 95% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 17 | 17 | 13 | 0 | 3 | 1 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 4 | 4 | 4 | 4 | 4 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6182 | 6163 | 299 | 0 | 13 | 0 | 6 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 419 | 390 | 257 | 0 | 74 | 10 | 53 | 93% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 27 | 27 | 28 | 0 | 5 | 0 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 8476 | 8455 | 332 | 0 | 18 | 4 | 10 | 100% |
| NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 261 | 238 | 246 | 0 | 50 | 0 | 22 | 91% |
| NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 23 | 23 | 127 | 0 | 10 | 0 | 1 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7791 | 7791 | 200 | 0 | 7 | 1 | 4 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 247 | 238 | 214 | 0 | 41 | 20 | 30 | 96% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 73 | 73 | 40 | 0 | 4 | 1 | 2 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4596 | 4591 | 259 | 0 | 6 | 1 | 3 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 442 | 430 | 233 | 0 | 22 | 0 | 1 | 97% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 48 | 47 | 117 | 0 | 5 | 0 | 1 | 98% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 3 | 0 | 0 | 0 | 0 | 0 | 75% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 5741 | 5734 | 302 | 0 | 9 | 0 | 3 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 591 | 578 | 206 | 0 | 63 | 0 | 31 | 98% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 80 | 80 | 20 | 0 | 2 | 0 | 1 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 4 | 4 | 3 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3044 | 3044 | 248 | 0 | 4 | 2 | 3 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 161 | 161 | 93 | 0 | 23 | 0 | 20 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 27 | 27 | 8 | 0 | 2 | 1 | 1 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 2 | 1 | 2 | 1 | 2 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6812 | 6812 | 189 | 0 | 6 | 1 | 4 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 142 | 141 | 166 | 0 | 35 | 35 | 35 | 99% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 22 | 22 | 20 | 0 | 4 | 1 | 2 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 3 | 33 | 1 | 15 | 1 | 11 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4926 | 4926 | 189 | 0 | 7 | 3 | 5 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 142 | 135 | 160 | 0 | 44 | 1 | 24 | 95% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 55 | 55 | 20 | 0 | 5 | 0 | 3 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7059 | 7057 | 243 | 0 | 11 | 5 | 8 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 148 | 145 | 191 | 0 | 55 | 0 | 35 | 98% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 28 | 28 | 35 | 0 | 7 | 10 | 5 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4198 | 4183 | 257 | 0 | 13 | 1 | 4 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 131 | 121 | 301 | 0 | 50 | 0 | 20 | 92% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 58 | 57 | 52 | 0 | 3 | 0 | 1 | 98% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4330 | 4330 | 257 | 0 | 7 | 5 | 6 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 174 | 172 | 204 | 0 | 34 | 8 | 10 | 99% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 74 | 74 | 19 | 0 | 3 | 1 | 1 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 4 | 29 | 0 | 8 | 0 | 1 | 80% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2042 | 2040 | 321 | 0 | 7 | 0 | 5 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2273 | 2273 | 119 | 0 | 5 | 2 | 4 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 97 | 94 | 237 | 0 | 48 | 0 | 29 | 97% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 145 | 142 | 239 | 0 | 33 | 4 | 13 | 98% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 55 | 55 | 87 | 0 | 4 | 0 | 1 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 106 | 90 | 32 | 0 | 3 | 0 | 1 | 85% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 4 | 2 | 3 | 1 | 2 | 1 | 2 | 50% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3071 | 3071 | 174 | 0 | 8 | 5 | 6 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 206 | 196 | 256 | 0 | 26 | 0 | 8 | 95% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 43 | 43 | 32 | 0 | 6 | 2 | 4 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 3 | 2 | 3 | 2 | 3 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5131 | 5129 | 183 | 0 | 10 | 4 | 6 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 131 | 124 | 166 | 0 | 16 | 1 | 3 | 95% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 102 | 102 | 54 | 0 | 4 | 0 | 1 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 35 | 35 | 35 | 35 | 35 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2699 | 2699 | 91 | 0 | 2 | 1 | 2 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 197 | 196 | 174 | 0 | 17 | 0 | 5 | 99% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 85 | 85 | 13 | 0 | 2 | 1 | 1 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 6 | 3 | 0 | 1 | 0 | 0 | 86% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3834 | 3834 | 78 | 0 | 5 | 2 | 4 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 82 | 81 | 133 | 0 | 20 | 0 | 7 | 99% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 413 | 411 | 64 | 0 | 8 | 1 | 4 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 21 | 21 | 39 | 0 | 6 | 0 | 2 | 100% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5138 | 5138 | 177 | 0 | 6 | 1 | 4 | 100% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 291 | 291 | 171 | 0 | 35 | 0 | 25 | 100% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 111 | 111 | 186 | 0 | 6 | 0 | 1 | 100% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1728 | 1728 | 36 | 0 | 3 | 1 | 2 | 100% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 149 | 144 | 182 | 0 | 37 | 0 | 26 | 97% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 27 | 27 | 25 | 0 | 3 | 2 | 2 | 100% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2944 | 2944 | 175 | 0 | 7 | 2 | 4 | 100% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 320 | 317 | 248 | 0 | 30 | 2 | 11 | 99% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 81 | 81 | 17 | 0 | 2 | 0 | 1 | 100% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 36 | 2 | 19 | 2 | 19 | 100% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5076 | 5076 | 232 | 0 | 6 | 2 | 4 | 100% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 194 | 182 | 196 | 0 | 41 | 0 | 28 | 94% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 129 | 129 | 29 | 0 | 2 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1971 | 1971 | 107 | 0 | 4 | 1 | 3 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 105 | 104 | 110 | 0 | 10 | 0 | 2 | 99% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 36 | 36 | 11 | 0 | 1 | 0 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7952 | 7951 | 183 | 0 | 5 | 0 | 3 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 210 | 197 | 247 | 0 | 33 | 1 | 8 | 94% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 88 | 88 | 32 | 0 | 5 | 0 | 4 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 12 | 54 | 0 | 12 | 2 | 7 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3445 | 3445 | 94 | 0 | 4 | 2 | 3 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 243 | 241 | 217 | 0 | 23 | 0 | 3 | 99% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 115 | 115 | 15 | 0 | 2 | 0 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 13 | 13 | 12 | 0 | 3 | 2 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2927 | 2927 | 15 | 0 | 2 | 1 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 107 | 104 | 270 | 0 | 36 | 0 | 25 | 97% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 167 | 167 | 17 | 0 | 1 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 8 | 23 | 0 | 8 | 2 | 3 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 895 | 895 | 11 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5648 | 5648 | 237 | 0 | 4 | 1 | 3 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 218 | 218 | 82 | 0 | 10 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 283 | 275 | 144 | 0 | 14 | 2 | 5 | 97% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 9 | 9 | 5 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 134 | 134 | 31 | 0 | 3 | 1 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 3 | 3 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 14 | 13 | 20 | 0 | 4 | 0 | 2 | 93% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 4897 | 4897 | 90 | 0 | 1 | 0 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 1875 | 1874 | 87 | 0 | 2 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 56 | 56 | 17 | 0 | 1 | 0 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 27 | 27 | 7 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 3724 | 3724 | 38 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6701 | 6701 | 148 | 0 | 3 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 168 | 167 | 229 | 0 | 14 | 0 | 6 | 99% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 358 | 355 | 172 | 0 | 16 | 0 | 2 | 99% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 164 | 164 | 21 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 64 | 64 | 7 | 0 | 1 | 0 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 2 | 1 | 0 | 0 | 0 | 0 | 0 | 50% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 45 | 0 | 23 | 0 | 23 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 4863 | 4863 | 132 | 0 | 1 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 47 | 47 | 227 | 0 | 23 | 2 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 68 | 67 | 30 | 0 | 2 | 0 | 1 | 99% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 6701 | 6701 | 169 | 0 | 1 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 433 | 433 | 189 | 0 | 32 | 1 | 7 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 98 | 98 | 18 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 1 | 6 | 6 | 6 | 6 | 6 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1961 | 1961 | 77 | 0 | 4 | 1 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 167 | 162 | 151 | 0 | 24 | 1 | 12 | 97% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 35 | 35 | 16 | 0 | 2 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 6 | 1 | 4 | 1 | 4 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2473 | 2473 | 36 | 0 | 3 | 2 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 150 | 141 | 155 | 0 | 35 | 2 | 21 | 94% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 15 | 10 | 0 | 5 | 1 | 4 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4087 | 4087 | 231 | 0 | 4 | 1 | 2 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 274 | 265 | 317 | 0 | 25 | 0 | 5 | 97% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 119 | 119 | 11 | 0 | 2 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 4 | 0 | 2 | 0 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6087 | 6087 | 172 | 0 | 7 | 2 | 5 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3045 | 3032 | 242 | 0 | 12 | 2 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 22 | 22 | 42 | 0 | 9 | 0 | 5 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 16 | 0 | 7 | 0 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7833 | 7833 | 213 | 0 | 7 | 1 | 5 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1902 | 1868 | 240 | 0 | 17 | 1 | 4 | 98% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 56 | 56 | 58 | 0 | 12 | 0 | 8 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 18 | 18 | 280 | 0 | 31 | 3 | 7 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2450 | 2450 | 272 | 0 | 7 | 1 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1498 | 1481 | 222 | 0 | 17 | 1 | 4 | 99% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 11 | 45 | 0 | 10 | 0 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 59 | 6 | 33 | 6 | 33 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6068 | 6068 | 208 | 0 | 5 | 1 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 920 | 903 | 324 | 0 | 17 | 1 | 4 | 98% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 43 | 43 | 19 | 0 | 2 | 1 | 1 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 130 | 0 | 20 | 1 | 1 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4570 | 4568 | 137 | 0 | 4 | 1 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 829 | 812 | 330 | 0 | 18 | 1 | 4 | 98% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 38 | 38 | 19 | 0 | 2 | 0 | 1 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 8 | 61 | 0 | 13 | 0 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5460 | 5460 | 139 | 0 | 4 | 1 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2724 | 2718 | 212 | 0 | 7 | 0 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 106 | 106 | 16 | 0 | 3 | 0 | 1 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 20 | 20 | 20 | 0 | 4 | 0 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3540 | 3540 | 169 | 0 | 7 | 2 | 5 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 498 | 493 | 235 | 0 | 54 | 77 | 49 | 99% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 86 | 86 | 23 | 0 | 6 | 1 | 1 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 4 | 158 | 1 | 81 | 1 | 83 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3003 | 3003 | 184 | 0 | 6 | 1 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 292 | 284 | 252 | 0 | 39 | 6 | 28 | 97% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 43 | 43 | 102 | 0 | 8 | 0 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 6 | 8 | 0 | 3 | 0 | 0 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4131 | 4124 | 183 | 0 | 5 | 1 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 482 | 474 | 264 | 0 | 73 | 2 | 41 | 98% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 11 | 31 | 0 | 7 | 1 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 36 | 0 | 5 | 0 | 0 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6460 | 6457 | 253 | 0 | 9 | 2 | 6 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1203 | 1185 | 302 | 0 | 40 | 5 | 17 | 99% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 36 | 36 | 197 | 0 | 12 | 1 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 5 | 20 | 5 | 11 | 5 | 11 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6119 | 6119 | 160 | 0 | 5 | 1 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1872 | 1869 | 232 | 0 | 20 | 0 | 9 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 76 | 76 | 14 | 0 | 4 | 0 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 16 | 16 | 154 | 0 | 16 | 0 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6059 | 6059 | 216 | 0 | 7 | 1 | 5 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1890 | 1884 | 237 | 0 | 20 | 2 | 10 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 33 | 33 | 31 | 0 | 7 | 0 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 8 | 84 | 2 | 24 | 2 | 14 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 5840 | 5840 | 108 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 2197 | 2195 | 194 | 0 | 9 | 1 | 2 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 101 | 101 | 54 | 0 | 2 | 0 | 0 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 21 | 21 | 3 | 0 | 1 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3043 | 3043 | 17 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1032 | 1010 | 206 | 0 | 29 | 2 | 15 | 98% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 57 | 57 | 15 | 0 | 3 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 10 | 71 | 0 | 16 | 0 | 5 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1293 | 1293 | 10 | 0 | 1 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2171 | 2171 | 18 | 0 | 1 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 226 | 226 | 154 | 0 | 19 | 0 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 349 | 349 | 204 | 0 | 15 | 1 | 4 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 14 | 10 | 1 | 3 | 1 | 3 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 15 | 15 | 4 | 0 | 1 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 5 | 5 | 5 | 5 | 5 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 8 | 8 | 48 | 0 | 9 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4404 | 4404 | 154 | 0 | 2 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 734 | 727 | 164 | 0 | 20 | 1 | 7 | 99% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 71 | 71 | 9 | 0 | 2 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 3 | 0 | 0 | 0 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6436 | 6436 | 55 | 0 | 2 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 598 | 584 | 249 | 0 | 53 | 1 | 48 | 98% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 46 | 46 | 15 | 0 | 3 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7552 | 7552 | 18 | 0 | 2 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1284 | 1282 | 209 | 0 | 16 | 1 | 4 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 67 | 67 | 12 | 0 | 3 | 1 | 3 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 8 | 38 | 0 | 7 | 0 | 3 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 5059 | 5059 | 59 | 0 | 2 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 359 | 358 | 165 | 0 | 25 | 0 | 4 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 155 | 155 | 58 | 0 | 1 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 2 | 2 | 2 | 0 | 1 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4071 | 4071 | 125 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 243 | 240 | 229 | 0 | 44 | 2 | 28 | 99% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 28 | 28 | 11 | 0 | 2 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3501 | 3501 | 83 | 0 | 4 | 2 | 3 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 848 | 845 | 276 | 0 | 66 | 5 | 53 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 31 | 31 | 17 | 0 | 2 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 9 | 9 | 9 | 9 | 9 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3671 | 3671 | 104 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 989 | 988 | 243 | 0 | 24 | 1 | 6 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 11 | 21 | 0 | 5 | 0 | 4 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 3 | 0 | 2 | 0 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3112 | 3112 | 28 | 0 | 2 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 2868 | 2867 | 246 | 0 | 9 | 1 | 4 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 66 | 66 | 5 | 0 | 1 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 16 | 16 | 2 | 0 | 0 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4732 | 4732 | 137 | 0 | 4 | 1 | 3 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 944 | 937 | 304 | 0 | 30 | 5 | 16 | 99% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 84 | 84 | 36 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 8 | 38 | 0 | 13 | 0 | 10 | 89% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 962 | 961 | 232 | 0 | 24 | 1 | 3 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 34099 | 34090 | 322 | 0 | 7 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 3 | 3 | 4 | 0 | 1 | 0 | 0 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 95 | 95 | 110 | 0 | 15 | 0 | 2 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 187 | 187 | 88 | 0 | 3 | 3 | 2 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6785 | 6785 | 162 | 0 | 7 | 1 | 3 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 23 | 23 | 4 | 0 | 1 | 1 | 1 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 102 | 102 | 93 | 0 | 18 | 0 | 4 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1176 | 1176 | 155 | 0 | 7 | 0 | 3 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 34356 | 34313 | 241 | 0 | 6 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 2 | 2 | 9 | 3 | 6 | 3 | 6 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 81 | 78 | 91 | 0 | 11 | 0 | 2 | 96% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 606 | 606 | 36 | 0 | 4 | 1 | 3 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 41 | 41 | 36 | 1 | 8 | 14 | 6 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 10594 | 10594 | 212 | 0 | 7 | 1 | 3 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 182 | 182 | 125 | 0 | 14 | 4 | 7 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 8 | 8 | 9 | 0 | 2 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 6 | 6 | 1 | 0 | 0 | 0 | 0 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 89 | 89 | 162 | 0 | 15 | 0 | 0 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5992 | 5992 | 246 | 0 | 5 | 1 | 3 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 453 | 442 | 254 | 0 | 16 | 0 | 3 | 98% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 19 | 12 | 0 | 5 | 0 | 5 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 6 | 20 | 0 | 6 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 32163 | 32163 | 223 | 0 | 5 | 1 | 3 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2624 | 2616 | 285 | 0 | 10 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 51 | 51 | 15 | 0 | 4 | 1 | 4 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 10 | 96 | 0 | 12 | 0 | 2 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 12794 | 12794 | 201 | 0 | 6 | 1 | 4 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 13538 | 13531 | 311 | 0 | 3 | 0 | 0 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 39 | 39 | 16 | 0 | 4 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 73 | 73 | 25 | 0 | 1 | 0 | 0 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2459 | 2459 | 222 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 16461 | 16459 | 231 | 0 | 3 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 6 | 6 | 4 | 0 | 1 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 44 | 44 | 101 | 0 | 15 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2306 | 2306 | 26 | 0 | 2 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 12105 | 12102 | 210 | 0 | 5 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 17 | 17 | 11 | 0 | 2 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 44 | 44 | 265 | 0 | 14 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 5286 | 5286 | 118 | 0 | 3 | 1 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6167 | 6167 | 176 | 0 | 4 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 17 | 17 | 20 | 0 | 4 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 35 | 35 | 103 | 0 | 15 | 1 | 4 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 771 | 770 | 50 | 0 | 5 | 5 | 5 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 11082 | 11081 | 260 | 0 | 8 | 1 | 4 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 93 | 93 | 75 | 0 | 7 | 0 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 684 | 684 | 152 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 7097 | 7088 | 183 | 0 | 5 | 1 | 2 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 18 | 18 | 7 | 0 | 2 | 1 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 37 | 37 | 72 | 0 | 6 | 0 | 2 | 100% |
| एलटी न्यू सर्व्हिस कनेक्शन (नॉन एजी) अर्जांची माहिती | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| सेवा प्रकार | अर्ज ओळख क्रमांक | पायाभूत सुविधांची स्थिती | अर्जाची तारीख | पावतीची तारीख | पुरवठ्याची तारीख | सुरक्षा ठेव रक्कम | प्रक्रिया शुल्काची रक्कम | जीएसटी रक्कम | एकूण रक्कम |
Empowering the Consumer