Maharashtra State Electricity Distribution Co. Ltd.
| एलटी नवीन सेवा कनेक्शन (नॉन एजी) अर्जांची राज्य आकडेवारी.10-Mar-2026 रोजी तयार केलेला अहवाल | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| सेवा | इन्फ्रा स्थिती | क्षेत्र | अधिसूचित टाइमलाइन (दिवस) | प्राप्त झालेल्या अर्जांची संख्या | मंजूर अर्जांची संख्या | कमाल (दिवस) | किमान (दिवस) | मीन (दिवस) | मोड (दिवस) | मीडियन(दिवस) | अनुपालन |
| Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 113164 | 110584 | 169 | 0 | 7 | 5 | 5 | 98% |
| Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 561115 | 544139 | 224 | 0 | 21 | 10 | 12 | 97% |
| Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 100745 | 98520 | 195 | 0 | 13 | 3 | 7 | 98% |
| Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 188559 | 179412 | 219 | 0 | 18 | 1 | 6 | 95% |
| Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 122201 | 111395 | 218 | 0 | 70 | 97 | 46 | 91% |
| Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 14792 | 14098 | 181 | 2 | 109 | 129 | 122 | 95% |
| Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 2137 | 2088 | 76 | 3 | 7 | 9 | 9 | 98% |
| Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6771 | 6393 | 211 | 4 | 19 | 11 | 13 | 94% |
| Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 1452 | 1397 | 83 | 0 | 11 | 1 | 3 | 96% |
| Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1947 | 1768 | 110 | 6 | 18 | 6 | 6 | 91% |
| Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 876 | 760 | 130 | 65 | 65 | 65 | 65 | 87% |
| Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 171 | 164 | 122 | 46 | 46 | 46 | 46 | 96% |
| एल टी नवीन सेवा कनेक्शन (नॉन ए जी) अर्जांची आकडेवारी 10-Mar-2026 रोजी तयार केलेला अहवाल |
|||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| प्रभाग | परिमंडळ | मंडल | विभाग | सेवा | इन्फ्रा स्थिती | क्षेत्र | अधिसूचित टाइमलाइन (दिवस) | प्राप्त झालेल्या अर्जांची संख्या | मंजूर अर्जांची संख्या | कमाल (दिवस) | किमान (दिवस) | मीन (दिवस) | मोड (दिवस) | मीडियन(दिवस) | अनुपालन |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1488 | 1210 | 127 | 0 | 6 | 0 | 3 | 81% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6614 | 6320 | 146 | 0 | 6 | 0 | 1 | 96% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 29 | 25 | 18 | 0 | 3 | 0 | 0 | 86% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 112 | 105 | 71 | 0 | 3 | 0 | 0 | 94% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1677 | 1543 | 98 | 0 | 5 | 2 | 3 | 92% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 2770 | 2751 | 158 | 0 | 9 | 0 | 4 | 99% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 35 | 33 | 36 | 0 | 6 | 0 | 2 | 94% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 23 | 23 | 12 | 0 | 1 | 0 | 0 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 11778 | 11010 | 201 | 0 | 6 | 1 | 5 | 93% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 990 | 902 | 126 | 0 | 8 | 0 | 1 | 91% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 60 | 55 | 21 | 0 | 6 | 1 | 4 | 92% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 8 | 62 | 0 | 13 | 1 | 6 | 80% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5073 | 4945 | 112 | 0 | 7 | 2 | 6 | 97% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1204 | 1143 | 176 | 0 | 22 | 10 | 15 | 95% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 39 | 38 | 22 | 0 | 3 | 0 | 1 | 97% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 1 | 0 | 0 | 0 | 0 | 0 | 33% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3921 | 3775 | 119 | 0 | 7 | 3 | 5 | 96% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1189 | 1068 | 174 | 0 | 17 | 0 | 7 | 90% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 17 | 17 | 26 | 0 | 9 | 0 | 11 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 9 | 24 | 0 | 4 | 0 | 0 | 90% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3205 | 3026 | 40 | 0 | 5 | 2 | 4 | 94% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 148 | 108 | 151 | 0 | 36 | 25 | 26 | 73% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 8 | 11 | 0 | 4 | 3 | 3 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2076 | 1906 | 162 | 0 | 4 | 0 | 2 | 92% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 7405 | 7289 | 142 | 0 | 5 | 0 | 3 | 98% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 11 | 73 | 0 | 28 | 3 | 6 | 100% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2093 | 2021 | 179 | 0 | 7 | 0 | 3 | 97% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3562 | 3471 | 178 | 0 | 16 | 0 | 8 | 97% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 4 | 5 | 0 | 2 | 0 | 2 | 67% |
| CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 15 | 13 | 60 | 0 | 8 | 0 | 1 | 87% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1765 | 1430 | 192 | 0 | 12 | 1 | 4 | 81% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2497 | 2405 | 191 | 0 | 16 | 2 | 9 | 96% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 10 | 8 | 27 | 0 | 5 | 0 | 0 | 80% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 9 | 31 | 0 | 7 | 2 | 4 | 90% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2476 | 2196 | 197 | 0 | 11 | 1 | 4 | 89% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1420 | 1326 | 203 | 0 | 16 | 0 | 6 | 93% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 17 | 17 | 12 | 0 | 2 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 9 | 61 | 0 | 7 | 0 | 0 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2910 | 2704 | 164 | 0 | 11 | 1 | 6 | 93% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2008 | 1929 | 201 | 0 | 17 | 2 | 10 | 96% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 23 | 22 | 32 | 0 | 6 | 1 | 2 | 96% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 18 | 17 | 9 | 0 | 3 | 0 | 2 | 94% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1924 | 1617 | 98 | 0 | 9 | 4 | 4 | 84% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3473 | 3439 | 167 | 0 | 11 | 1 | 6 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 6 | 15 | 1 | 6 | 1 | 5 | 86% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 13 | 11 | 77 | 0 | 8 | 2 | 2 | 85% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 941 | 803 | 103 | 0 | 9 | 1 | 5 | 85% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1457 | 1253 | 61 | 0 | 11 | 1 | 6 | 86% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2593 | 2482 | 195 | 0 | 13 | 1 | 8 | 96% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 2423 | 2404 | 112 | 0 | 7 | 0 | 4 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 3 | 6 | 1 | 3 | 1 | 3 | 50% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 41 | 40 | 8 | 0 | 1 | 0 | 0 | 98% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 10 | 13 | 0 | 4 | 0 | 2 | 83% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 52 | 52 | 15 | 0 | 2 | 0 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2123 | 1488 | 148 | 0 | 12 | 10 | 10 | 70% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3585 | 3266 | 183 | 0 | 23 | 3 | 15 | 91% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 6 | 11 | 0 | 3 | 1 | 1 | 75% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 9 | 30 | 0 | 8 | 0 | 3 | 75% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2594 | 2392 | 180 | 0 | 11 | 0 | 6 | 92% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2681 | 2655 | 183 | 0 | 20 | 10 | 14 | 99% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 16 | 15 | 29 | 0 | 6 | 0 | 2 | 94% |
| CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 6 | 39 | 1 | 12 | 1 | 8 | 86% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5736 | 5516 | 190 | 0 | 8 | 2 | 5 | 96% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 161 | 141 | 186 | 0 | 12 | 0 | 6 | 88% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 16 | 31 | 0 | 7 | 1 | 3 | 84% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 11 | 0 | 6 | 0 | 6 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4005 | 3864 | 185 | 0 | 9 | 1 | 4 | 96% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 108 | 95 | 144 | 0 | 27 | 18 | 18 | 88% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 18 | 14 | 37 | 0 | 11 | 2 | 6 | 78% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5259 | 5045 | 205 | 0 | 16 | 4 | 9 | 96% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 80 | 73 | 121 | 0 | 32 | 28 | 23 | 91% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 8 | 7 | 0 | 3 | 1 | 2 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 344 | 317 | 129 | 0 | 14 | 5 | 5 | 92% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 5655 | 5612 | 195 | 0 | 9 | 1 | 5 | 99% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3 | 3 | 20 | 0 | 8 | 0 | 4 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 57 | 57 | 62 | 0 | 14 | 0 | 5 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 4 | 9 | 4 | 5 | 4 | 4 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 17 | 17 | 15 | 0 | 4 | 1 | 3 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2644 | 2514 | 95 | 0 | 7 | 3 | 4 | 95% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 353 | 343 | 115 | 0 | 13 | 5 | 9 | 97% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 44 | 43 | 20 | 0 | 1 | 0 | 0 | 98% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3270 | 3088 | 219 | 0 | 21 | 1 | 9 | 94% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1906 | 1839 | 176 | 0 | 13 | 2 | 7 | 96% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 80 | 40 | 106 | 0 | 20 | 0 | 8 | 50% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 10 | 10 | 74 | 0 | 19 | 0 | 13 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 7 | 103 | 0 | 19 | 11 | 5 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 21 | 18 | 81 | 0 | 11 | 0 | 1 | 86% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 8 | 8 | 8 | 8 | 8 | 100% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3612 | 3508 | 182 | 0 | 13 | 0 | 6 | 97% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 88 | 66 | 145 | 0 | 19 | 11 | 11 | 75% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 8 | 48 | 0 | 9 | 0 | 4 | 67% |
| CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 2 | 1 | 0 | 1 | 0 | 1 | 67% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6086 | 5997 | 168 | 0 | 3 | 1 | 2 | 99% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 495 | 447 | 107 | 0 | 19 | 2 | 13 | 90% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 211 | 199 | 46 | 0 | 8 | 0 | 5 | 94% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 15 | 15 | 110 | 0 | 30 | 0 | 7 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4195 | 4090 | 58 | 0 | 4 | 1 | 2 | 97% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 223 | 193 | 117 | 0 | 39 | 84 | 21 | 87% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 206 | 197 | 28 | 0 | 4 | 0 | 1 | 96% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 6 | 64 | 0 | 13 | 2 | 2 | 75% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 15258 | 14945 | 100 | 0 | 6 | 2 | 4 | 98% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1545 | 1269 | 188 | 0 | 13 | 2 | 8 | 82% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 145 | 141 | 86 | 0 | 10 | 0 | 7 | 97% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 13 | 13 | 84 | 0 | 22 | 0 | 15 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5479 | 5351 | 61 | 0 | 3 | 1 | 2 | 98% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 245 | 227 | 189 | 0 | 20 | 32 | 11 | 93% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 126 | 117 | 26 | 0 | 4 | 0 | 2 | 93% |
| KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 7 | 42 | 4 | 19 | 4 | 16 | 88% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1046 | 1046 | 63 | 0 | 3 | 1 | 2 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6329 | 6132 | 122 | 0 | 6 | 1 | 3 | 97% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 63 | 63 | 9 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 137 | 130 | 59 | 0 | 3 | 0 | 1 | 95% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 676 | 674 | 10 | 0 | 2 | 1 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 5732 | 5587 | 61 | 0 | 2 | 1 | 1 | 97% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 59 | 59 | 5 | 0 | 1 | 0 | 0 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 182 | 173 | 42 | 0 | 2 | 0 | 1 | 95% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 839 | 828 | 34 | 0 | 2 | 1 | 1 | 99% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 681 | 675 | 55 | 0 | 3 | 0 | 1 | 99% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 75 | 74 | 14 | 0 | 1 | 0 | 1 | 99% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 75 | 71 | 25 | 0 | 1 | 0 | 0 | 95% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 740 | 735 | 9 | 0 | 1 | 1 | 1 | 99% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 4426 | 4236 | 170 | 0 | 8 | 0 | 3 | 96% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 55 | 53 | 7 | 0 | 1 | 0 | 1 | 96% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 108 | 103 | 47 | 0 | 5 | 0 | 0 | 95% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1389 | 1359 | 9 | 0 | 1 | 1 | 1 | 98% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 9302 | 8737 | 158 | 0 | 5 | 0 | 1 | 94% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 98 | 98 | 6 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 109 | 101 | 75 | 0 | 4 | 0 | 1 | 93% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 7581 | 7460 | 59 | 0 | 2 | 1 | 1 | 98% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3445 | 3339 | 135 | 0 | 3 | 1 | 1 | 97% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 369 | 364 | 37 | 0 | 2 | 0 | 1 | 99% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 87 | 81 | 28 | 0 | 2 | 0 | 0 | 93% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 3613 | 3498 | 26 | 0 | 2 | 1 | 1 | 97% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6157 | 5895 | 38 | 0 | 3 | 1 | 2 | 96% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 5585 | 5508 | 99 | 0 | 6 | 1 | 3 | 99% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 10184 | 10023 | 126 | 0 | 5 | 1 | 2 | 98% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 144 | 143 | 58 | 0 | 2 | 0 | 1 | 99% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 126 | 121 | 38 | 0 | 4 | 0 | 2 | 96% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 173 | 170 | 90 | 0 | 5 | 0 | 1 | 98% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 137 | 128 | 46 | 0 | 5 | 0 | 2 | 93% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2006 | 1921 | 98 | 0 | 3 | 1 | 2 | 96% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 7481 | 7450 | 83 | 0 | 5 | 1 | 3 | 100% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 58 | 46 | 32 | 0 | 4 | 2 | 2 | 79% |
| KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 289 | 276 | 87 | 0 | 4 | 0 | 1 | 96% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4501 | 4218 | 196 | 0 | 14 | 0 | 7 | 94% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 161 | 123 | 167 | 0 | 27 | 0 | 1 | 76% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 4 | 2 | 1 | 2 | 1 | 2 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2552 | 2490 | 174 | 0 | 14 | 0 | 7 | 98% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1940 | 1916 | 122 | 0 | 11 | 1 | 5 | 99% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 87 | 61 | 127 | 0 | 20 | 0 | 15 | 70% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 35 | 30 | 96 | 0 | 12 | 5 | 5 | 86% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 16 | 7 | 24 | 0 | 11 | 0 | 7 | 44% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 20 | 20 | 41 | 0 | 3 | 0 | 1 | 100% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3658 | 3588 | 123 | 0 | 9 | 1 | 5 | 98% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 597 | 563 | 102 | 0 | 10 | 0 | 2 | 94% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 41 | 39 | 13 | 0 | 1 | 0 | 0 | 95% |
| KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 3 | 3 | 3 | 3 | 3 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4218 | 4093 | 126 | 0 | 11 | 2 | 8 | 97% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 262 | 211 | 218 | 0 | 39 | 22 | 27 | 81% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 23 | 23 | 25 | 0 | 8 | 0 | 2 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 46 | 46 | 46 | 46 | 46 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3676 | 3632 | 162 | 0 | 7 | 1 | 4 | 99% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 178 | 172 | 100 | 0 | 21 | 2 | 15 | 97% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 19 | 49 | 0 | 6 | 0 | 1 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5682 | 5588 | 167 | 0 | 15 | 3 | 9 | 98% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 205 | 175 | 183 | 0 | 31 | 1 | 15 | 85% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 30 | 30 | 30 | 0 | 7 | 3 | 4 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 50 | 50 | 50 | 50 | 50 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1961 | 1924 | 192 | 0 | 17 | 5 | 9 | 98% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3855 | 3621 | 111 | 0 | 6 | 0 | 3 | 94% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 111 | 89 | 183 | 0 | 57 | 9 | 18 | 80% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 460 | 343 | 138 | 0 | 32 | 0 | 21 | 75% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 4 | 15 | 0 | 5 | 0 | 2 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 169 | 165 | 49 | 0 | 3 | 0 | 1 | 98% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 65 | 65 | 65 | 65 | 65 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 2 | 1 | 0 | 0 | 0 | 0 | 0 | 50% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1976 | 1925 | 128 | 0 | 15 | 3 | 10 | 97% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 144 | 98 | 165 | 0 | 37 | 35 | 33 | 68% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 3 | 9 | 2 | 6 | 2 | 7 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 13 | 13 | 13 | 13 | 13 | 50% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3181 | 3096 | 224 | 0 | 11 | 2 | 8 | 97% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 58 | 43 | 139 | 0 | 36 | 0 | 14 | 74% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 15 | 43 | 0 | 7 | 0 | 2 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 3 | 3 | 3 | 3 | 3 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3661 | 3592 | 117 | 0 | 9 | 3 | 5 | 98% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 103 | 87 | 118 | 0 | 25 | 1 | 19 | 84% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 7 | 18 | 0 | 6 | 4 | 4 | 100% |
| KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2837 | 2764 | 191 | 0 | 12 | 3 | 7 | 97% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 202 | 174 | 174 | 0 | 28 | 0 | 13 | 86% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 44 | 42 | 42 | 0 | 7 | 0 | 3 | 95% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 30 | 30 | 30 | 30 | 30 | 50% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2810 | 2782 | 125 | 0 | 5 | 0 | 2 | 99% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1267 | 1259 | 193 | 0 | 70 | 42 | 45 | 99% |
| KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 27 | 27 | 16 | 0 | 2 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 3817 | 3787 | 24 | 0 | 2 | 1 | 2 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 443 | 437 | 22 | 0 | 5 | 1 | 2 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 174 | 173 | 30 | 0 | 2 | 1 | 1 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 5 | 5 | 2 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 21886 | 21672 | 97 | 0 | 3 | 1 | 2 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 1595 | 1370 | 103 | 0 | 8 | 1 | 2 | 86% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 157 | 153 | 76 | 0 | 6 | 0 | 1 | 97% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 5 | 5 | 82 | 0 | 18 | 1 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 6359 | 6293 | 160 | 0 | 3 | 1 | 2 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 481 | 412 | 80 | 0 | 1 | 0 | 0 | 86% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 98 | 93 | 16 | 0 | 1 | 1 | 1 | 95% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 1 | 6 | 6 | 6 | 6 | 6 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 12723 | 12548 | 131 | 0 | 4 | 2 | 3 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 181 | 170 | 181 | 0 | 14 | 3 | 4 | 94% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 154 | 152 | 60 | 0 | 7 | 3 | 3 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 0 | 0 | 0 | 0 | 0 | 50% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 15872 | 15701 | 128 | 0 | 3 | 1 | 2 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 219 | 173 | 190 | 0 | 13 | 5 | 6 | 79% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 52 | 48 | 118 | 0 | 10 | 1 | 4 | 92% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3034 | 3017 | 133 | 0 | 5 | 2 | 3 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 75 | 74 | 133 | 2 | 109 | 129 | 122 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 27 | 27 | 27 | 0 | 5 | 0 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 6098 | 6059 | 101 | 0 | 2 | 0 | 0 | 99% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 332 | 326 | 79 | 0 | 5 | 0 | 0 | 98% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 91 | 91 | 15 | 0 | 3 | 0 | 1 | 100% |
| KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 22 | 20 | 122 | 0 | 6 | 0 | 0 | 91% |
| KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 26679 | 26360 | 149 | 0 | 6 | 1 | 4 | 99% |
| KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 11932 | 9676 | 192 | 0 | 13 | 1 | 9 | 81% |
| KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 428 | 412 | 84 | 0 | 8 | 0 | 2 | 96% |
| KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 16 | 10 | 89 | 0 | 11 | 0 | 0 | 63% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3215 | 3117 | 170 | 0 | 9 | 5 | 6 | 97% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 22105 | 21784 | 128 | 0 | 3 | 1 | 2 | 99% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 281 | 252 | 163 | 0 | 12 | 0 | 0 | 90% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 1170 | 1128 | 173 | 0 | 12 | 2 | 4 | 96% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 48 | 45 | 65 | 0 | 16 | 0 | 13 | 94% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 137 | 130 | 34 | 0 | 4 | 0 | 1 | 95% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 5 | 32 | 0 | 9 | 0 | 2 | 83% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 13 | 12 | 18 | 0 | 5 | 0 | 1 | 92% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 22808 | 22639 | 111 | 0 | 3 | 1 | 2 | 99% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 830 | 717 | 162 | 0 | 43 | 1 | 6 | 86% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 278 | 276 | 47 | 0 | 3 | 0 | 2 | 99% |
| KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 4 | 4 | 27 | 0 | 13 | 0 | 13 | 100% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3184 | 2989 | 105 | 0 | 6 | 1 | 3 | 94% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 958 | 745 | 184 | 0 | 37 | 5 | 11 | 78% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 39 | 28 | 24 | 0 | 8 | 0 | 5 | 72% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 4 | 123 | 3 | 44 | 3 | 24 | 80% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3534 | 3416 | 125 | 0 | 5 | 1 | 3 | 97% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 609 | 457 | 186 | 0 | 37 | 6 | 14 | 75% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 113 | 97 | 42 | 0 | 8 | 1 | 6 | 86% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 7 | 82 | 0 | 14 | 0 | 2 | 64% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5839 | 5652 | 133 | 0 | 6 | 1 | 4 | 97% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 798 | 609 | 213 | 0 | 40 | 2 | 30 | 76% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 306 | 292 | 85 | 0 | 7 | 1 | 4 | 95% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 31 | 26 | 33 | 0 | 6 | 0 | 4 | 84% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3622 | 3488 | 195 | 0 | 6 | 1 | 4 | 96% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 496 | 411 | 182 | 0 | 31 | 5 | 17 | 83% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 230 | 193 | 211 | 0 | 11 | 1 | 4 | 84% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 22 | 11 | 72 | 0 | 17 | 0 | 7 | 50% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3508 | 3408 | 198 | 0 | 9 | 1 | 5 | 97% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 458 | 406 | 188 | 0 | 27 | 3 | 16 | 89% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 263 | 224 | 78 | 0 | 9 | 1 | 5 | 85% |
| KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 26 | 19 | 68 | 0 | 15 | 0 | 4 | 73% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4929 | 4642 | 176 | 0 | 10 | 4 | 6 | 94% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 279 | 259 | 126 | 0 | 21 | 0 | 6 | 93% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 9 | 9 | 24 | 2 | 9 | 6 | 6 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 15 | 15 | 15 | 15 | 15 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3430 | 3363 | 112 | 0 | 6 | 1 | 3 | 98% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 6183 | 5911 | 186 | 0 | 7 | 1 | 5 | 96% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 523 | 462 | 96 | 0 | 11 | 0 | 2 | 88% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 154 | 128 | 107 | 0 | 26 | 0 | 11 | 83% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 14 | 19 | 0 | 5 | 0 | 3 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 54 | 54 | 31 | 0 | 4 | 1 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 8 | 18 | 0 | 4 | 0 | 0 | 89% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 1 | 1 | 46 | 46 | 46 | 46 | 46 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3513 | 3419 | 102 | 0 | 6 | 0 | 2 | 97% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 471 | 397 | 175 | 0 | 22 | 0 | 11 | 84% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 6 | 2 | 0 | 1 | 0 | 0 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7912 | 7732 | 187 | 0 | 5 | 0 | 3 | 98% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1048 | 990 | 151 | 0 | 7 | 0 | 3 | 94% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 51 | 51 | 20 | 0 | 3 | 0 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 4 | 2 | 0 | 1 | 0 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4796 | 4738 | 120 | 0 | 5 | 1 | 3 | 99% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 369 | 335 | 148 | 0 | 12 | 0 | 6 | 91% |
| KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 13 | 13 | 12 | 0 | 1 | 0 | 0 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2406 | 2364 | 96 | 0 | 4 | 1 | 2 | 98% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 159 | 115 | 177 | 0 | 12 | 0 | 1 | 72% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 49 | 48 | 9 | 0 | 2 | 0 | 2 | 98% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2418 | 2222 | 167 | 0 | 17 | 9 | 12 | 92% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 157 | 127 | 119 | 0 | 29 | 10 | 20 | 81% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 5 | 22 | 4 | 13 | 9 | 9 | 83% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 9 | 9 | 9 | 9 | 9 | 100% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3148 | 2991 | 161 | 0 | 12 | 3 | 10 | 95% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 73 | 64 | 65 | 0 | 14 | 0 | 8 | 88% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 16 | 15 | 68 | 0 | 10 | 1 | 2 | 94% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1861 | 1813 | 118 | 0 | 6 | 0 | 4 | 97% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 128 | 120 | 142 | 0 | 18 | 0 | 8 | 94% |
| KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 14 | 9 | 0 | 2 | 2 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3816 | 3681 | 27 | 0 | 4 | 2 | 3 | 96% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 340 | 311 | 199 | 0 | 22 | 0 | 7 | 91% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 60 | 60 | 25 | 0 | 3 | 0 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 20 | 20 | 55 | 0 | 5 | 3 | 3 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 8067 | 7818 | 130 | 0 | 5 | 1 | 3 | 97% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1396 | 1241 | 156 | 0 | 12 | 0 | 3 | 89% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 89 | 88 | 14 | 0 | 3 | 0 | 2 | 99% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 3 | 7 | 0 | 3 | 0 | 1 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 8070 | 8008 | 28 | 0 | 0 | 0 | 0 | 99% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 429 | 407 | 97 | 0 | 4 | 0 | 0 | 95% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 118 | 117 | 6 | 0 | 0 | 0 | 0 | 99% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 3 | 3 | 2 | 2 | 2 | 2 | 2 | 100% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 16620 | 15920 | 27 | 0 | 1 | 1 | 1 | 96% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7011 | 6689 | 112 | 0 | 3 | 1 | 3 | 95% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 1795 | 1678 | 183 | 0 | 2 | 0 | 0 | 93% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1325 | 1240 | 151 | 0 | 4 | 0 | 1 | 94% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 116 | 112 | 19 | 0 | 1 | 0 | 0 | 97% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 64 | 59 | 8 | 0 | 1 | 0 | 1 | 92% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 11 | 8 | 1 | 0 | 0 | 0 | 0 | 73% |
| KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 25 | 22 | 9 | 0 | 1 | 0 | 1 | 88% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4673 | 4520 | 192 | 0 | 14 | 1 | 9 | 97% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 207 | 147 | 187 | 0 | 49 | 0 | 32 | 71% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 23 | 22 | 41 | 0 | 11 | 2 | 9 | 96% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 26 | 26 | 26 | 26 | 26 | 100% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3178 | 3052 | 145 | 0 | 10 | 3 | 6 | 96% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 356 | 286 | 181 | 0 | 52 | 13 | 50 | 80% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 86 | 85 | 83 | 0 | 2 | 0 | 1 | 99% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2851 | 2735 | 192 | 0 | 10 | 3 | 6 | 96% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 170 | 140 | 173 | 0 | 43 | 2 | 39 | 82% |
| NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 22 | 22 | 25 | 0 | 4 | 0 | 2 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4436 | 4363 | 212 | 0 | 7 | 0 | 4 | 98% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 354 | 321 | 195 | 0 | 27 | 0 | 19 | 91% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 41 | 38 | 15 | 0 | 1 | 1 | 1 | 93% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4799 | 4709 | 200 | 0 | 10 | 1 | 5 | 98% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 633 | 524 | 167 | 0 | 32 | 38 | 22 | 83% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 69 | 69 | 10 | 0 | 1 | 0 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 3 | 0 | 0 | 0 | 0 | 0 | 75% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4273 | 4126 | 196 | 0 | 11 | 0 | 6 | 97% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 235 | 178 | 207 | 0 | 49 | 97 | 39 | 76% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 16 | 16 | 13 | 0 | 3 | 0 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5712 | 5547 | 196 | 0 | 11 | 0 | 6 | 97% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 418 | 271 | 206 | 0 | 50 | 10 | 30 | 65% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 23 | 23 | 16 | 0 | 4 | 0 | 1 | 100% |
| NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7316 | 7095 | 192 | 0 | 15 | 5 | 9 | 97% |
| NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 250 | 164 | 186 | 0 | 32 | 0 | 18 | 66% |
| NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 21 | 21 | 44 | 0 | 6 | 0 | 1 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7294 | 7085 | 198 | 0 | 7 | 1 | 4 | 97% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 283 | 216 | 146 | 0 | 39 | 20 | 30 | 76% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 70 | 69 | 40 | 0 | 4 | 2 | 2 | 99% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 40 | 40 | 40 | 40 | 40 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4541 | 4418 | 140 | 0 | 5 | 0 | 3 | 97% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 503 | 430 | 154 | 0 | 14 | 0 | 0 | 85% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 47 | 40 | 22 | 0 | 2 | 0 | 1 | 85% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 4 | 0 | 0 | 0 | 0 | 0 | 80% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2089 | 2008 | 162 | 0 | 6 | 0 | 3 | 96% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3513 | 3345 | 165 | 0 | 7 | 0 | 3 | 95% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 316 | 222 | 155 | 0 | 18 | 0 | 6 | 70% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 172 | 103 | 100 | 0 | 25 | 23 | 19 | 60% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 28 | 28 | 20 | 0 | 3 | 0 | 1 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 48 | 48 | 17 | 0 | 2 | 0 | 0 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 2 | 2 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 2 | 2 | 3 | 0 | 2 | 0 | 2 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2925 | 2895 | 102 | 0 | 4 | 2 | 3 | 99% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 224 | 168 | 166 | 0 | 25 | 3 | 21 | 75% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 26 | 26 | 8 | 0 | 2 | 1 | 1 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 2 | 1 | 2 | 1 | 2 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6514 | 6357 | 156 | 0 | 5 | 1 | 4 | 98% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 162 | 142 | 122 | 0 | 31 | 35 | 31 | 88% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 21 | 20 | 20 | 0 | 4 | 1 | 2 | 95% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 11 | 1 | 6 | 1 | 6 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4701 | 4564 | 189 | 0 | 7 | 3 | 5 | 97% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 154 | 132 | 166 | 0 | 36 | 1 | 13 | 86% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 52 | 52 | 20 | 0 | 5 | 0 | 3 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6503 | 6161 | 212 | 0 | 10 | 2 | 8 | 95% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 148 | 138 | 143 | 0 | 29 | 0 | 19 | 93% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 27 | 26 | 35 | 0 | 7 | 10 | 5 | 96% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3782 | 3721 | 194 | 0 | 9 | 1 | 3 | 98% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 177 | 158 | 176 | 0 | 23 | 0 | 10 | 89% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 57 | 55 | 11 | 0 | 2 | 0 | 1 | 96% |
| NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 63 | 63 | 63 | 63 | 63 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4417 | 4303 | 92 | 0 | 7 | 5 | 6 | 97% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 205 | 175 | 178 | 0 | 33 | 8 | 10 | 85% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 69 | 69 | 19 | 0 | 3 | 1 | 1 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 2 | 0 | 0 | 0 | 0 | 0 | 50% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1965 | 1933 | 172 | 0 | 7 | 0 | 5 | 98% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2177 | 2124 | 54 | 0 | 5 | 2 | 4 | 98% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 119 | 81 | 211 | 0 | 48 | 0 | 26 | 68% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 144 | 116 | 174 | 0 | 39 | 6 | 19 | 81% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 53 | 52 | 15 | 0 | 2 | 0 | 1 | 98% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 102 | 82 | 26 | 0 | 3 | 0 | 1 | 80% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 4 | 2 | 3 | 1 | 2 | 1 | 2 | 50% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2870 | 2747 | 97 | 0 | 7 | 4 | 6 | 96% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 205 | 166 | 149 | 0 | 19 | 0 | 8 | 81% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 39 | 35 | 32 | 0 | 6 | 5 | 4 | 90% |
| NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 4 | 39 | 0 | 11 | 0 | 3 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5369 | 5243 | 160 | 0 | 9 | 4 | 6 | 98% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 146 | 114 | 160 | 0 | 15 | 0 | 1 | 78% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 98 | 95 | 45 | 0 | 2 | 0 | 1 | 97% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 35 | 35 | 35 | 35 | 35 | 100% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2530 | 2510 | 91 | 0 | 2 | 1 | 2 | 99% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 201 | 185 | 119 | 0 | 12 | 0 | 5 | 92% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 78 | 77 | 9 | 0 | 1 | 1 | 1 | 99% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 6 | 3 | 0 | 1 | 0 | 0 | 86% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3926 | 3872 | 78 | 0 | 6 | 2 | 4 | 99% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 95 | 77 | 118 | 0 | 15 | 0 | 7 | 81% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 429 | 387 | 51 | 0 | 7 | 1 | 4 | 90% |
| NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 19 | 17 | 39 | 0 | 6 | 0 | 2 | 89% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5031 | 4950 | 88 | 0 | 6 | 1 | 4 | 98% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 313 | 241 | 179 | 0 | 29 | 0 | 24 | 77% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 107 | 104 | 54 | 0 | 3 | 0 | 1 | 97% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1723 | 1669 | 23 | 0 | 3 | 1 | 2 | 97% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 162 | 123 | 186 | 0 | 31 | 0 | 24 | 76% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 25 | 23 | 18 | 0 | 2 | 2 | 2 | 92% |
| NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2796 | 2729 | 175 | 0 | 7 | 2 | 4 | 98% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 346 | 295 | 178 | 0 | 24 | 2 | 10 | 85% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 79 | 74 | 17 | 0 | 2 | 0 | 1 | 94% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 36 | 2 | 19 | 2 | 19 | 100% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4957 | 4796 | 111 | 0 | 6 | 3 | 4 | 97% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 233 | 171 | 167 | 0 | 35 | 0 | 25 | 73% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 124 | 116 | 29 | 0 | 2 | 0 | 0 | 94% |
| NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1862 | 1835 | 71 | 0 | 4 | 1 | 3 | 99% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 123 | 112 | 110 | 0 | 15 | 0 | 3 | 91% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 36 | 35 | 11 | 0 | 1 | 0 | 0 | 97% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7584 | 7462 | 145 | 0 | 4 | 0 | 3 | 98% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 205 | 134 | 184 | 0 | 27 | 0 | 11 | 65% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 81 | 79 | 32 | 0 | 5 | 0 | 4 | 98% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 15 | 15 | 54 | 0 | 11 | 0 | 7 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3278 | 3163 | 94 | 0 | 4 | 2 | 3 | 96% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 235 | 207 | 189 | 0 | 19 | 0 | 2 | 88% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 105 | 102 | 15 | 0 | 2 | 0 | 2 | 97% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 9 | 7 | 0 | 2 | 2 | 2 | 75% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2792 | 2759 | 15 | 0 | 2 | 1 | 2 | 99% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 141 | 99 | 114 | 0 | 24 | 0 | 14 | 70% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 151 | 150 | 17 | 0 | 1 | 1 | 1 | 99% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 6 | 23 | 2 | 9 | 2 | 3 | 86% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 820 | 796 | 11 | 0 | 1 | 0 | 0 | 97% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5481 | 5261 | 84 | 0 | 4 | 1 | 3 | 96% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 207 | 201 | 50 | 0 | 4 | 0 | 0 | 97% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 320 | 284 | 144 | 0 | 13 | 2 | 4 | 89% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 9 | 9 | 5 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 123 | 120 | 31 | 0 | 3 | 1 | 2 | 98% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 3 | 3 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 17 | 16 | 30 | 0 | 7 | 0 | 3 | 94% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 4539 | 4356 | 79 | 0 | 1 | 0 | 1 | 96% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 1954 | 1945 | 87 | 0 | 2 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 57 | 55 | 10 | 0 | 1 | 1 | 1 | 96% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 27 | 26 | 7 | 0 | 1 | 0 | 0 | 96% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 3556 | 3512 | 38 | 0 | 1 | 0 | 0 | 99% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6634 | 6507 | 98 | 0 | 2 | 1 | 1 | 98% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 215 | 209 | 118 | 0 | 11 | 0 | 2 | 97% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 420 | 373 | 172 | 0 | 11 | 0 | 1 | 89% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 165 | 165 | 21 | 0 | 1 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 62 | 62 | 6 | 0 | 1 | 0 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 2 | 1 | 0 | 0 | 0 | 0 | 0 | 50% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 4766 | 4718 | 23 | 0 | 1 | 1 | 1 | 99% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 36 | 33 | 68 | 0 | 14 | 0 | 2 | 92% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 62 | 61 | 28 | 0 | 1 | 0 | 0 | 98% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 6360 | 6260 | 169 | 0 | 1 | 0 | 1 | 98% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 340 | 318 | 86 | 0 | 12 | 1 | 6 | 94% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 97 | 95 | 18 | 0 | 1 | 0 | 0 | 98% |
| NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 1 | 6 | 6 | 6 | 6 | 6 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1894 | 1851 | 68 | 0 | 3 | 1 | 2 | 98% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 170 | 149 | 151 | 0 | 21 | 1 | 9 | 88% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 32 | 32 | 9 | 0 | 2 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 6 | 1 | 4 | 1 | 4 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2329 | 2280 | 36 | 0 | 3 | 2 | 2 | 98% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 142 | 104 | 129 | 0 | 28 | 0 | 20 | 73% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 14 | 10 | 0 | 4 | 1 | 4 | 93% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 5 | 0 | 3 | 0 | 3 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3866 | 3808 | 113 | 0 | 3 | 1 | 2 | 98% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 280 | 232 | 162 | 0 | 17 | 0 | 4 | 83% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 118 | 118 | 11 | 0 | 2 | 1 | 1 | 100% |
| NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 3 | 15 | 0 | 6 | 0 | 4 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5481 | 5287 | 172 | 0 | 7 | 2 | 5 | 96% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 3123 | 2940 | 159 | 0 | 10 | 2 | 3 | 94% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 20 | 19 | 42 | 0 | 8 | 0 | 4 | 95% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 6 | 16 | 0 | 6 | 0 | 2 | 86% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7313 | 7117 | 163 | 0 | 7 | 1 | 5 | 97% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1925 | 1784 | 205 | 0 | 15 | 1 | 4 | 93% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 51 | 45 | 44 | 0 | 10 | 0 | 8 | 88% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 19 | 14 | 42 | 0 | 13 | 3 | 5 | 74% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2226 | 2108 | 102 | 0 | 6 | 1 | 4 | 95% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1654 | 1520 | 213 | 0 | 15 | 1 | 4 | 92% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 8 | 27 | 0 | 5 | 0 | 1 | 100% |
| PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 6 | 6 | 6 | 6 | 6 | 50% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5740 | 5579 | 156 | 0 | 5 | 1 | 3 | 97% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 942 | 844 | 205 | 0 | 11 | 1 | 3 | 90% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 43 | 41 | 19 | 0 | 2 | 1 | 1 | 95% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 130 | 0 | 20 | 1 | 1 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4249 | 4153 | 137 | 0 | 4 | 1 | 2 | 98% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 806 | 724 | 165 | 0 | 13 | 1 | 3 | 90% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 37 | 34 | 19 | 0 | 2 | 0 | 1 | 92% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 6 | 61 | 0 | 16 | 0 | 8 | 75% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5144 | 5049 | 139 | 0 | 4 | 1 | 3 | 98% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2739 | 2676 | 195 | 0 | 6 | 0 | 2 | 98% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 101 | 96 | 16 | 0 | 2 | 0 | 1 | 95% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 19 | 19 | 20 | 0 | 3 | 0 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3427 | 3354 | 169 | 0 | 7 | 2 | 5 | 98% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 544 | 436 | 180 | 0 | 50 | 77 | 46 | 80% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 87 | 86 | 23 | 0 | 6 | 1 | 1 | 99% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 2 | 21 | 1 | 11 | 1 | 11 | 50% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2855 | 2769 | 133 | 0 | 6 | 1 | 4 | 97% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 336 | 253 | 174 | 0 | 32 | 1 | 23 | 75% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 43 | 40 | 34 | 0 | 5 | 1 | 2 | 93% |
| PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 8 | 0 | 3 | 0 | 0 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3926 | 3833 | 147 | 0 | 4 | 1 | 2 | 98% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 518 | 330 | 156 | 0 | 32 | 2 | 15 | 64% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 11 | 31 | 0 | 7 | 1 | 3 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 36 | 0 | 5 | 0 | 0 | 100% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6040 | 5883 | 150 | 0 | 8 | 2 | 6 | 97% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1284 | 1098 | 211 | 0 | 26 | 5 | 15 | 86% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 33 | 31 | 21 | 0 | 5 | 1 | 4 | 94% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 5 | 20 | 5 | 11 | 5 | 11 | 83% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5709 | 5509 | 111 | 0 | 5 | 1 | 4 | 96% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1958 | 1809 | 176 | 0 | 16 | 0 | 9 | 92% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 64 | 62 | 14 | 0 | 4 | 0 | 4 | 97% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 20 | 15 | 35 | 0 | 6 | 0 | 3 | 75% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5611 | 5344 | 192 | 0 | 7 | 1 | 4 | 95% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1915 | 1839 | 218 | 0 | 17 | 2 | 10 | 96% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 33 | 31 | 31 | 0 | 7 | 0 | 5 | 94% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 8 | 84 | 2 | 23 | 2 | 13 | 80% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 5500 | 5308 | 108 | 0 | 3 | 1 | 2 | 97% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 2165 | 2111 | 98 | 0 | 5 | 1 | 2 | 98% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 99 | 89 | 17 | 0 | 2 | 0 | 0 | 90% |
| PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 22 | 21 | 3 | 0 | 1 | 0 | 0 | 95% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2798 | 2761 | 17 | 0 | 3 | 1 | 2 | 99% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1172 | 1012 | 195 | 0 | 24 | 1 | 11 | 86% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 55 | 54 | 20 | 0 | 3 | 0 | 1 | 98% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 6 | 21 | 0 | 6 | 0 | 2 | 75% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1220 | 1208 | 10 | 0 | 1 | 1 | 1 | 99% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2069 | 2028 | 18 | 0 | 2 | 1 | 1 | 98% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 230 | 159 | 130 | 0 | 16 | 0 | 2 | 69% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 330 | 275 | 148 | 0 | 13 | 1 | 4 | 83% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 14 | 13 | 10 | 1 | 3 | 3 | 3 | 93% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 12 | 12 | 4 | 0 | 1 | 1 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 5 | 5 | 5 | 5 | 5 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 8 | 8 | 48 | 0 | 9 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4181 | 4119 | 154 | 0 | 2 | 1 | 2 | 99% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 740 | 625 | 147 | 0 | 17 | 1 | 5 | 84% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 67 | 60 | 9 | 0 | 2 | 0 | 1 | 90% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 3 | 0 | 0 | 0 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6124 | 6039 | 55 | 0 | 2 | 1 | 2 | 99% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 671 | 514 | 209 | 0 | 49 | 1 | 45 | 77% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 37 | 37 | 15 | 0 | 3 | 1 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7187 | 7099 | 18 | 0 | 2 | 1 | 1 | 99% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1360 | 1209 | 143 | 0 | 14 | 1 | 4 | 89% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 70 | 70 | 12 | 0 | 3 | 1 | 3 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 8 | 38 | 0 | 7 | 0 | 3 | 100% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 4767 | 4723 | 59 | 0 | 2 | 1 | 1 | 99% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 358 | 346 | 165 | 0 | 24 | 0 | 3 | 97% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 150 | 145 | 7 | 0 | 1 | 0 | 1 | 97% |
| PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 2 | 2 | 2 | 0 | 1 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3898 | 3826 | 125 | 0 | 3 | 1 | 2 | 98% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 268 | 207 | 171 | 0 | 42 | 2 | 22 | 77% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 26 | 26 | 11 | 0 | 2 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 13 | 9 | 11 | 9 | 11 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3410 | 3335 | 83 | 0 | 4 | 2 | 3 | 98% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1046 | 640 | 186 | 0 | 44 | 5 | 37 | 61% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 30 | 30 | 17 | 0 | 2 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 48 | 9 | 29 | 9 | 29 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3548 | 3469 | 104 | 0 | 3 | 1 | 2 | 98% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 988 | 882 | 210 | 0 | 16 | 1 | 4 | 89% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 9 | 9 | 21 | 0 | 6 | 5 | 5 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 3 | 0 | 2 | 0 | 2 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2823 | 2746 | 17 | 0 | 2 | 1 | 1 | 97% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 2951 | 2893 | 136 | 0 | 8 | 1 | 4 | 98% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 65 | 65 | 5 | 0 | 1 | 0 | 1 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 16 | 16 | 2 | 0 | 0 | 0 | 0 | 100% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 4537 | 4472 | 137 | 0 | 4 | 1 | 3 | 99% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1022 | 830 | 196 | 0 | 24 | 5 | 13 | 81% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 82 | 77 | 16 | 0 | 2 | 1 | 2 | 94% |
| PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 7 | 38 | 0 | 14 | 0 | 10 | 70% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1042 | 1034 | 26 | 0 | 3 | 1 | 2 | 99% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 30987 | 29334 | 219 | 0 | 7 | 1 | 2 | 95% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 4 | 4 | 4 | 0 | 1 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 106 | 84 | 110 | 0 | 9 | 0 | 1 | 79% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 193 | 143 | 6 | 0 | 2 | 0 | 2 | 74% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6643 | 5969 | 108 | 0 | 6 | 1 | 3 | 90% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 27 | 26 | 4 | 0 | 1 | 1 | 1 | 96% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 97 | 84 | 64 | 0 | 15 | 0 | 3 | 87% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1298 | 1294 | 155 | 0 | 7 | 0 | 3 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 30112 | 28920 | 184 | 0 | 6 | 1 | 2 | 96% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 3 | 3 | 9 | 3 | 7 | 9 | 9 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 79 | 64 | 91 | 0 | 11 | 0 | 2 | 81% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 629 | 615 | 36 | 0 | 4 | 1 | 3 | 98% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 10544 | 9710 | 175 | 0 | 7 | 1 | 3 | 92% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 14 | 14 | 9 | 0 | 1 | 0 | 0 | 100% |
| PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 86 | 60 | 101 | 0 | 6 | 0 | 0 | 70% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5604 | 5465 | 109 | 0 | 5 | 1 | 3 | 98% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 471 | 419 | 182 | 0 | 12 | 0 | 4 | 89% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 20 | 19 | 12 | 0 | 5 | 0 | 5 | 95% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 5 | 20 | 0 | 7 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 31466 | 31011 | 201 | 0 | 5 | 1 | 3 | 99% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2482 | 2333 | 168 | 0 | 6 | 0 | 1 | 94% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 54 | 53 | 27 | 0 | 5 | 3 | 4 | 98% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 9 | 96 | 0 | 14 | 1 | 2 | 90% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 10677 | 10090 | 175 | 0 | 5 | 1 | 4 | 95% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 14133 | 13843 | 157 | 0 | 2 | 0 | 0 | 98% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 36 | 31 | 9 | 0 | 2 | 0 | 1 | 86% |
| PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 75 | 74 | 25 | 0 | 1 | 0 | 0 | 99% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2969 | 2873 | 27 | 0 | 4 | 1 | 2 | 97% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 16378 | 15202 | 139 | 0 | 2 | 0 | 1 | 93% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 6 | 6 | 4 | 0 | 1 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 44 | 31 | 23 | 0 | 3 | 0 | 0 | 70% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2294 | 2192 | 26 | 0 | 2 | 2 | 2 | 96% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 11791 | 11073 | 194 | 0 | 5 | 1 | 2 | 94% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 17 | 17 | 11 | 0 | 2 | 0 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 44 | 39 | 37 | 0 | 4 | 0 | 1 | 89% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 5028 | 4971 | 118 | 0 | 3 | 1 | 1 | 99% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6200 | 6093 | 158 | 0 | 4 | 1 | 2 | 98% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 16 | 14 | 20 | 0 | 4 | 1 | 2 | 88% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 34 | 29 | 103 | 0 | 12 | 1 | 4 | 85% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 808 | 780 | 22 | 0 | 4 | 5 | 5 | 97% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 11268 | 10991 | 202 | 0 | 7 | 1 | 4 | 98% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 90 | 82 | 61 | 0 | 6 | 0 | 2 | 91% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 643 | 621 | 152 | 0 | 3 | 1 | 2 | 97% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 7230 | 6904 | 164 | 0 | 5 | 1 | 2 | 95% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 18 | 17 | 7 | 0 | 2 | 1 | 1 | 94% |
| PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 35 | 30 | 72 | 0 | 6 | 0 | 2 | 86% |
| एलटी न्यू सर्व्हिस कनेक्शन (नॉन एजी) अर्जांची माहिती | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| सेवा प्रकार | अर्ज ओळख क्रमांक | पायाभूत सुविधांची स्थिती | अर्जाची तारीख | पावतीची तारीख | पुरवठ्याची तारीख | सुरक्षा ठेव रक्कम | प्रक्रिया शुल्काची रक्कम | जीएसटी रक्कम | एकूण रक्कम |