Ref: PR-3/AG/35758 Date: 21/11/2005
Commercial Circular No. 19
Sub :- Release of power supply on priority basis to agricultural consumers - “ KRISHI – VIKAS – III SCHEME”.
The total number of agricultural consumers in the State, though is maximum among all other State Electricity Boards, the number of prospective agricultural consumers who have completed all the formalities, including payment & submission of Test Report, is also considerably large. Any abnormal delay in getting power supply sometimes results in increase in tendency to obtain the same illegally, resulting in undesired strain on our Distribution System and also adversely affects the “Transmission & Distribution Loss “ in the system. There is also consistent demand from the prospective agricultural consumers for expeditious release of power supply against payment of capital cost, instead of only normative Service Connection Charges payable as per the prevailing provisions.
In view of the above and as approved by the Board vide Item No. 8 dated 26/10/2005, it has been decided to introduce a scheme “KRISHI – VIKAS –III SCHEME ” which will facilitate the prospective agricultural consumers to get the power supply quickly. The salient features of the said scheme are as follows.
- The Scheme will be called as “KRISHI-VIKAS-III SCHEME” consumers having connected load of
i) upto 5 HP and ii) above 5 H.P. and upto 15 H.P. will be eligible for the said Scheme.
- The Scheme will be implemented as per the following schedule:
Sr.No |
Activity |
Time Limit and details of activity |
1 |
Acceptance of application, completed in all respect. |
31.12.2005 |
2 |
Survey & issue of firm quotation |
Within one month of receipt of application. |
3 |
Payment of necessary charges & completion of other formalities, like submission of Test report, execution of agreement, etc. |
Within 30 days after issue of firm quotation. Test report is to be submitted within 15 days from date of receipt of the payment and agreement to be executed immediately. If payment is not within due date his name will be cancelled.
In case of non-submission of test report and non-execution of agreement within 15 days from the date of receipt of payment., the beneficiary shall not be considered under Krishi Vikas-III Scheme and his name shall stand cancelled. |
4 |
Release of connections under the Scheme. |
The period for release of connection is proposed as under:
a) For only service connection within one month from date of completion of all
the formalities.
b) For L.T. lines within three months from date of completion of all the
formalities.
c) Augmentation of T/F capacity and L.T. execution within three months from
date of completion of all the formalities.
d) Erection of H.T. Line ,new T/F and L.T. line within four to six months from
date of completion of all the formalities.
If the beneficiary is availing unauthorized supply, the assessment towards energy charges for the unauthorized use should be recovered as per Board’s Rules and directives from MERC. |
- For connected Load up to 5 H.P. the other details of the scheme are as follows:
(A) ZERO POLE CASES: (which are technically feasible on existing
network both for loading conditions and percentage V.R.)
a) For those who have applied & paid the Charges:
Connections to be released immediately (within 3 months) after payment of normal Service Connections Charges as per Conditions of Supply.
b) For those who have applied, paid the charges and are availing electric supply illegally:
Connections to be released immediately ( within 3 months) after payment of -
i. Normal Service Connection Charges as per conditions of Supply,
Plus
ii. Penalty amounting to six month’s bill (as per MERC rates),
Plus
iii. A Voluntary Disclosure Fees of -
a) Upto 3 HP : Rs.1,000/-.
b) Above 3 HP & Up to 5 HP : Rs.1500/-.
c) Those who have not applied for connections, but are availing supply illegally:
Connections to be released immediately( within 3 months) after payment of –
i. Normal Service Connection Charges as per Conditions of Supply.
Plus
ii. Penalty amounting to six month’s bill (as per MERC rates)
Plus
iii. A Voluntary Disclosure Fee of :
a) Upto 3 HP : Rs.2,000/-.
b) Above 3 HP & Up to 5 HP : Rs.3000/-.
(B) OTHER THAN ZERO POLE CASES :
a) For those who have applied & paid the Charges:
Connections to be released immediately (within3 months) after payment of –
i. Normal Service Connection Charges as per Conditions of Supply.
Plus
ii. A payment of Rs.10,000/per pole up to 5 poles (up to 300 mtrs.)
b) For those who have applied and paid the chages, but are availing electric supply illegally:
Connections to be released immediately (within 3 months) after payment of
i. Normal Service Connection Charges as per Conditions of Supply.
Plus
ii. Penalty amounting to six month’s bill (as per MERC rates)
Plus
iii. A Voluntary Disclosure Fee of -
a) upto 3 HP : Rs.1,000/-
b) above 3 HP & Up to 5 HP : Rs.1500/-.
Plus
iv. A payment of Rs. 10,000/pole upto 5 poles (300 mtrs)
c) For those who have not applied but are availing electric supply illegally:
Connections to be released immediately (within 3 months) after payment of -
i. Normal Service Connection Charges as per
Conditions of Supply.
Plus
ii. Penalty amounting to six month’s bill (as per MERC rates)
Plus
iii. A Voluntary Disclosure Fee of :
a) Upto 3 HP : Rs.2,000/-
b) Above 3 HP & Up to 5 HP : Rs.3000/-.
Plus
iv. A payment of Rs. 10,000/- per pole upto 5 poles (300 mtrs)
1. For connected load above 5 H.P. and upto 15 HP the other
details of the Scheme are as follow :
(A) Zero Pole Cases : (which are technically feasible on existing network both for loading conditions and percentage V.R.)
a) For those who have applied & paid the Charges:
Connections to be released immediately (within 3 months) after payment of normal Service Connections Charges as per Conditions of Supply plus infrastructure charges of –
a) Above 5 HP & upto 10 HP : Rs.10,000/-.
b) Above 10 HP & upto 15 HP : Rs.30,000/-.
b) For those who have applied, paid the charges and are availing electric supply illegally:
Connections to be released immediately (within 3 months) after payment of –
i. Normal Service Connection Charges as per
Conditions of Supply,
Plus
ii. Plus infrastructure charges of
a) Above 5 HP & upto 10 HP : Rs. 10,000/-.
b) Above 10 HP & upto 15 HP : Rs. 30,000/-.
Plus
iii. Penalty amounting to six month’s bill (as per MERC rates)
Plus
iv. A Voluntary Disclosure fess of -
a) Above 5 HP & upto 7.5 HP : Rs.3000/-
b) Above 7.5 HP & Up to 10 HP : Rs.4500/-.
c) Above 10 HP & upto 12.5 HP : Rs.6000/-
d) Above 12.5 HP & Up to 15 HP : Rs.7500/-.
c) Those who have not applied for Connection but are availing supply illegally:
Connections to be released immediately (within 3 months) after payment of -
i. Normal Service Connection Charges as per Conditions of Supply.
Plus
ii. infrastructure charges of –
a) Above 5 HP & upto 10 HP : Rs.10000/-.
b) Above 10 HP & upto 15 HP : Rs.30000/-.
Plus
iii. Penalty amounting to six month’s bill (as per MERC rates)
Plus
iv. A Voluntary Disclosure Fee of –
a) Above 5 HP & upt 7.5 H.P. :Rs. 6000/-
b) Above 7.5 HP & Up to 10 HP :Rs. 9000/-.
c) Above 10 HP & upto 12.5 HP : Rs.12000/-
d) Above 12.5 HP & Up to 15 HP: Rs.15000/-.
(B) Other than Zero Pole Cases:
a) For those who have applied & paid the Charges:
Connections to be released immediately (within 3 months) after payment of -
i. Normal Service Connections Charges as per Conditions of Supply
Plus
ii. Infrastructure charges of
a) Above 5 HP & upto 10 HP : Rs.10000/-.
b) Above 10 HP & upto 15 HP : Rs.30000/-.
Plus
iii. A payment of Rs. 10,000/- per pole Upto 5 poles (Upto 300 mtrs.)
b) For those who have applied and Paid the charges
but are availing electric supply illegally:
Connections to be released immediately (within 3 months ) after payment of
i. Normal Service Connection Charges as per Conditions of Supply,
Plus
ii. Infrastructure charges of -
a) Above 5 HP & upto 10 HP : Rs.10000/-.
b) Above 10 HP & upto 15 HP : Rs.30000/-.
Plus
iii. Penalty amounting to six month’s bill (as per MERC rates)
Plus
iv. A Voluntary Disclosure fee of -
a) Above 5 HP & upto 7.5 HP : Rs.3000/-.
b) Above 7.5 HP & Up to 10 HP : Rs.4500/-.
c) above 10 HP & upto 12.5 HP : Rs.6000/-.
d) above 12.5 HP & Up to 15 HP : Rs.7500/-.
Plus
v. A payment of Rs. 10,000/- per pole upto five poles (300 mtrs.)
c) For those who have not applied but are availing electric supply illegally:
Connections to be released immediately (within 3 months) after payment of -
i. Normal Service Connection Charges as per Conditions of Supply.
Plus
ii. Infrastructure charges of -
a) Above 5 HP & upto 10 HP : Rs.10000/-.
b) Above 10 HP & upto 15 HP : Rs.30000/-.
Plus
iii. Penalty amounting to six month’s bill (as per MERC rates)
Plus
iv. A Voluntary Disclosure Fee of -
a) Above 5 HP & upt 7.5 HP :Rs. 6,000/-
b) Above 7.5 HP & Up to 10 HP :Rs. 9000/-.
c) Above 10 HP & upto 12.5 HP :Rs.12000/-
d) Above 12.5 HP & Up to 15 HP :Rs.15000/-.
Plus
v. A payment of Rs. 10,000/- per pole upto five poles ( 300 mtrs.)
In all the above cases (Zero pole and other than Zero pole), the Board
has further directed that the connections are to be released only after completion of all other formalities, like submission of Test Report, Payment of Security Deposit, Agreement Fee, Capacitor Testing Fee, Meter Cost etc. As per Board’s Conditions Of Supply & Miscellaneous Charges.
All the Field Officers are instructed to take due note of the provisions of
the “KRISHI VIKAS – III SCHEME” as above and to initiate all such actions, as may be necessary, to ensure success of the scheme.
Executive Director (Comm.)